Cal. Code Regs. Tit. 2, § 1859.14 - Priority One Modernization
Priority One modernization projects that have either Phase C approval by the Board prior to November 4, 1998, or have Phase P approval by the Board and DSA plan approval prior to November 4, 1998, may proceed under either (a) or (b). Districts may either:
(a) Receive funding under the provisions of
the LPP; or,
(b) By January 31,
1999, withdraw the Priority One modernization LPP project and submit a new
application for funding under the provisions of the SFP, pursuant to Section
1859.20. The project approval date
under the LPP will be retained for the project approval date under the SFP. If
the project is eligible for further funding under the SFP, the Modernization
Adjusted Grant provided under the SFP will be reduced by any previous
apportionments made under the LPP.
Notes
2. New section refiled 3-31-99 as an emergency; operative 3-31-99 (Register 99, No. 14). A Certificate of Compliance must be transmitted to OAL by 7-29-99 or emergency language will be repealed by operation of law on the following day.
3. New section refiled 7-29-99 as an emergency; operative 7-29-99 (Register 99, No. 31). A Certificate of Compliance must be transmitted to OAL by 11-26-99 or emergency language will be repealed by operation of law on the following day.
4. Certificate of Compliance as to 7-29-99 order transmitted to OAL 8-26-99 and filed 10-8-99 (Register 99, No. 41).
5. Amendment of subsection (b) filed 6-26-2000; operative 6-26-2000 pursuant to Government Code section 11343.4(d) (Register 2000, No. 26).
Note: Authority cited: Section 17070.35, Education Code. Reference: Section 17009.5, Education Code.
2. New section refiled 3-31-99 as an emergency; operative 3-31-99 (Register 99, No. 14). A Certificate of Compliance must be transmitted to OAL by 7-29-99 or emergency language will be repealed by operation of law on the following day.
3. New section refiled 7-29-99 as an emergency; operative 7-29-99 (Register 99, No. 31). A Certificate of Compliance must be transmitted to OAL by 11-26-99 or emergency language will be repealed by operation of law on the following day.
4. Certificate of Compliance as to 7-29-99 order transmitted to OAL 8-26-99 and filed 10-8-99 (Register 99, No. 41).
5. Amendment of subsection (b) filed 6-26-2000; operative 6-26-2000 pursuant to Government Code section 11343.4(d) (Register 2000, No. 26).
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.