99- 346 C.M.R. ch. 16 , 346-16 app B - Pre-Application Submission Requirements

Applicants must submit a request for pre-application review and the following information to MaineHousing at least 60 calendar days before the applicable Application deadline.

1. A narrative description of the Project and any Related Development, including, the location, type of housing, total number of units by bedroom size, breakdown of required and/or pledged accessible units by type and location, total number of income-restricted units by bedroom size, proposed affordability, any existing affordability restrictions, any existing or proposed use restrictions, common areas and amenities at the Project, any community service facilities, any commercial space and other unique features of the Project.

2. Conceptual, Diagrammatic Site Plan and Conceptual Floor Plans and Conceptual Building Elevations in accordance with the requirements set forth in MaineHousing's Quality Standards and Procedures Manual.

3. The status of applicable federal, State and local land use approvals for the Project and any Related Development, and any site, subdivision and other plans for the Project and any Related Development that have been prepared for submission or have been submitted to applicable municipal, state and federal governmental entities.

4. Details about the parking for the Project, including the number, type and location of all on-site parking and off-site parking and the terms and conditions thereof.

5. An explanation and all supporting documentation for any exceptions from the requirement to provide a community room, laundry facilities, telemedicine facilities or area activities in accordance with Section 5.J of the QAP.

6. All available information about any known or suspected environmental conditions on the Project site and any Related Development or adjacent sites that may impact the Project site or any Related Development, including any environmental reports. To the extent feasible, identify any and all visible (both on and off-site) fuel oil and propane tanks and include them on the site plan.

7. A capital needs assessment for any existing housing that meets the requirements in Section 5. D. and Appendix C.

8. A conceptual construction estimate(s) prepared by a qualified general contractor or third-party estimator for the Project and any Related Development, including trade breakdowns in the form of a schedule of values and a reasonable estimating contingency, if applicable, with sufficient detail to demonstrate expected construction-related costs. All exclusions and qualifications, if any, must be clearly stated in the estimate. The estimate is to be the basis of the hard cost line items contained in the project underwriting without exception.

9. A projected development and operating budget(s) for the Project and any Related Development which must be submitted electronically in the format prescribed by MaineHousing.