40 CFR § 72.62 - Draft permit.
(a) After the Administrator receives a complete Acid Rain permit application and any supplemental information, the Administrator will issue a draft permit that incorporates in whole, in part, or with changes or conditions as appropriate, the permit application or deny the source a draft permit.
(b) The draft permit will be based on the information submitted by the designated representative of the affected source and other relevant information.
(c) The Administrator will serve a copy of the draft permit and the statement of basis on the designated representative of the affected source.
(d) The Administrator will provide a 30-day period for public comment, and opportunity to request a public hearing, on the draft permit or denial of a draft permit, in accordance with the public notice required under § 72.65(a)(1)(i) of this part.