The policy of the Board of Environmental Protection is that the storage of tankers or tank vessels in Maine waters is an emergency or temporary situation, therefore the board shall place strict time limits on any approved lay-up.

A. Terms of Permit
(1) The board shall issue a permit for a period not to exceed three (3) months.
(2) This three month period may be renewed five (5) additional times after the initial permit for a maximum total of eighteen (18) months after which the vessel must leave the waters of the State of Maine.

Notes

06-096 C.M.R. ch. 680, § 6

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.