Conn. Agencies Regs. § 16-50v-1a - Regulation of fees
(a) All application
filing fees required by this section shall be paid to the Council at the time
an application, amendment to an application, petition, statement of intent,
modification of an existing facility, exempt modification, tower share, notice
of exemption, or appeal is filed with the Council. Assessments shall be made on
the applicant, petitioner, or appellant during any proceeding, or thereafter
for all administrative, consulting, hearing, field inspections, and Development
and Management Plan oversight expenses incurred by the Council and staff in
excess of any filing fees paid pursuant to this section. The amount of any fees
or assessments paid pursuant to this section in excess of actual costs incurred
by the Council and staff, including consultant expenses, in connection with any
proceeding shall be refunded to the applicant, petitioner, or appellant not
later than 180 days after the Council's decision in the matter.
(b) The fee for each application for a
certificate for a facility described in subdivisions (1) to (6), inclusive, of
subsection (a) of Section
16-50i of
the Connecticut General Statutes shall be as follows:
Estimated construction cost |
Fee |
|
Up to |
$5,000,000 |
05% or $1,250.00, whichever is greater |
Above |
$5,000,000 |
.1% or $25,250.00, whichever is less. |
If an application for a certificate for a facility is incorporated in an application for a certificate for any other facility, the fee shall be calculated from the total cost of all such facilities.
(c) The filing fee for an
application for an amendment to a certificate, for modification of any existing
facility defined in Section
16-50i of
the Connecticut General Statutes, for an appeal pursuant to Section
16-50x(d)
of the Connecticut General Statutes, for an exempt modification pursuant to
Sections
16-50j-57
and
16-50j-72
of the Regulations of Connecticut State Agencies, for a tower share pursuant to
Section
16-50aa
of the Connecticut General Statutes or for a petition for declaratory ruling or
advisory ruling pursuant to Section
16-50j-38
of the Regulations of Connecticut State Agencies shall be $625.00. If a hearing
is scheduled for any of the foregoing actions, the Council may assess an
applicant or petitioner during the proceeding and thereafter for all expenses
of the Council and staff in connection with the review, hearing and decision of
a matter.
(d) The filing fee for a
statement of intent to acquire real property pursuant to Section
16-50z(a)
of the Connecticut General Statutes shall be $100.00.
(e) The expenses incurred for a Council or
staff field inspection of a certified construction project, of a project for
which a petition for declaratory ruling was filed, or for a statement of intent
to acquire real property shall be billed quarterly to the applicant, petitioner
or filer, and shall in no event exceed $500.00 per review.