7 CCR 1103-6-4 - Prevailing Wage Act: Contractor Payment Obligations

4.1 A contractor or subcontractor is required to pay all laborers, mechanics, and other construction workers all wages owed under the Prevailing Wage Act, C.R.S. ยง 24-92-202, no less frequently than once every seven calendar days (not workdays), regardless of any contractual relationship which may be alleged to exist between the contractor or subcontractor and such employees.
4.2 A contractor or subcontractor may discharge its minimum obligation for the payment of wages as contained in a wage determination by paying all employees the full amount unconditionally and at least once per week, the prevailing wage as defined in Rule 2.13.
4.3 An employee performing multiple positions with differing prevailing wage rates or classifications must be paid the appropriate wages on the wage determination for the classification(s) of work actually performed, without regard to skill.

Notes

7 CCR 1103-6-4
40 CR 15, August 10, 2017, effective 9/1/2017 45 CR 23, December 10, 2022, effective 1/1/2023 46 CR 23, December 10, 2023, effective 1/1/2024

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.