Iowa Admin. Code r. 199-24.11 - Site preparation
(1) In the
event no certificate has been issued after 90 days from the commencement of the
hearing, the commission may permit the applicant to begin work to prepare the
site for construction of the facility. Any activities conducted pursuant to
this rule shall have no probative value to the commission's decision concerning
the actual issuance of a certificate.
(2) In the event the commission denies an
application for a certificate or an amendment to a certificate, applicants who
have received permission to begin site preparation, pursuant to 24.11(1), shall
restore the site, in accordance with the commission order denying the
application.