Rule 312 IAC 25-6 - Performance Standards
- § 312 IAC 25-6-1 - Coal exploration; applicability
- § 312 IAC 25-6-2 - Coal exploration; required documents
- § 312 IAC 25-6-3 - Coal exploration; performance standards
- § 312 IAC 25-6-4 - Coal exploration; permit requirements
- § 312 IAC 25-6-5 - Surface mining; applicability
- § 312 IAC 25-6-6 - Surface mining; signs and markers
- § 312 IAC 25-6-7 - Surface mining; coal recovery
- § 312 IAC 25-6-8 - Surface mining; casing and sealing drilled holes; general requirements
- § 312 IAC 25-6-9 - Surface mining; casing and sealing drilled holes; temporary
- § 312 IAC 25-6-10 - Surface mining; casing and sealing drilled holes; permanent
- § 312 IAC 25-6-11 - Surface mining; topsoil and subsoil
- § 312 IAC 25-6-12 - Hydrologic balance; general requirements
- § 312 IAC 25-6-12.5 - Hydrologic balance; application of ground water quality standards at surface coal mining and reclamation operations permitted under IC 14-34 on which coal extraction, including augering, coal processing, coal processing waste disposal, or spoil deposition, occurs after the effective date of this section, or on which disposal activity subject to IC 13-19-3-3 has occurred and the area is not fully released from the performance bond required by IC 14-34-6
- § 312 IAC 25-6-13 - Surface mining; hydrologic balance; water quality standards and effluent limitations
- § 312 IAC 25-6-14 - Hydrologic balance; diversion; general requirements
- § 312 IAC 25-6-15 - Hydrologic balance; diversions of perennial streams, intermittent streams, miscellaneous flows; supplemental requirements
- § 312 IAC 25-6-16 - Surface mining; hydrologic balance; sediment control measures
- § 312 IAC 25-6-17 - Surface mining; hydrologic balance; siltation structures
- § 312 IAC 25-6-18 - Hydrologic balance; discharge structures
- § 312 IAC 25-6-19 - Hydrologic balance; acid-forming and toxic-forming spoil
- § 312 IAC 25-6-20 - Surface mining; hydrologic balance; permanent and temporary impoundments
- § 312 IAC 25-6-21 - Hydrologic balance; ground water protection
- § 312 IAC 25-6-22 - Hydrologic balance; ground water recharge capacity protection
- § 312 IAC 25-6-23 - Surface mining; hydrologic balance; surface and ground water monitoring
- § 312 IAC 25-6-24 - Hydrologic balance; transfer of wells
- § 312 IAC 25-6-25 - Hydrologic balance; water rights and replacement
- § 312 IAC 25-6-26 - Hydrologic balance; water discharge into underground mine
- § 312 IAC 25-6-27 - Surface mining; hydrologic balance; siltation structures postmining rehabilitation; diversions, impoundments, and treatment facilities
- § 312 IAC 25-6-28 - Surface mining; hydrologic balance; stream buffer zone
- § 312 IAC 25-6-29 - Surface mining; explosives; general requirements
- § 312 IAC 25-6-30 - Surface mining; explosives; preblasting survey
- § 312 IAC 25-6-31 - Surface mining; explosives; publication of blasting schedule
- § 312 IAC 25-6-32 - Surface mining; explosives; blasting operations
- § 312 IAC 25-6-33 - Surface mining; explosives; records of blasting operations
- § 312 IAC 25-6-34 - Surface mining; disposal of excess spoil
- § 312 IAC 25-6-35 - Surface mining; protection of underground mines
- § 312 IAC 25-6-36 - Surface mining; coal mine waste; general requirements
- § 312 IAC 25-6-37 - Surface mining; coal mine waste; refuse piles; site inspection
- § 312 IAC 25-6-38 - Coal processing waste; refuse piles; water control measures
- § 312 IAC 25-6-39 - Surface mining; coal mine waste; refuse piles; construction requirements
- § 312 IAC 25-6-40 - Coal processing waste; burning
- § 312 IAC 25-6-41 - Coal processing waste; return to underground workings
- § 312 IAC 25-6-42 - Disposal of noncoal wastes
- § 312 IAC 25-6-43 - Surface mining; coal mine waste; dams and embankments; general requirements
- § 312 IAC 25-6-44 - Coal processing waste; dams and embankments; site preparation
- § 312 IAC 25-6-45 - Surface mining; coal mine waste; dams and embankments; design and construction
- § 312 IAC 25-6-46 - Surface mining; protection of fish, wildlife, and related environmental values
- § 312 IAC 25-6-47 - Surface mining; slides and other damage
- § 312 IAC 25-6-48 - Surface mining; contemporaneous reclamation
- § 312 IAC 25-6-49 - Surface mining; backfilling and grading; timing limitations
- § 312 IAC 25-6-50 - Surface mining; backfilling and grading; general requirements
