06-096 C.M.R. ch. 342, § 8 - Pre-application and pre-submission meeting

A pre-application meeting is required prior to submission to the department of a new application for a significant groundwater well pursuant to the NRPA. The applicant must meet the requirements in Section 10 of Rules Concerning the Processing of Applications, 06-096 CMR 2. A pre-submission meeting is required unless waived as provided in 06-096 CMR 2(10)(D).

NOTE: See Rules Concerning the Processing of Applications and Other Administrative Matters, 06-096 CMR 2 for requirements applicable to a Site Law development concerning public information meetings, and pre-application and pre-submission meetings.