Ill. Admin. Code tit. 44, § 950.370 - Effect on Current Contracts
Current CDB contracts may be terminated when a contractor is determined to be non-responsible and it is in the public interest to do so, whether or not the non-responsibility has a direct connection with the current contract. Contracts may be terminated with or without further action on the contractor's prequalification.
Notes
Amended at 22 Ill. Reg. 20007, effective November 9, 1998
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.