310 CMR 4.10 - Appendix: Schedules for Timely Action and Permit Application Fees

(1) General.
(a) Unless otherwise specifically provided in 310 CMR 4.10, timely action schedules and application fees in effect on the day the application is filed, shall apply to that application.
(b) The following permit category sets as established in 310 CMR 4.10 effective January 1, 1991 are consolidated effective July 1, 1992: WP 06 and 07, WP 08 and 09, WP 21 and 22, WP 23 and 24, WP 35 and 36; IW 03 and 04, IW 05, 06 and 07, IW 08 and 09, IW 10 and 11, IW 13 and 14, IW 12 and 15, IW 16 and 17, IW 18 and 19, IW 21 and 22.

For reviews pending on July 1, 1992 in categories WP 06, 08, 21, 23, 35, IW 03, 05, 06, 08, 10, 12, 14, 16, 18, 21, the applicant may upon issuance of that permit, file an application in the consolidated category. The consolidated category timely action schedule and permit application fee amount for such application shall be that which would have been applicable prior to July 1, 1992 for the remaining permits of the set.

Permit categories WS13 and 14 and WS15 and 16 are consolidated effective July 1, 1993. For reviews pending on July 1, 1993 in WS 13 or 15, the applicant may upon issuance of that permit, file an application in the consolidated category. The schedule and fee amount for such application shall be that which would have been applicable prior to July 1, 1993 for the remaining permit of the set.

(c) State Agency Applicants. For state agency applicants, any permit application fee of $100 or less shall be waived as representing an administrative expense associated with transfer of funds between state agencies that is a substantial portion of the fee. Notwithstanding the prior sentence, fees pursuant to M.G.L. c. 21E shall be required of state agency applicants.
(d) Refund. The Department shall notify applicants and allow submission of an application for a refund within 30 days for those permit applications filed on January 1, 1992 through June 30, 1992 with a review pending on July 1, 1992, and for which a reduced fee may have been available if the application had been filed on or after July 1, 1992. The amount of the refund, if any, shall be the difference between the old and new fee. 310 CMR 4.10(1)(d) shall not apply to individual rule and alternative schedule projects.
(e) Index and Key

BUREAU OF AIR AND WASTE

(2) Air Quality Control.

Plan Approvals.

(a) (AQ01) Permits for air quality, plan approvals.
1. Category: limited plan approvals.
2. Description: permit to construct, substantially reconstruct or alter any facility required to obtain a limited plan approval pursuant to 310 CMR 7.02(4): Limited Plan Application (LPA).
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $645.
(b) (AQ02) Permits for air quality, plan approvals.
1. Category: non-major comprehensive plan approval.
2. Description: effective March 24, 2017 Permit to construct, substantially reconstruct or alter a facility pursuant to 310 CMR 7.02(5): Comprehensive Plan Application (CPA) that is not listed in 310 CMR 4.10(2)(c).
3. Schedule for timely action: for projects for which applications are filed and fees received on or after May 1, 2020,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 72 days of the close of the period for public comment, including any public hearing, the Department shall complete a public comment review.
4. Permit application fee: $2,370.
(c) (AQ03) Permits for air quality, plan approvals.
1. Category: major comprehensive plan approval.
2. Description:
a. Effective March 24, 2017 Permit to construct, substantially reconstruct or alter a facility pursuant to 310 CMR 7.02(5): Comprehensive Plan Application (CPA) where the construction, substantial reconstruction or alteration has potential emissions greater than or equal to 100 tons per year of any criteria air contaminant, excluding products of combustion, or;
b. (Reserved);
c. Permit subject to 310 CMR 7.02(5): Comprehensive Plan Application (CPA) and 310 CMR 7.00: Appendix A (Non-attainment Review) or;
d. (Reserved)
e. Permit to construct, substantially reconstruct or alter a fuel utilization facility where the portion being constructed, substantially reconstructed or altered has an energy input capacity equal to or greater than the threshold requirements of 310 CMR 7.02(5)(a)2.: Fuel Utilization Emission Units, and will result in increased potential emissions greater than or equal to 100 tons per year of any criteria air contaminant; or f. Permit subject to 310 CMR 7.02(5): Comprehensive Plan Application (CPA) and 40 CFR 52.21 (Prevention of Significant Deterioration); or g. A permit to construct an incinerator having a waste capacity greater than 2000 pounds per hour of waste.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after May 1, 2020,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 128 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 128 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 72 days of the close of the period for public comment, including any public hearing, the Department shall complete a public comment review.
4. Permit application fee: $24,305.
(c)
(1) (AQ33) Permits for Air Quality: Consolidated Plan Approval.
1. Category: consolidated plan approval.
2. Description: consolidated plan for a facility's applicable requirements pursuant to 310 CMR 7.02(12): U Consolidation of Applicable Requirements.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 30 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 90 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 60 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $1,500 plus $150 per requirement consolidated for each emission unit up to a maximum total fee of $5,000.

Emission Control Plans.

