7 CFR § 1410.52 - Violations.
§ 1410.52 Violations.
(a) If a participant fails to carry out the terms and conditions of a CRP contract, CCC may terminate the CRP contract in whole or in part.
(b) If the CRP contract is terminated in whole or in part by CCC in accordance with paragraph (a) of this section, the participant will:
(1) Forfeit all rights to further payments under such CRP contract for the terminated acres, and refund all payments previously received for the terminated acres, plus interest; and
(2) Pay liquidated damages to CCC in an amount as specified in the contract.