40 CFR Appendix Table 8 to Subpart JJJJJ of Part 63 - Deadlines for Submitting Notifications
Table 8 to Subpart JJJJJ of Part 63—Deadlines for Submitting Notifications
As stated in § 63.8480, you must submit each notification that applies to you according to the following table:
| If you . . . | You must . . . | No later than . . . | As specified in . . . |
|---|---|---|---|
| 1. Start up your affected source before December 28, 2015 | Submit an Initial Notification | June 22, 2016, or no later than 120 days after the source becomes subject to this subpart, whichever is later | § 63.9(b)(2). |
| 2. Start up your new or reconstructed affected source on or after December 28, 2015 | Submit an Initial Notification | 120 calendar days after you become subject to this subpart | § 63.9(b)(2). |
| 3. Are required to conduct a performance test | Submit a notification of intent to conduct a performance test | 60 calendar days before the performance test is scheduled to begin | § 63.7(b)(1). |
| 4. Are required to conduct a compliance demonstration that includes a performance test according to the requirements in Table 4 to this subpart | Submit a Notification of Compliance Status, including the performance test results | 60 calendar days following the completion of the performance test, by the close of business | § 63.9(h) and § 63.10(d)(2). |
| 5. Are required to conduct a compliance demonstration required in Table 5 to this subpart that does not include a performance test ( |
Submit a Notification of Compliance Status | 30 calendar days following the completion of the compliance demonstrations, by the close of business | § 63.9(h). |
| 6. Request to use the routine control device maintenance alternative standard according to § 63.8420(d) | Submit your request | 120 calendar days before the compliance date specified in § 63.8395 |
[80 FR 65520, Oct. 26, 2015, as amended at 85 FR 73914, Nov. 19, 2020]