30 CFR Subpart G - Subpart G—Facility Design, Fabrication, and Installation
-
Reports (§§ 285.700 - 285.704)
- § 285.700 What reports must I submit to BSEE before installing facilities described in my approved SAP, COP, or GAP?
- § 285.701 What must I include in my Facility Design Report?
- § 285.702 What must I include in my Fabrication and Installation Report?
- § 285.703 What reports must I submit for project modifications and repairs?
- § 285.704 [Reserved]
-
Certified Verification Agent (§§ 285.705 - 285.714)
- § 285.705 When must I use a Certified Verification Agent (CVA)?
- § 285.706 How do I nominate a CVA for BSEE approval?
- § 285.707 What are the CVA's primary duties for facility design review?
- § 285.708 What are the CVA's or project engineer's primary duties for fabrication and installation review?
- § 285.709 When conducting onsite fabrication inspections, what must the CVA or project engineer verify?
- § 285.710 When conducting onsite installation inspections, what must the CVA or project engineer do?
- § 285.711 [Reserved]
- § 285.712 What are the CVA's or project engineer's reporting requirements?
- § 285.713 What must I do after the CVA or project engineer confirms conformance with the Fabrication and Installation Report on my commercial lease?
- § 285.714 What records relating to SAPs, COPs, and GAPs must I keep?