(d) (AQ08) Permits for Emission Control Plans.
1. Category: emission control plans.
2. Description: emission control plan required pursuant to 310 CMR 7.18: U Volatile and Halogenated Organic Compounds or 310 CMR 7.19: U Reasonably Available Control Technology (RACT) for Sources of Oxides of Nitrogen (NOX).
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. where compliance can be achieved by meeting emission limitations specifically articulated in 310 CMR 7.00: Air Pollution Control, including through the use of emissions averaging or trading as described in 310 CMR 7.00: Appendix B
(i) Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
(ii) Within 63 days of making a determination of administrative completeness, the Department shall complete a technical review.
(iii) The permit applicant may remedy identified deficiencies within 45 days of the Department's statement identifying deficiencies, if any.
(iv) Within 63 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
(v) Within 30 days of the close of the period for public comment, including any public hearing, the Department shall complete a public comment review.
b. Where approval is required by the US Environmental Protection Agency as a single source SIP (State Implementation Plan) revision to demonstrate compliance with federally mandated RACT because compliance cannot be achieved by meeting emission limitations specifically articulated in 310 CMR 7.00: Air Pollution Control, or to satisfy 310 CMR 7.18(17): Reasonable Technology or 7.19(12): Miscellaneous RACT,
(i) Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
(ii) Within 128 days of making a determination of administrative completeness, the Department shall complete a technical review.
(iii) The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
(iv) Within 128 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
(v) Within 72 days of the close of the period for public comment, including any public hearing, the Department shall complete a public comment review.
4. Permit application fee:
a. Permits meeting the description of 310 CMR 4.10(2)(d)3.a.: $1,880.
b. Permits meeting the description of 310 CMR 4.10(2)(d)3.b.: $22,310.
(d)
(1) (AQ22) - Permits for Emission Control Plan for Municipal Waste Combustors.
1. Category: Municipal Waste Combustor emission control plan.
2. Description: Emission Control Plan required pursuant to 310 CMR 7.08(2): Municipal Waste Combustors for sources constructed prior to 1994.
3. Schedule for timely action: for projects for which application is filed and fee received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy any identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental review.
e. Within 24 days of the close of the period for public comment, the Department will issue or deny the permit.
4. Permit application fee: $8,820.

Restrictions on Potential Emissions.

(e) (AQ09) Permit to restrict potential emissions.
1. Category: permit restrictions or Restricted Emission Status (RES).
2. Description: permit restriction issued to any facility pursuant to 310 CMR 7.02(9): Restricted Emission Status (RES) to restrict potential emissions in order to:
a. allow redesignation for purposes of annual compliance fee for permittees for regulated air contaminants; or
b. lower potential emissions below the Reasonably Available Control Technology (RACT) applicability thresholds for halogenated organic compounds (HOC) (310 CMR 7.18: U Volatile and Halagonated Organic Compounds); or
c. lower federal potential emissions below the Reasonably Available Control Technology (RACT) applicability thresholds for volatile organic compounds (310 CMR 7.18: U Volatile and Halagonated Organic Compounds and 310 CMR 7.00: Appendix C where applicable); or
d. lower federal potential emissions below the Reasonably Available Control Technology (RACT) applicability thresholds for oxides of nitrogen (NO) (310 CMR 7.19: U Reasonable Available Control Technology (RACT) for Sources of Oxides of Nitrogen (NOx and 310 CMR 7.00: Appendix C where applicable); or
e. restrict federal potential emissions of regulated pollutants to eliminate applicability to an otherwise applicable requirement, including but not limited to, 310 CMR 7.00 Appendix C.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review e. Within ten days of the close of the period for public comment, including public hearing, if applicable, the Department will complete a public comment review.
4. Permit application fee: $1,900.

Asbestos and Construction Notifications

(f) (AQ04) Permits for Asbestos.
1. Category: asbestos removal notification.
2. Description: notification submitted to satisfy the requirements of 310 CMR 7.15(6): Notification Requirements for asbestos abatement activity at industrial, commercial and institutional sites and residential property, excluding owner-occupied residential property with four or fewer units.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within ten working days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review. The notification form shall be deemed accepted by the Department, unless the applicant is notified in writing of deficiencies.
b. The permit applicant may remedy identified deficiencies within 30 days of the Department's statement identifying deficiencies, if any.
c. Within ten working days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a final review.
4. Permit application fee: $100.
(g) (AQ05) Permits for Asbestos.
1. Category: asbestos blanket notification.
2. Description: notification submitted of plan for multiple demolition or renovation jobs within a single facility during a period not to exceed one year, where permitted by the Department pursuant to 310 CMR 7.15(6)(j): Facility Blanket Notification.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after May 1, 2020,
a. Within 20 days of receipt of an application and payment of the permit application fee, the Department shall complete a technical review and notify the applicant of any deficiencies.
b. The permit applicant may remedy identified deficiencies within 30 days of the Department's statement identifying deficiencies, if any.
c. Within 20 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee:
a. Asbestos blanket notification application: $200.
b. Asbestos removal notification submitted under an approved asbestos blanket notification: $100.
(h) (AQ06) Construction and Demolition Notification.
1. Category: notification prior to construction or demolition of an industrial, commercial, or institutional building or residential building with 20 or more units, pursuant to 310 CMR 7.09(2).
2. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within ten working days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review and indicate deficiencies, if any, to the applicant.
b. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any. Submission of amended information, except as provided in 310 CMR 4.10, within the 60-day period shall not constitute a new notification.
c. Within ten working days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a final review.
3. Permit application fee: $100.
(h)
(1) (AQ35) Permits for Asbestos.
1. Category: revised asbestos removal notification.
2. Description: the revision of an asbestos removal notification, or an asbestos removal notification submitted under an approved blanket notification, to satisfy the requirements of 310 CMR 7.15(6): Notification Requirements; or a construction and demolition notification submitted to satisfy the requirements of 310 CMR 7.09(2).
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within ten working days of receipt of an application and payment of the permit application fee, the Department will complete an administrative completeness review. The revised notification form shall be deemed accepted by the Department unless the applicant is notified in writing of deficiencies.
b. The permit applicant may remedy identified deficiencies within 30 days of the Department's statement identifying deficiencies, if any.
c. Within ten working days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a final review.
4. Permit application fee: $35.
(h)
(2) (AQ36) Permits for Asbestos.
1. Category: non-traditional asbestos abatement work practice approval.
2. Description: non-traditional asbestos abatement work practice approvals for sites where traditional practices cannot be implemented due to specific circumstances as specified in 310 CMR 7.15(14): Non-traditional Asbestos Abatement Work Practice Approvals.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within ten working days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. The permit applicant may remedy identified deficiencies within 30 days of the Department's statement identifying deficiencies, if any.
c. Within ten working days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a final review.
4. Permit application fee: $600.

