Md. Code Regs. 20.62.02.09 - Utility Cost Recovery

A. An electric company shall receive full and timely cost recovery of program credit costs.
B. An electric company may not establish a separate surcharge, fee, or rate for recovery of any program costs, including credit and administrative costs.
C. An electric company may include program credit costs in existing rate adjustments for distribution rates or as a revenue or cost component for transmission or commodity rates as accepted by the Commission.

Notes

Md. Code Regs. 20.62.02.09
Regulations .09 adopted effective 43:14 Md. R. 781, eff. 7/18/2016

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.