3-4-1
Temporary Closure
(a)
Owners/operators shall notify the Director in writing at least 10 calendar days
prior to placing an AST system in temporary closure, and at that same time
submit records documenting the prior 12 months of monthly visual inspections,
inventory control, ullage records, piping release detection records, and
corrosion protection testing (if applicable) for tanks and piping. In lieu of
submitting these records, the owner/operator may conduct a tightness test of
the tanks and underground piping, and complete a site assessment as required by
the Director, and submit these results with the temporary closure
notification.
(b) Temporarily
closed tanks must be emptied of liquid, rendered vapor free and safeguarded
against trespassing by means of locked gates, fences etc. When an AST system is
temporarily closed, owners/operators must continue the operation, maintenance,
inspection, and testing of corrosion protection in accordance with these
regulations. Because the tanks must be emptied, release detection is not
required.
(c) When an AST system is
temporarily closed, vent lines must be left open and functioning. If the
temporary closure period is 3 months or more, all pumps, manways, ancillary
equipment and lines other than vent lines must be capped and secured, unless an
alternate schedule is approved by the Director.
(d) When an AST system is temporarily closed
for more than 12 months, owners/operators must permanently close the AST system
in accordance with
3-4-2, unless the Director provides
a written extension of the 12-month temporary closure period. Before requesting
this extension, owners/operators must complete a site assessment as required by
the Director.
(e) Owner/operators
shall notify the Director in writing no more than 30 calendar days prior to
placing an AST back in service, and at that same time submit corrosion
protection records (if applicable) for the period of temporary closure, and
documentation of passing tightness tests for the AST conducted within the past
30 calendar days. The owner/operator shall obtain passing tightness tests for
underground lines immediately upon introduction of fuel into the lines and
submit documentation of testing to the Director within 10 calendar
days.
(f) If an owner/operator
operates a facility which has a specific period of time or season during the
year when the tank system is empty, as described in (b) of this section, the
requirements for maintaining corrosion protection and the following
requirements below will apply:
(1) The
owner/operator shall notify the Director that the facility does include
seasonal operation on a form provided by the Director. If this information
changes, the owner/operator shall complete and submit the form to the
Director.
(2) The period may not
exceed 6 consecutive months.
(3)
The owner/operator shall maintain manifest documentation completed during
emptying of the tank.
(4) At the
end of the seasonal period, the owner/operator must conduct one of the
following actions:
(i) Return the tank to
service.
(ii) Place the tank into
proper temporary closure. The owner/operator must notify the Director in
writing within 10 calendar days, submit records according to (a) as applicable
and complete requirements in (c) immediately.
(iii) Permanently close the tank as required
by 3-4-2.
3-4-2
Permanent
Closure
(a) Owners/operators shall
notify the Director in writing at least 10 calendar days prior to placing an
AST system in permanent closure, and at that same time submit records
documenting the prior 12 months of monthly visual inspections, inventory
control, ullage records, piping release detection records, and corrosion
protection testing (if applicable) for tanks and piping.
Exception: Records do not need to be submitted
where they have already been submitted as part of placing the tank into
temporary closure as required by
3-4-1.
(b) Empty and clean the tank by removing all
liquids and accumulated sludges as described in
3-4-5; and
(c) Clean out and plug both ends of all
connected piping; and
(d) Remove
all dispensers; and
(e) Render all
connected loading facilities completely inoperative; and
(f) Safeguard the AST system from trespassing
as described in
3-4-1, or remove the tanks from the
facility; and
3-4-3
Change in Service
(a) Continued
use of an AST system to store a substance other than a regulated substance is
considered a change-in-service. Before a change-in-service, owners/operators
must empty and clean the tank, connected piping, and any other equipment that
previously contained a regulated substance as described in
3-4-5; then notify the Director in
writing of the change of service.
3-4-4
Site Assessment
(a) Before an extension to temporary closure,
permanent closure or a change-in-service is completed, or upon request by the
Director for previously closed sites, owners/operators must measure for the
presence of a release where contamination is most likely to be present at the
site. In selecting sample types, sample locations, and measurement methods,
owners/operators must consider the method of closure, the nature of the stored
substance, the depth to groundwater, and other factors appropriate for
identifying the presence of a release.
(1) For
assessments when the tank system is removed during permanent closure, the
owner/operator must collect soil samples from beneath each tank, beneath each
dispenser island, beneath areas of piping, and beneath any loading
racks.
(2) For assessments when the
tank system is left in-place during permanent closure, prior to placing the
tank into temporary closure, or when there is a change-in-service, the
owner/operator shall collect samples of the type and at locations as specified
by the Director. Samples collected at all sites must be analyzed for individual
chemicals of concern (COC) as described in 5-2.
(b) If contaminated soils, contaminated
groundwater, LNAPL, or vapor is discovered, owners/operators must report a
release in accordance with Article 4.
(c) If the tank closure assessment does not
identify a release, the owner/operator must submit documentation of the
assessment to the Director within 30 calendar days of the tank closure.
[Note 1: Permanently closed or non-regulated ASTs may be
returned to active regulated substance service only after meeting the
reinstallation rules described in
3-2-3(d).]
[Note 2: These closure rules are the minimum required in
Colorado; they do not preempt local fire district rules, local building codes,
or local zoning rules. In fire districts where the Uniform Fire Code is in
effect, the fire district may require that temporarily closed ASTs be removed
or demolished.]
[Note 3: The following procedures may be used to comply
with 3-4:
(A) American Petroleum
Institute Standard 2015, Requirements for Safe Entry and Cleaning of Petroleum
Storage Tanks;
(B) National
Institute for Occupational Safety and Health "Criteria for a
Recommended Standard...Working in Confined Space" may be used as
guidance for conducting safe closures.]
3-4-5
Waste Handling
(a) All liquids and accumulated sludges must
be removed and disposed of according to the rules adopted pursuant to the Solid
Waste Disposal Regulations and the Colorado Hazardous Waste Regulations adopted
by the Colorado Department of Public Health and Environment.
Notes
7 CCR 1101-14-3-4
37
CR 18, September 25, 2014, effective
10/15/2014
39
CR 18, September 25, 2016, effective
1/1/2017
40
CR 05, March 10, 2017, effective
5/1/2017
40
CR 07, April 10, 2017, effective
5/1/2017
41
CR 07, April 10, 2018, effective
5/1/2018
42
CR 04, February 25, 2019, effective
3/17/2019