Operating Permits

(j)
(4) (AQ14) Permits for Air Quality Control.
1. Category: initial operating permit application for a facility subject to 310 CMR 7.00: Appendix C.
2. Description: operating permit for a facility subject to 310 CMR 7.00: Appendix C.
3. Schedule for timely action: for applications which are filed and fees received on or after March 24, 2017,
a. Within 60 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 180 days of a determination of administrative completeness, the Department shall conduct a technical review.
c. The permit applicant may remedy identified deficiencies within 30 days of the Department's statement identifying deficiencies, if any.
d. Within 180 days of receipt of materials from the applicant, in response to the Department's statement identifying deficiencies, the Department shall conduct a supplemental technical review.
e. Within 45 days of the completion of a public comment period including public hearing, if applicable, the Department shall complete a proposed decision for submission to EPA.
f. Within 45 days of the receipt of EPA final comment on the proposed decision, the Department shall complete a final review.
4. Permit application fee: the amount shall be calculated, in accordance with definitions in 310 CMR 7.00: Air Pollution Control, by adding (AA x $ 9) plus (EC x $ 549) plus (EU x $ 405), but the amount shall not be less than $ 2312; where AA is the Adjusted Actual Emissions tons per year of criteria pollutants for the calendar year prior to the submittal of an application for an operating permit, excluding carbon monoxide, capped at 4000 tons/year per pollutant; and EC is an Emissions Unit with Air Pollution Control Equipment; and EU is an Emissions Unit with no Air Pollution Control Equipment.

Emission Reduction Certification

(l) (AQ18) Permits for Air Quality; Emission Reduction Certification.
1. Category: certification of emission reductions for emission banking and trading pursuant to 310 CMR 7.00: Appendix B.
2. Description: certification of emission reductions which exceed state and federal requirements as Emission Reduction Credits (ERCs).
3. Schedule for timely action: for projects for which applications are filled and fees received on or after March 24, 2017,
a. Within 48 days of receipt of an application and payment of the permit application fee the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, if any, the Department shall complete a supplemental technical review.
e. Within 36 days of the close of the period for public comment, including any public hearing, the Department shall complete public comment review and issue final decision.
4. Permit application fee:

$1,225 greater than or equal to five, but less than ten tons or tpy ERC;

$6,140 greater than or equal to ten, but less than 50 tons or tpy ERC;

$9,215 greater than or equal to 50, but less than 100 tons or tpy ERC; $15,360 greater than or equal to 100, but less than 500 tons or tpy ERC; $18,430 greater than or equal to 500 tons or tpy ERC.

(3) Hazardous Waste.

