18-554 C.M.R. ch. 60, § 23 - Approval
Summary: This section specifies that written approval is required before a project may proceed.
1.
Approval
A project may proceed to subsequent phases of development only upon written approval by the Bureau or other entity with approval authority over a given building.
Notes
September 18, 2004 - filing 2004-398
NON-SUBSTANTIVE CHANGES:
October 18, 2004
STATUTORY AUTHORITY FOR ENTIRE CHAPTER:
5 M.R.S.A. §1764-A
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.