Md. Code Regs. 20.79.04.01 - Purpose and Justification

A. An application for a proposed transmission line or modification to an existing transmission line shall include:
(1) An explanation of the need for the project in meeting demands for service;
(2) A description of the effect of the project on system stability and reliability;
(3) A description of the consequences if the project is delayed or not approved;
(4) An explanation of the cost effectiveness of the project, including an estimate of capital cost and annual operating cost; and
(5) A description of the impact of the project on the economies of the State.
B. If requested by the Commission, an application for a proposed transmission line shall include a plan as defined under COMAR 20.79.01.02B.

Notes

Md. Code Regs. 20.79.04.01
Regulation .01 amended effective November 8, 2004 (31:22 Md. R. 1598)