Hazardous Waste Recycling

(a)
(1) (HW21) Hazardous waste recycling permits.
1. Category: Class A recycling presumptive approval permit/renewal.
2. Description: Class A recycling permit and permit renewals for Class A regulated recyclable material pursuant to 310 CMR 30.221(2) for recycling activities described in 310 CMR 30.221: Table 1 and designated by an "N".
3. Schedule for timely action: for projects for which applications are filed and fees received on or after May 1, 2020,
a. Within ten days the Department shall complete an administrative completeness review.
b. Within 21 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 21 days of the Department's statement identifying deficiencies, if any.
d. Within 21 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a final review.
4. Permit application fee: $155.
(b)
(1) (HW22) Hazardous waste recycling permits.
1. Category: Level I recycling permits and permit renewals.
2. Description:
a. Applications pursuant to 310 CMR 30.261: Applications for Class B(3) Permits for Generators to Market Off-specification Used Oil Fuel or 310 CMR 30.264: Class B(3) Permits to Market Specification Used Oil Fuel for a permit or permit renewal to market Class B(3) regulated recyclable materials described in 310 CMR 30.213(3), except those proposing to burn such materials for energy recovery;
b. Applications pursuant to 310 CMR 30.232: Class B(1) Permits and Permit Applications for a permit or permit renewal to recycle regulated materials described in 310 CMR 30.213(1): Class B(1);
c. Applications pursuant to 310 CMR 30.280: Requirements for Recycling Class B(5) Regulated Recyclable Materials for a permit or permit renewal to recycle regulated recyclable materials described in 310 CMR 30.213(5): Class B(5);
d. Applications pursuant to 310 CMR 30.273: Generator Permits and Permit Applications for a permit or permit renewal to recycle regulated recyclable materials described in 310 CMR 30.213(4): Class B(4).
3. Schedule for timely action: for projects for which applications are filed and fees received on or after May 1, 2020,
a. Within ten days of receipt of an application and payment of the permit application fee the Department shall complete an administrative completeness review.
b. Within 24 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 24 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $245.
(c)
(1) (HW23) Hazardous waste recycling permits.
1. Category: Level II recycling permits.
2. Description:
a. applications pursuant to 310 CMR 30.247: Permits and Permit Applications for Those Who Burn Hazardous Waste Fuel at the Site of Generation for a permit to recycle regulated recyclable materials described in 310 CMR 30.213(2): Class B(2);
b. applications pursuant to 310 CMR 30.260(3) or (4) for a permit to recycle regulated recyclable materials described in 310 CMR 30.213(3): Class B(3) in amounts less than 100,000 gallons per year;
c. applications for transfer stations pursuant to 310 CMR 30.010: Definitions and 30.277: Recycling and Transfer Station Permits and Permit Applications concerning the regulated recyclable materials described in 310 CMR 30.213(4): Class B(4).
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 36 days of receipt of an application and payment of the permit application fee, the department shall complete an administrative completeness review.
b. Within 36 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 36 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $1,235.
(c)
(2) (HW24) Hazardous waste recycling permits.
1. Category: Level II recycling permit renewals or modifications.
2. Description: Level II recycling permit renewals or permit modifications for HW23.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $325.
(d) (HW12) Hazardous waste recycling permits.
1. Category: Level III Recycling Permit - Precious Metals.
2. Description: application for recycling facilities pursuant to 310 CMR 30. 277: Recycling and Transfer Station Permits and Permit Applications for a permit to recycle regulated recyclable material described in 310 CMR 30.213(4): Class B(4).
3. Schedule for timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 96 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 96 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $5,845.
(d)
(1) (HW25) Hazardous waste recycling permits.
1. Category: Level III recycling permits.
2. Description:
a. applications pursuant to 310 CMR 30.224: Applications for Class A Permits for a permit to recycle regulated recyclable materials described in 310 CMR 30.212(3) or (5) through (8) allowing applicants to accept for recycling such materials generated off site;
b. applications pursuant to 310 CMR 30.260(2) for a permit to market regulated recyclable materials described in 310 CMR 30.213(3): Class B(3);
c. applications pursuant to 310 CMR 30.260(3) or (4) for a permit to recycle regulated recyclable materials described in 310 CMR 30.213(3): Class B(3) in amounts equal to or greater than 100,000 gallons per year;
d. applications pursuant to 310 CMR 30.290: Requirements for Recycling Class C Regulated Recyclable Materials for a permit to recycle regulated recyclable materials described in 310 CMR 30.214: Class C Regulated Recyclable Materials.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the department shall complete an administrative completeness review.
b. Within 96 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 96 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 24 days of the close of the period for public comment, including any public hearing, the department shall complete a public comment review.
4. Permit application fee: $9,550.
(d)
(2) (HW26) Hazardous waste recycling permits.
1. Category: Level III recycling permit renewals or modifications.
2. Description: Level III recycling permits renewals or permit modifications for permits HW12 and HW25.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after May 1, 2020,
a. Within 24 days of receipt of an application and payment of the permit application fee, the department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $1,065.

Hazardous Waste Transporters

(g) (HW05) Permits for Transporters of Hazardous Waste.
1. Category: permits to transport hazardous waste, including mixed waste, pursuant to 310 CMR 30.400: Requirements for Transporters of Hazardous Waste, and 310 CMR 30.800: Licensing Requirements and Procedures.
2. Schedule for timely action: for projects for which applications are filed and fees received on or after May 1, 2020,
a. Within 30 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 60 days of making a determination of administrative completeness, the Department shall complete a technical review, including the response to any public comments made during a public comment period if any,
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 60 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
3. Permit application fee: $3,450.
(g)
(1) (HW28) Permits for Transporters of Hazardous Waste.
1. Category: annual vehicle identification device (VID).
2. Description: one or more vehicle VID(s) for use during a single calendar year pursuant to 310 CMR 30.010: Definitions and 310 CMR 30.414: Vehicle Identification Device by a licensed hazardous waste transporter. After issuance of VID(s) for use during a single calendar year, additional or replacement VID(s) for the same calendar year may be requested without an additional fee.
3. Schedule for timely action: for projects for which application is filed and fees received on or after March 24, 2017,
a. Within 72 days of receipt of an application and payment of the application fee, the Department shall complete a technical review.
b. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any,
c. Within 72 days of receipt of materials in response to the Department's statement identifying deficiencies, the Department shall complete a final review.
4. Permit application fee: calculated in accordance with 310 CMR 30.000: Hazardous Waste and 801 CMR 4.07: Hazardous Waste Transporters Fee by adding the volume in pounds of all nonexempt hazardous waste manifested for transport in Massachusetts during the 12 months ending the March 31st prior to the application, and multiplying pounds by $0.00084 for calendar year 2003 VID(s) and by $0.00172 for applications for each year thereafter; but regardless of calculation, the fee shall be a minimum of $60.
(h)
(1) (HW14) Permit Renewals for Transporters of Hazardous Waste.
1. Category: renewal of Hazardous Waste Transporter permits, including mixed waste, pursuant to 310 CMR 30.400: Requirements for Transporters of Hazardous Waste and 310 CMR 30.800: Licensing Requirements and Procedures.
2. Schedule of timely action: for projects for which applications are filed and/or fees received on or after May 1, 2020,
a. Within 30 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 60 days of making a determination of administrative completeness, the Department shall complete a technical review, including the response to any public comments made during a public comment period if any,
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 60 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
3. Permit application fee: $2,375.

