A. This regulation applies to the owner or
operator of a:
(1) Surface impoundment that is
subject to the requirements of Regulation .11D(4) or (5) of this
chapter;
(2) Waste pile that is
subject to the requirements of Regulation .12D(1) or (2) of this chapter;
or
(3) Landfill unit that is
subject to the requirements of Regulation .14B(3) or (4) of this
chapter.
B. The owner or
operator of a land disposal unit identified in §A of this regulation shall:
(1) Incorporate into facility operations a
construction quality assurance program that:
(a) Ensures that the constructed unit meets
or exceeds all design criteria and specifications in the facility permit;
and
(b) Has been developed and
implemented under the direction of a construction quality assurance officer who
is a registered professional engineer; and
(2) As qualified by §C of this regulation,
ensure that the construction quality assurance program meets the requirements
of 40 CFR §
264.19(a)(2), (b), and
(c).
C. In complying with the requirements of
40 CFR §
264.19, the owner or operator shall:
(1) Substitute "Secretary" for "Regional
Administrator"; and
(2) Substitute
the corresponding regulation or regulations identified in COMAR
26.13.01.05B(2)
for the provisions in other sections of the Code of Federal Regulations that
are cited within 40 CFR §
264.19.
D. Certification. The owner or operator of a
unit identified in §A if this regulation:
(1)
May not accept waste into the unit until the owner or operator has submitted to
the Department by certified mail or hand delivery a certification signed by the
construction quality assurance officer that the:
(a) Approved construction quality assurance
plan has been successfully carried out;
(b) Unit meets the requirements of:
(i) Regulation .11D(4) or (5) of this
chapter;
(ii) Regulation .12D(1) or
(2) of this chapter; or
(iii)
Regulation . 14B(3) or (4) of this chapter; and
(c) Procedure of COMAR
26.13.07.15C(2) and
(3) regarding inspection by the Department
has been carried out; and
(2) Shall furnish documentation supporting
the construction quality assurance officer's certification to the Department
upon request.