40 CFR Appendix Table 2 to Subpart BB of Part 63 - Table 2 to Subpart BB of Part 63—New Source Emission Limits ab
Table 2 to Subpart BB of Part 63—New Source Emission Limits
ab
For the following new sources . . . | You must meet the emission limits for the specified pollutant . . . |
---|---|
Total fluorides | |
Phosphate Fertilizer Process Line ( |
0.0580 lb/ton of equivalent P2O5 feed. |
Granular Triple Superphosphate Process Line | 0.1230 lb/ton of equivalent P2O5 feed. |
GTSP storage building | 5.0 × 10−4 lb/hr/ton of equivalent P2O5 stored. |
a The new source compliance dates are based on date of construction or reconstruction as specified in § 63.622(a).
b During periods of startup and shutdown, for emission limits stated in terms of pounds of pollutant per ton of feed, you are subject to the work practice standards specified in § 63.622(d).