7 CCR 1101-14-9-5 - Eligible Costs and Reimbursement
(a)
Costs associated with eligible activities completed during the application
process and subsequent project site assessment, characterization and cleanup
will be reimbursed.
(b) In general,
project costs shall not exceed the current Reasonable Cost Guideline unit
rates.
(c) Requests for
reimbursement must include the following:
(1)
Documentation of the work performed per project work plan.
(2) Proof of payment for all invoices
submitted for reimbursement.
(3)
Affidavit of work performed, with regards to services, material, and equipment
procured by the applicant.
(d) Reimbursement of Level III cleanup costs
shall be contingent upon completion of project milestones in the approved
cleanup work plan.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.