- § 312 IAC 25-6-51 - Surface mining; stabilization of surface areas
- § 312 IAC 25-6-52 - Surface mining; backfilling and grading; thick overburden
- § 312 IAC 25-6-53 - Surface mining; backfilling and grading; previously mined areas
- § 312 IAC 25-6-54 - Surface mining; revegetation; general requirements
- § 312 IAC 25-6-55 - Surface mining; revegetation; use of introduced species
- § 312 IAC 25-6-56 - Surface mining; revegetation; timing
- § 312 IAC 25-6-57 - Surface mining; revegetation; mulching and other soil stabilizing practices
- § 312 IAC 25-6-58 - Surface mining; revegetation; grazing
- § 312 IAC 25-6-59 - Surface mining; revegetation; standards for success for nonprime farmland
- § 312 IAC 25-6-60 - Revegetation; sampling techniques for nonprime farmland
- § 312 IAC 25-6-61 - Revegetation; statistical methodology
- § 312 IAC 25-6-62 - Cessation of operations; temporary
- § 312 IAC 25-6-63 - Cessation of operations; permanent
- § 312 IAC 25-6-64 - Postmining land use
- § 312 IAC 25-6-65 - Surface mining; roads
- § 312 IAC 25-6-66 - Surface mining; primary roads
- § 312 IAC 25-6-67 - Surface mining; other transportation facilities
- § 312 IAC 25-6-68 - Support facilities and utility installations
- § 312 IAC 25-6-69 - Surveyor corner markers; replacement
- § 312 IAC 25-6-70 - Underground mining; applicability
- § 312 IAC 25-6-71 - Underground mining; signs and markers
- § 312 IAC 25-6-72 - Underground mining; casing and sealing exposed underground openings; general requirements
- § 312 IAC 25-6-73 - Underground mining; casing and sealing exposed underground openings; temporary
- § 312 IAC 25-6-74 - Underground mining; casing and sealing exposed underground openings; permanent
- § 312 IAC 25-6-75 - Underground mining; topsoil and subsoil
- § 312 IAC 25-6-76 - Underground mining; hydrologic balance; general requirements
- § 312 IAC 25-6-76.5 - Underground mining; hydrologic balance; application of ground water quality standards at underground coal mining and reclamation operations permitted under IC 14-34 on which coal extraction, coal processing, coal processing waste disposal, or underground development waste and spoil deposition occurs after the effective date of this section, or on which disposal activity subject to IC 13-19-3-3 has occurred and the area is not fully released from the performance bond required by IC 14-34-6
- § 312 IAC 25-6-77 - Underground mining; hydrologic balance; water quality standards and effluent limitations
- § 312 IAC 25-6-78 - Underground mining; hydrologic balance; diversions; general requirements
- § 312 IAC 25-6-79 - Underground mining; hydrologic balance; diversions of perennial streams, intermittent streams with a watershed greater than one square mile, miscellaneous flows; stream channel diversions; supplemental requirements
- § 312 IAC 25-6-80 - Underground mining; hydrologic balance; sediment control measures
- § 312 IAC 25-6-81 - Underground mining; hydrologic balance; siltation structures
- § 312 IAC 25-6-82 - Underground mining; hydrologic balance; discharge structures
- § 312 IAC 25-6-83 - Underground mining; hydrologic balance; acid-forming and toxic-forming materials
- § 312 IAC 25-6-84 - Underground mining; hydrologic balance; permanent and temporary impoundments
- § 312 IAC 25-6-85 - Underground mining; hydrologic balance; underground mine entry and access discharges
- § 312 IAC 25-6-86 - Underground mining; hydrologic balance; surface and ground water monitoring
- § 312 IAC 25-6-87 - Underground mining; hydrologic balance; transfer of wells
- § 312 IAC 25-6-88 - Underground mining; hydrologic balance; water rights and replacement
- § 312 IAC 25-6-89 - Underground mining; hydrologic balance; discharge of water into underground mine
- § 312 IAC 25-6-90 - Underground mining; hydrologic balance; postmining rehabilitation of siltation structures, diversions, impoundments, and treatment facilities
- § 312 IAC 25-6-91 - Underground mining; hydrologic balance; stream buffer zones
- § 312 IAC 25-6-92 - Underground mining; coal recovery
- § 312 IAC 25-6-93 - Underground mining; explosives; general requirements
- § 312 IAC 25-6-94 - Underground mining; explosives; preblasting survey
- § 312 IAC 25-6-95 - Underground mining; explosives; publication of blasting schedule
- § 312 IAC 25-6-96 - Underground mining; explosives; surface blasting operations
- § 312 IAC 25-6-97 - Underground mining; explosives; records of blasting operations
