12 CCR 2516-1-27.450 - TIMELINES AND SELECTION CRITERIA
A. The
grant program application timeline shall be:
1. May 1: Distribution of the grant
application;
2. June 30: Deadline
for final applications;
3. July 31:
Review and approval or disapproval of the applications by the committee and
submittal of the recommendations to the Commission; and,
4. September 1: After considering the
recommendations of the committee, announcement of the grant recipient(s) by the
Commission will be made through a public electronic newsletter or at a regular
or special meeting
B.
Grant Applications will be reviewed and selected according to the following:
1. Completion of all application
requirements;
2. Assurances of
matching funds readily available or committed when required by the
application;
3. Demonstration of
fiscal and programmatic management capability as evidenced by operating
experience, audit or financial review as appropriate, or a plan of grant
management if the agency is newly created;
4. Cost of the project compared to other
projects, including indirect costs not to exceed 20 percent (20%) of the total
budget;
5. A demonstrated community
priority, which the grant proposal addresses;
6. Demonstration of community support as
evidenced by direct community contributions, a volunteer component, and letters
of support from other community agencies; and,
7. The availability of grant funds for the
project.