Transporters of Class B(4) Regulated Recyclable Material

(i) (HW06) permits for Transporters of Class B(4) Regulated recyclable material.
1. Category: permits for Transporters of Class B(4) Regulated recyclable material.
2. Description: permit to transport Class B(4) Regulated Recyclable Materials pursuant to 310 CMR 30.213(4): Class B(4) and 310 CMR 30.275: Transporter Permits and Permit Applications.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after May 1, 2020,
a. Within ten days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $1,290.
(j)
(1) (HW15) Permit Renewal for Transporters of Regulated Recyclable Material
1. Category: permit Renewal for Transporters of Regulated Recyclable Material.
2. Description: renewal of permit to transport Class B(4) Regulated Recyclable Material pursuant to 310 CMR 30.213(4): Class B(4) and 310 CMR 30.275: Transporter Permits and Permit Applications.
3. Schedule of Timely Action: for projects for which applications are filed and/or fees received on or after May 1, 2020,
a. Within ten days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $890.

Hazardous Waste Transporter Permit and Class B(4) Regulated Recyclable Material Transporter Permit Modifications

(j)
(3) (HW27) Permit Modification for Hazardous Waste Transporter Permit and Class B(4) Regulated Recyclable Material Transporter Permit.
1. Category: presumptive approval permit modification for Hazardous Waste transporter permits and Class B(4) Regulated Recyclable Material pursuant to 310 CMR 30.200: Provisions for Recyclable Material and for Waste Oil, 310 CMR 30.400: Requirements for Transporters of Hazardous Waste, and 310 CMR 30.800: Licensing Requirements and Procedures, as applicable.
2. Description: approval of a change in address, E.P.A. identification number, telephone number, waste categories/codes, and the following which are not 310 CMR 30.828: Transfer of Licenses license transfers: name changes, stock transfers (less than 5% equity/liability), and new owners/operators.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after May 1, 2020,
a. Within ten days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 20 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy any identified deficiencies within 30 days of the Department's statement identifying deficiencies, if any.
d. Within 20 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a final review.
4. Permit application fee: $280.

Treatability Studies

(k) (HW07) Permits for hazardous waste.
1. Category: approval of hazardous waste treatability studies pursuant to 310 CMR 30.010: Definitions and 310 CMR 30.104(3)(c).
2. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 36 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 36 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
3. Permit application fee: $2,695.

TSD Facilities

(l) (HW08) Permits for hazardous waste treatment, storage, or disposal (TSD) facilities.
1. Category: license to operate or approval of closure plan for TSD facility.
2. Description: licenses for facilities that treat, store, or dispose of hazardous wastes, pursuant to 310 CMR 30.010: Definitions, 310 CMR 30.099: Interim Status Facilities, and 310 CMR 30.800: Licensing Requirements and Procedures; approval of closure plans for such facilities pursuant to 310 CMR 30.010 and 310 CMR 30.580: Closure.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017, individual rule project subject to 310 CMR 4.05.
4. Permit application fee: individual rule project subject to 310 CMR 4.05.

