La. Admin. Code tit. 70, § II-1915 - Pre-Installation CCTV Inspection
A. It
shall be the responsibility of the permittee to televise the sewer pipe
immediately before the pipe bursting/crushing to assure that the existing pipe
conditions are acceptable for pipe bursting/crushing.
B. If Pre-Installation CCTV inspection
reveals a sag in the existing sewer that is greater than one-half the diameter
of the existing pipe, it shall be the responsibility of permittee to install
the replacement pipe so that the result is an acceptable grade without the sag.
The permittee shall take the necessary measures to eliminate these sags by one
of the following measures:
1. pipe
replacement
2. digging a sag
elimination pit and bringing the bottom of the pipe trench to a uniform grade
in line with the existing pipe invert, or
3. by other measures approved by the
DOTD.
C. Eliminating
sags under the roadway will not be allowed if it necessitates open cutting the
roadway.