Ill. Admin. Code tit. 35, § 705.126 - Decision Schedule

For each permit application from a major new HWM facility or major new UIC injection well, the Agency must, no later than the effective date of the application, prepare and mail to the applicant a projected decision schedule. The schedule must specify target dates by which the Agency intends to do the following:

a) Prepare a draft permit pursuant to Subpart C;
b) Give public notice pursuant to Subpart D;
c) Complete the public comment period, including any public hearing pursuant to Subpart E; and
d) Issue a final permit pursuant to Subpart F.

Notes

Ill. Admin. Code tit. 35, § 705.126

Amended at 27 Ill. Reg. 3675, effective February 14, 2003

Amended at 42 Ill. Reg. 21179, effective 11/19/2018

BOARD NOTE: Derived from 40 CFR 124.3(g) (2017).