4 CCR 723-3-3914 - Establishment of Requirements for a Qualifying Facility
(a) Within 25 days after submission of
complete design information by a qualifying facility, a utility shall:
(I) establish written operations requirements
for the qualifying facility so that interconnection with the qualifying
facility will not cause abnormal operation of the utility's protective
equipment; and
(II) inform the
qualifying facility of the existing phase conductors and utility's requirements
for system electrical phase sequence/rotation available to the qualifying
facility and encourage the qualifying facility to use the existing phasing for
the proposed interconnection. The utility shall inform the qualifying facility
that any phase imbalances may affect the safety of the proposed service or
neighboring customer's loads.
(b) In the event that phased loadings of
interconnection cause phase imbalances, the cost of equipment to correct the
imbalances shall be an interconnection cost of the qualifying
facility.