- § 312 IAC 25-6-98 - Underground mining; disposal of underground development waste and excess spoil
- § 312 IAC 25-6-99 - Underground mining; coal mine waste; general requirements
- § 312 IAC 25-6-100 - Underground mining; coal mine waste; refuse piles; site inspection
- § 312 IAC 25-6-101 - Underground mining; coal mine waste banks; refuse piles; water control measures
- § 312 IAC 25-6-102 - Underground mining; coal mine waste; refuse piles; construction requirements
- § 312 IAC 25-6-103 - Underground mining; coal processing waste; burning
- § 312 IAC 25-6-104 - Underground mining; coal processing waste; return to underground workings
- § 312 IAC 25-6-105 - Underground mining; disposal of noncoal wastes
- § 312 IAC 25-6-106 - Underground mining; coal mine waste; refuse piles; dams and embankments; general requirements
- § 312 IAC 25-6-107 - Underground mining; coal processing waste; dams and embankments; site preparation
- § 312 IAC 25-6-108 - Underground mining; coal mine waste; refuse piles; dams and embankments; design and construction
- § 312 IAC 25-6-109 - Underground mining; protection of fish, wildlife, and related environmental values
- § 312 IAC 25-6-110 - Underground mining; slides and other damage
- § 312 IAC 25-6-111 - Underground mining; contemporaneous reclamation
- § 312 IAC 25-6-112 - Underground mining; backfilling and grading; general requirements
- § 312 IAC 25-6-113 - Underground mining; stabilization of surface areas
- § 312 IAC 25-6-114 - Underground mining; backfilling and grading; previously mined areas
- § 312 IAC 25-6-115 - Underground mining; revegetation; general requirements
- § 312 IAC 25-6-116 - Underground mining; revegetation; use of introduced species
- § 312 IAC 25-6-117 - Underground mining; revegetation; timing
- § 312 IAC 25-6-118 - Underground mining; revegetation; mulching and soil stabilizing
- § 312 IAC 25-6-119 - Underground mining; revegetation; grazing
- § 312 IAC 25-6-120 - Underground mining; revegetation; standards for success for nonprime farmland
- § 312 IAC 25-6-121 - Underground mining; revegetation; sampling techniques
- § 312 IAC 25-6-122 - Underground mining; revegetation; statistical methodology
- § 312 IAC 25-6-123 - Underground mining; subsidence control; general requirements
- § 312 IAC 25-6-124 - Underground mining; subsidence control; public notice
- § 312 IAC 25-6-125 - Underground mining; subsidence control; buffer zones
- § 312 IAC 25-6-126 - Underground mining; cessation of operation; temporary
- § 312 IAC 25-6-127 - Underground mining; cessation of operation; permanent
- § 312 IAC 25-6-128 - Underground mining; postmining land use
- § 312 IAC 25-6-129 - Underground mining; roads
- § 312 IAC 25-6-130 - Underground mining; primary roads
- § 312 IAC 25-6-131 - Underground mining; other transportation facilities
- § 312 IAC 25-6-132 - Underground mining; support facilities and utility installations
- § 312 IAC 25-6-133 - Underground mining; surveyor corner markers; replacement
- § 312 IAC 25-6-134 - Concurrent surface and underground mining; applicability
- § 312 IAC 25-6-135 - Concurrent surface and underground mining; compliance with variance terms
- § 312 IAC 25-6-136 - Concurrent surface and underground mining; additional performance standards
- § 312 IAC 25-6-137 - Auger mining; special standards; applicability
- § 312 IAC 25-6-138 - Auger mining; special standards; additional performance standards
- § 312 IAC 25-6-139 - Prime farmland; special performance standards; scope, purpose, and applicability
- § 312 IAC 25-6-140 - Prime farmland; special performance standards; United States Soil Conservation Service criteria
- § 312 IAC 25-6-141 - Prime farmland; special performance standards; soil removal and stockpiling
- § 312 IAC 25-6-142 - Prime farmland; special performance standards; soil replacement
- § 312 IAC 25-6-143 - Prime farmland; special performance standards; revegetation and restoration of soil productivity
- § 312 IAC 25-6-144 - Steep slopes; backfilling and grading
- § 312 IAC 25-6-145 - Coal preparation plants not within permit area for a mine; permits; applicability
- § 312 IAC 25-6-146 - Coal preparation plants not within a permit area for a mine; special performance standards
- § 312 IAC 25-6-147 - In situ processing; special performance standards
- § 312 IAC 25-6-148 - In situ processing; monitoring
- § 312 IAC 25-6-149 - Annual report