40 CFR § 35.2032 - Innovative and alternative technologies.
(a) Funding for innovative and alternative technologies. Projects or portions of projects using unit processes or techniques which the Regional Administrator determines to be innovative or alternative technology shall receive increased grants under § 35.2152.
(1) Only funds from the reserve in § 35.2020(c) shall be used to increase these grants.
(2) If the project is an alternative to conventional treatment works for a small community, funds from the reserve in § 35.2020(b) may be used for the 75 percent portion, or any lower Federal share of the grant as determined under § 35.2152.
(b) Cost-effectiveness preference. The Regional Administrator may award grant assistance for a treatment works or portion of a treatment works using innovative or alternative technologies if the total present worth cost of the treatment works for which the grant is to be made does not exceed the total present worth cost of the most cost-effective alternative by more than 15 percent.
(1) Privately-owned individual systems (§ 35.2034) are not eligible for this preference.
(2) If the present worth costs of the innovative or alternative unit processes are 50 percent or less of the present worth cost of the treatment works, the cost-effectiveness preference applies only to the innovative or alternative components.
(c) Modification or replacement of innovative and alternative projects. The Regional Administrator may award grant assistance to fund 100 percent of the allowable costs of the modification or replacement of any project funded with increased grant funding in accordance with paragraph (a) of this section if he determines that:
(1) The innovative or alternative elements of the project have caused the project or significant elements of the complete waste treatment system of which the project is a part to fail to meet project performance standards;
(2) The failure has significantly increased operation and maintenance expenditures for the project or the complete waste treatment system of which the project is a part; or requires significant additional capital expenditures for corrective action;
(3) The failure has occurred prior to two years after initiation of operation of the project; and
(4) The failure is not attributable to negligence on the part of any person.