Conn. Agencies Regs. § 22a-209-16 - Fees for transfer of a permit to construct or a permit to operate a solid waste facility

(a) Authority. This section is adopted under the authority of subdivision (a) (10) of Section 22a-6 of the General Statutes and Section 22a-208a of the General Statutes.
(b) Transfer fee.
(1) The fee for transfer of a permit to construct or operate a solid waste facility shall be $500.00. The fee shall be submitted simultaneously with the request for transfer, and the permit shall not be transferred prior to payment of the fee and approval of the transfer by the Commissioner, as required by Section 22a-209-4 of the Regulations of Connecticut State Agencies. The fee provided in this section shall be non-refundable.
(2) Within thirty (30) days after issuance of notice from the Commissioner that the actual cost of reviewing and acting on a request has substantially exceeded the amount of the fee as specified in this section, the applicant shall submit the difference between the fee which it has paid and the actual costs to the Commissioner.
(3) The transfer fee shall be paid by certified check or money order payable to the Department of Environmental Protection. The certified check or money order shall state on its face, "Solid Waste Transfer Fee."