Iowa Admin. Code r. 721-45.7 - Forfeiture and cancellation of mechanics' liens
(1)
Demand for acknowledgment of
satisfaction of claim.
a. When a
mechanic's lien is satisfied by payment of the claim, the claimant may post
acknowledgment of that satisfaction on the MNLR.
b. If the claimant fails to acknowledge
satisfaction by posting, the owner, general contractor or owner-builder may
personally serve the claimant with a written demand that the claimant post the
acknowledgment of satisfaction on the MNLR. If the claimant fails to post the
acknowledgment of satisfaction within 30 days of when the demand is served, the
mechanic's lien is forfeited and canceled upon the posting of a copy of the
demand and the posting of endorsed proofs of service.
(2)
Posting of demand to commence
action to enforce the lien. The owner may serve a written demand on
the claimant demanding that the claimant commence action to enforce the lien.
If the claimant fails to commence action to enforce the lien within 30 days of
receipt of the written demand, the owner may post a copy of the demand to
commence action and the endorsed proofs of service. Completion of these
requirements provides constructive notice to all parties that the lien has been
canceled.
(3)
'Notice to
both parties. At the time that a demand is posted on the MNLR, the
administrator shall mail a date- and time-stamped copy of the demand to both
parties.