7 CCR 1101-14-9-5 - Eligible Costs and Reimbursement

(a) Costs associated with eligible activities completed during the application process and subsequent project site assessment, characterization and cleanup will be reimbursed.
(b) In general, project costs shall not exceed the current Reasonable Cost Guideline unit rates.
(c) Requests for reimbursement must include the following:
(1) Documentation of the work performed per project work plan.
(2) Proof of payment for all invoices submitted for reimbursement.
(3) Affidavit of work performed, with regards to services, material, and equipment procured by the applicant.
(d) Reimbursement of Level III cleanup costs shall be contingent upon completion of project milestones in the approved cleanup work plan.

Notes

7 CCR 1101-14-9-5
37 CR 18, September 25, 2014, effective 10/15/2014 39 CR 18, September 25, 2016, effective 1/1/2017 40 CR 05, March 10, 2017, effective 5/1/2017 40 CR 07, April 10, 2017, effective 5/1/2017 41 CR 07, April 10, 2018, effective 5/1/2018 42 CR 04, February 25, 2019, effective 3/17/2019

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.