TSD Facility Modification

(m) (HW09) Permits for TSD Facility Modifications.
1. Category: Class I modifications.
2. Description: modifications to TSD licenses pursuant to 310 CMR 30.852: Facility License Modification at the Request of the Licensee, which require prior written approval of the Department pursuant to 310 CMR 30.852(2)(b) and Table 30.852: Classification of License Modifications; and modifications to TSD licenses pursuant to 310 CMR 30.099(5): Changes during Interim Status and 310 CMR 30.852 which require prior written approval of the Department pursuant to 310 CMR 30.852(2)(b) and Table 30.852. 3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 24 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. The applicant may elect to follow the procedures for Class II modifications. If the applicant so elects, the fee and schedule provisions applicable to Class II modifications at 310 CMR 4.10(3)(n) shall apply.
4. Permit application fee: $215.
(n) (HW10) Permits for TSD Facility Modifications.
1. Category: Class II modifications.
2. Description: modifications of licenses for TSD facilities pursuant to 310 CMR 30.852(3): Class 2 Modifications and Table 30.852: Classification of License Modifications; and modifications to TSD licenses pursuant to 310 CMR 30.099(5): Changes during Interim Status and 310 CMR 30.852(2): Class 1 Modifications.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after May 1, 2020,
a. Within ten days of the latest date of receipt of the application, payment of the application fee and filing of the public notice required by 310 CMR 30.852(2): Class 1 Modifications, the Department shall complete an administrative completeness review.
b. Within 96 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 36 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $12,525.
(o) (HW11) Permits for TSD Facility Modifications.
1. Category: Class III modifications.
2. Description: modifications of licenses for TSD facilities pursuant to 310 CMR 30.852(4): Class 1 Modifications and Table 310 CMR 30.852: Classification of License Modifications or 310 CMR 30.852(5): Other Modifications; and modifications to TSD licenses pursuant to 310 CMR 30.099(5): Changes During Interim Status, and 310 CMR 30.852(3): Class 2 Modifications or 310 CMR 30.852(4): Class 3 Modifications.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after October 8, 2004, individual rule project subject to 310 CMR 4.05.
4. Permit application fee: individual rule project subject to 310 CMR 4.05.

Declassification

(p) (HW16) Permit for Declassification.
1. Category: approval of declassification.
2. Description: approval of petition to classify waste as nonhazardous pursuant to 310 CMR 30.141: When a Hazardous Waste Ceases to Be a Hazardous Waste and 310 CMR 30.142: Petition to Classify a Waste as Nonhazardous.
3. Schedule for timely action: individual rule project subject to 310 CMR 4.05.
4. Permit application fee: for projects for which applications are filed and fees received on or after July 1, 1992, individual rule project subject to 310 CMR 4.05.

Research Facilities

(q) (HW20) Permits for hazardous waste research facilities.
1. Category: license to operate a research facility where research studies are conducted.
2. Description: licenses for facilities which intend to conduct research studies or otherwise engage in continuous research, development, and demonstration activities as defined in 310 CMR 30.010: Definitions and which require prior Department approval or approval to continue activities as required by 310 CMR 30.104(3)(d): Research Study Samples and 30.864: Research Facility License.
3. Schedule for timely action: for projects for which applications are filed and fees received on and after October 8, 2004, individual rule project subject to 310 CMR 4.05.
4. Permit application fee: individual rule project subject to 310 CMR 4.05.
(4) Solid Waste.

Facility Siting

(a) (SW01) Permits for solid waste facility siting.
1. Category: solid waste facility site suitability report pursuant to 310 CMR 16.00: Site Assignment Regulations for Solid Waste Facilities for a new site or expanded site or for a site assigned site applying for a major modification where the site had never received a site suitability report.
2. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 21 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 60 days of receipt of proof that the public notice requirement set forth in 310 CMR 16.10(4): Public Notice Application has been satisfied by the applicant, the Department shall finish review and issue the site suitability report.
3. Permit application fee: $10,585.
(a)
(1) (SW38) Permits for solid waste facility siting.
1. Category: solid waste facility site suitability report pursuant to 310 CMR 16.22: Modifications to and Rescissions and Suspensions of Site Assignments for a major modification to site assignment where a site suitability report has previously been issued for the site.
2. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 21 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 60 days of receipt of proof that the public notice requirement set forth in 310 CMR 16.10(4): Public Notice Application has been satisfied by the applicant, the Department shall finish review and issue the site suitability report.
3. Permit application fee: $1,920.
(b)
(1) (SW46) Permits for solid waste: recyclable and organic material management.
1. Category: permits for a new recycling, composting or conversion operation handling recyclable or organic material.
2. Description: recycling, composting, or conversion operation pursuant to 310 CMR 16.05: Permit for Recycling, Composting or Conversion (RCC) Operations.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 60 days of the close of the period for public comment, including any public hearing, the Department shall complete a public comment review.
4. Permit application fee:
a. A transfer operation limited to organic material only that receives a maximum of two tons per day and has no more than five tons on-site at any time: $1,000
b. Any other recycling, composting or conversion operation: $8,750
(b)
(2) (SW47) Permits for solid waste: recyclable and organic material management.
1. Category: permit renewal or modification for recycling, composting, or conversion operation handling recyclable or organic material.
2. Description: permit renewal or modification for recycling, composting or conversion operation pursuant to 310 CMR 16.05: Permit for Recycling, Composting or Conversion (RCC) Operations.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 24 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 24 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 60 days of the close of the period for public comment, including any public hearing, the Department shall complete a public comment review.
4. Permit application fee:
a. A transfer operation limited to organic material only that receives a maximum of two tons per day and has no more than five tons on site at any time: $200.
b. Any other recycling, composting or conversion operation: $1,458.

Certain Modifications to Any Facility

(d)
(1) (SW45) Permits for solid waste management.
1. Category: presumptive approval procedure for certain modifications of any type of solid waste management facility pursuant to 310 CMR 19.029(3): Use of Presumptive Approval Procedure at 310 CMR 19.034 .
2. Description: review of a notice of modification pursuant to 310 CMR 19.029(3): Use of Presumptive Approval Procedure at 310 CMR 19.034 .
3. Schedule for timely action: for projects for which applications are filed and fees received on or after May 1, 2020,
a. Within ten days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 45 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 45 days of the Department's statement identifying deficiencies, if any.
d. Within 45 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $595.

