Idaho Admin. Code r. 02.04.32.160 - TRANSFER OF PERMITS

01. Transfer Application. A new owner or operator of a facility must submit a transfer application to the director that includes at least the following: (3-15-22)
a. The relevant information required by Subsection 110.03; and (3-15-22)
b. Any change of conditions at the facility resulting from the ownership or operation transfer. (3-15-22)
02. Transfer Application Review. The director will review the transfer application and either approve or deny the application within sixty (60) days of its receipt. (3-15-22)
a. An approved transfer will be considered a minor modification pursuant to Subsection 150.01 as long as there are no major changes of conditions at the facility. Major changes of conditions at the facility are subject to Subsection 150.02. (3-15-22)
b. If the director denies the transfer application, he will set forth the specific reasons for the denial, the steps necessary to meet the requirements for a permit transfer, and the opportunity to request a hearing. (3-15-22)