Ga. Comp. R. & Regs. R. 110-2-6-.03 - In-Plant Inspections of Manufacturing Facilities and Products

The approved inspection agency shall conduct a thorough inspection of all manufacturing facilities prior to the submission of the application of a manufacturer applying for state approval. The results of this inspection shall be reported to the Department along with the initial application for approval. Thereafter, the agency shall conduct announced and unannounced inspections at the manufacturing site to review any or all aspects of the manufacturer's production and quality control procedures. Changes in the manufacturer's quality control or responsible personnel shall be promptly reported to the Commissioner. The inspection agency shall make a complete inspection of at least one unit through all the operations of manufacture to assure that the manufacturer has the capabilities to produce units in compliance with their approved design and/or the appropriate codes. Thereafter, to determine if the inplant quality control program is working as set forth in manufacturer's approved quality control manual, inspection of every visible aspect of every building or component shall be made at least at one point during the manufacturing process.

Notes

Ga. Comp. R. & Regs. R. 110-2-6-.03
O.C.G.A. Sec. 8-2-113.
Original Rule entitled "Information Requirements" adopted. F. June 20, 1983; eff. July 10, 1983. Repealed: New Rule entitled "In-plant Inspections of New Industrialized Buildings and Components" adopted. F. Sept. 25, 2000; eff. Oct. 15, 2000. Repealed: New Rule entitled "In-Plant Inspections of Manufacturing Facilities and Products" adopted. F. Mar. 4, 2003; eff. Apr. 1, 2003, as specified by the Agency.

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.