Transfer Station and Handling Facilities

(g) (SW05) Permits for solid waste transfer stations or handling facilities.
1. Category: permit and authorization to construct a new or expanded large transfer station, C&D transfer station, large C&D processing facility, or other large handling facility pursuant to 310 CMR 19.029(1): Use of Permit Procedure at 310 CMR 19.032 , and 310 CMR 19.041: Authorization to Construct.
2. Description: authorization to construct a large transfer station, C&D transfer station, large C&D processing facility or other large handling facility, any of which receives 50 tons per day or more.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 60 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 60 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 60 days of the close of the period of public comment, including any public hearing, the Department shall complete a public comment review.
f. Where a variance is required pursuant to 310 CMR 19.080: Variances, the time periods for completion of technical and public comment reviews shall each be increased by 30 days.
4. Permit application fee: $7,235.
(h) (SW19) Permits for solid waste transfer stations or other handling facilities.
1. Category: permit and authorization to construct a new or expanded small transfer station, small C&D processing facility or other small handling facility pursuant to 310 CMR 19.029(1): Use of Permit Procedure at 310 CMR 19.032 , and 19.041: Authorization to Construct.
2. Description: authorization to construct a small transfer station, small C&D processing facility, or other small handling facility, any of which receives less than 50 tons per day.
3. Schedule for timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 24 days of the close of the period of public comment, including any public hearing, the Department shall complete a public comment review.
f. Where a variance pursuant to 310 CMR 19.080: Variances is required, the time periods for completion of technical and public comment reviews shall each be increased by 30 days.
4. Permit application fee: $2,075.
(i) (SW06) Permits for solid waste transfer stations or other handling facility.
1. Category: authorization to operate or renew operation permit for a C&D transfer station, large C&D processing facility, or other large handling facility pursuant to 310 CMR 19.029(2): Use of Permit Procedures at 310 CMR 19.033 and 19.042: Authorization to Operate.
2. Description: authorization to operate or renew operation permit for a C&D transfer station, large C&D processing facility, or other large handling facility any of which receives 50 tons per day or more excluding non-C&D transfer station.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 36 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 36 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $1,940.
(j) (SW20) Permits for solid waste transfer station or other handling facility.
1. Category: authorization to operate or renew operation permit for a small C&D processing facility or other small handling facility pursuant to 310 CMR 19.029(2): Use of Permit Procedures at 310 CMR 19.033 and 19.042: Authorization to Operate.
2. Description: authorization to operate or renew operation permit for a small C&D processing facility or other small handling facility, any of which receives less than 50 tons per day excluding all small transfer stations.
3. Schedule for timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 20 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 20 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $985.
(k) (SW07) Permits for solid waste transfer stations or other handling facilities.
1. Category: modification of permit for previously approved C&D transfer station, large C&D processing facility or other large handling facility pursuant to 310 CMR 19.029(2): Use of Permit Procedure at 310 CMR 19.033 .
2. Description: modification of permit for a C&D transfer station, large C&D processing facility or other large handling facility which receives 50 tons per day or more excluding all small transfer stations.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $3,235.
(l) (SW21) Permits for solid waste transfer stations or other handling facilities.
1. Category: modification of permit for previously approved, small C&D processing facility or other small handling facility pursuant to 310 CMR 19.029(2): Use of Permit Procedure at 310 CMR 19.033 .
2. Description: modification of permit for a small C&D processing facility or other small handling facility which receives less than 50 tons per day excluding non-C&D transfer station.
3. Schedule for timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 20 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 20 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $1,380.

