Cal. Code Regs. Tit. 20, § 2023 - Data Adequacy Review and Acceptance
(a) Upon the receipt of an application filed
pursuant to this Article, the executive director or a delegatee shall review
all documentation to determine whether the application contains all the
information required by section
2022 and is, therefore, complete.
Except as provided by this section the review of the application for
completeness shall be in accordance with section
1709.
(b) No later than 45 days after receipt of an
application, the commission shall act upon the executive director's
recommendation as to whether the application contains the information required
by section
2022 and is, therefore, complete.
If the commission determines that the application is complete, the application
shall be accepted as of that date and the proceeding for reaching a final
decision within six months shall begin. Based on meeting the information
requirements of section
2022, the application shall be
considered to be an initial showing that there is substantial evidence that the
project will not cause a significant adverse impact on the environment or
electrical system and will comply with all applicable standards, ordinances,
and laws.
(c) If the commission
determines that the application contains all of the information required by
Appendix B to this Chapter, but not all of the additional information required
by section
2022, the application shall be
deemed accepted for purposes of reaching a final decision within 12 months. The
applicant, however, may request an immediate suspension at the time of
acceptance for a 12-month decision to allow for the submittal of additional
information to meet the requirements of section
2022(b)(1) through
(5). If the applicant makes such a request,
the commission shall specify in writing what information is needed to complete
the application for a six-month decision.
(d) If the commission determines that the
application is incomplete with respect to Appendix B to this Chapter, the
application shall not be accepted. The commission shall indicate in writing
those parts of the application that fail to meet the information requirements
and the manner in which they can be made complete.
(e) The applicant may file additional
information and the commission, in accordance with section
1709, shall determine, within 30
days of receipt of the data, whether the information is sufficient to complete
the application. The application shall be eligible for a final decision within
six months from the day the commission determines that the application is
complete pursuant to section
2022.
Notes
2. Certificate of Compliance as to 11-27-2000 order transmitted to OAL 3-21-2001 and filed 4-25-2001 (Register 2001, No. 17).
Note: Authority cited: Sections 25213 and 25218(e), Public Resources Code. Reference: Sections 25522(b) and 25550, Public Resources Code.
2. Certificate of Compliance as to 11-27-2000 order transmitted to OAL 3-21-2001 and filed 4-25-2001 (Register 2001, No. 17).