(a) FHFA acceptance of resolution plan; review for completeness.

(1) After receipt of a resolution plan, FHFA will either acknowledge acceptance of the plan for review or return the resolution plan if FHFA determines that it is incomplete or that substantial additional information is required to facilitate review of the resolution plan.

(2) If FHFA determines that a resolution plan is incomplete or that substantial additional information is necessary to facilitate review of the resolution plan:

(i) FHFA shall provide notice to the Enterprise in writing of the area(s) in which the resolution plan is incomplete or with respect to which additional information is required; and

(ii) Within 30 days after receiving such notice (or such other time period as FHFA may establish in the notice), the Enterprise shall resubmit a complete resolution plan or such additional information as requested to facilitate review of the resolution plan.

(b) FHFA review of complete plan; determination regarding deficient resolution plan.

(1) Following review of a complete resolution plan, FHFA will send a notification to each Enterprise that:

(i) Identifies any deficiencies or shortcomings in the Enterprise's resolution plan (or confirms that no deficiencies or shortcomings were identified);

(ii) Identifies any planned actions or changes set forth by the Enterprise that FHFA agrees could facilitate a rapid and orderly resolution of the Enterprise; and

(iii) Provides any other feedback on the resolution plan (including feedback on timing of actions or changes to be undertaken by the Enterprise). FHFA will send the notification no later than 12 months after accepting a complete plan, unless FHFA determines in its discretion that extenuating circumstances exist that require delay.

(2) For purposes of paragraph (b)(1) of this section, a “deficiency” is an aspect of an Enterprise's resolution plan that FHFA determines presents a weakness that, individually or in conjunction with other aspects, could undermine the feasibility of the Enterprise's resolution plan. A “shortcoming” is a weakness or gap that raises questions about the feasibility of an Enterprise's resolution plan, but does not rise to the level of a deficiency. If a shortcoming is not satisfactorily explained or addressed before or in the submission of the Enterprise's next resolution plan, it may be found to be a deficiency in the Enterprise's next resolution plan. FHFA may identify an aspect of an Enterprise's resolution plan as a deficiency even if such aspect was not identified as a shortcoming in an earlier resolution plan submission.

(c) Resubmission of a resolution plan. Within 90 days of receiving a notice of deficiency, or such shorter or longer period as FHFA may establish by written notice to the Enterprise, an Enterprise shall submit a revised resolution plan to FHFA that addresses all deficiencies identified by FHFA, and that discusses in detail:

(1) Revisions to the plan made by the Enterprise to address the identified deficiencies;

(2) Any changes to the Enterprise's business operations and corporate structure that the Enterprise proposes to undertake to address a deficiency (including a timeline for completing such changes); and

(3) Why the Enterprise believes that the revised resolution plan is feasible and would facilitate a rapid and orderly resolution by FHFA as receiver.