Existing Landfill

(m) (SW08) Permits for solid waste landfill.
1. Category: authorization to construct in an existing permitted landfill pursuant to 310 CMR 19.041: Authorization to Construct.
2. Description: authorization to construct in an existing permitted landfill area where construction requires additional approval in phases pursuant to 310 CMR 19.041: Authorization to Construct and the initial permit.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 36 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 36 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 72 days of the close of the period for public comment, including any public hearing, the Department shall complete a public comment review.
4. Permit application fee: $1,780.
(o) (SW10) Permits for solid waste landfill.
1. Category: authorization to operate a landfill, pursuant to 310 CMR 19. 042: Authorization to Operate.
2. Description: authorization to operate new phases of a permitted landfill as required pursuant to 310 CMR 19.042: Authorization to Operate and the initial permit.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 36 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 36 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $1,940.
(p) (SW11) Permits for solid waste landfill.
1. Category: major modification of landfill permit pursuant to 310 CMR 19.029(2): Use of Permit Procedure at 310 CMR 19.033 .
2. Description: major modification of a landfill plan where a design change will result in the construction of an appurtenance or structure.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Where a variance pursuant to 310 CMR 19.080: Variances is required, the time periods for completion of technical reviews shall each be increased by 30 days.
4. Permit application fee,
a. Where the Secretary of Energy and Environmental Affairs determines that additional review pursuant to the Massachusetts Environmental Policy Act (MEPA) and 301 CMR 11.00: MEPA Regulations is required: $5,290.
b. Where additional review pursuant to MEPA is not required: $3,880.
(q) (SW22) Permits for solid waste landfill.
1. Category: minor modification of a landfill pursuant to 310 CMR 19.029(2): Use of Permit Procedure at 310 CMR 19.033 .
2. Description: modification of a landfill permit with a change in operations, equipment or daily capacity but not construction of an appurtenance or structure.
3. Schedule for timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 20 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 20 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Where a variance pursuant to 310 CMR 19.080: Variances is required, the time periods for completion of technical reviews shall each be increased by 30 days.
4. Permit application fee $1,380.
(r) (SW12) Permits for solid waste landfill.
1. Category: approval of landfill closure and assessment evaluation pursuant to 310 CMR 19.150: Landfill Assessment Requirements.
2. Description: approval of complete initial site assessment and draft scope of work for a comprehensive site assessment pursuant to 310 CMR 19.150(4): Initial Site Assessment.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 36 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 36 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $1,380.
(s) (SW23) Permit for solid waste landfill.
1. Category: approval of landfill closure and assessment evaluation pursuant to 310 CMR 19.150: Landfill Assessment Rewuirements.
2. Description: approval of complete landfill comprehensive site assessment pursuant to 310 CMR 19.150(5): Comprehensive Site Assessment.
3. Schedule of timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 60 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 60 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $5,645.
(t) (SW24) Permit for solid waste landfill.
1. Category: approval of landfill closure and assessment evaluation pursuant to 310 CMR 19.150: Landfill Assessment Requirements.
2. Description: Approval of a corrective action alternative analysis report pursuant to 310 CMR 19.150(6): Comprehensive Site Assessment.
3. Schedule of timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $3,565.
(u) (SW25) Permit for solid waste landfill.
1. Category: approval landfill closure and assessment evaluation pursuant to 310 CMR 19.150: Landfill Assessment Requirements.
2. Description: approval of the corrective action design pursuant to 310 CMR 19.151(2)(a): Corrective Action Design.
3. Schedule of timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $4,255.
(u)
(1) (SW43) Permits for solid waste landfill.
1. Category: Determination of landfill closure completion pursuant to 310 CMR 19.140(6): Completion of Closure.
2. Description: approval of documentation of closure and post-closure planning.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Where a variance pursuant to 310 CMR 19.080: Variances is required, the time periods for completion of technical reviews shall each be increased by 30 days.
4. Permit application fee: $2,435.

New Landfill or Expanded Existing Landfill

(v) (SW26) Permit for solid waste landfill.
1. Category: permit and authorization to construct new large landfill or large expansion of permitted landfill pursuant to 310 CMR 19.029(1): Use of Permit Procedure at 310 CMR 19.032 and 19.041: Authorization to Construct.
2. Description: permit to construct a new landfill with 250 acre-feet or more of disposal volume or expand a permitted landfill by 250 feet or more of disposal volume.
3. Schedule of timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017, individual rule project subject to 310 CMR 4.05.
4. Permit application fee: individual rule project subject to 310 CMR 4.05.
(w) (SW27) Permit for solid waste landfill.
1. Category: Permit and authorization to construct new medium sized landfill or medium expansion of permitted landfill pursuant to 310 CMR 19.029(1): Use of Permit Procedure at 310 CMR 19.032 and 19.041: Authorization to Construct.
2. Description: permit to construct a new landfill with greater than 25 acre-feet but less than 250 feet of disposal volume or to expand a permitted landfill by greater than 25 feet but less than 250 feet of disposal volume.
3. Schedule of timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 80 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 80 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 72 days after the close of any public comment period including public hearing, the Department shall complete a public comment review, make any adjustments to the draft permit and issue a final permit decision.
f. Where a variance pursuant to 310 CMR 19.080: Variances is required, the time periods for completion of technical and public comment reviews shall each be increased by 30 days.
4. Permit application fee: $28,555.
(x) (SW28) Permit for solid waste landfill.
1. Category: permit and authorization to construct new small landfill or to construct small expansion of permitted landfill pursuant to 310 CMR 19.029(1): Use of Permit Procedure at 310 CMR 19.032 and 19.041: Authorization to Construct.
2. Description: permit to construct a new landfill with no more than 25 acre-feet of disposal volume or to expand a permitted landfill by no more than 25 acre-feet disposal volume.
3. Schedule of timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 72 days after the close of any public comment period including public hearing, the Department shall complete a public comment review, make any adjustments to the draft permit and issue a final permit decision.
f. Where a variance pursuant to 310 CMR 19.080: Variances is required, the time periods for completion of technical and public comment reviews shall each be increased by 30 days.
4. Permit application fee: $14,275.
(y) (SW29) Permit for solid waste landfill.
1. Category: permit and authorization to construct new woodwaste landfill or to construct the expansion of a permitted woodwaste landfill pursuant to 310 CMR 19.029(1): Use of Permit Procedure at 310 CMR 19.032 and 19.041: Authorization to Construct.
2. Description: permit and authorization to construct a new woodwaste landfill or expand woodwaste capacity of a permitted landfill to dispose of uncontaminated woodwaste pursuant to 310 CMR 19.006: Definitions, including reclamation activities but excluding construction and demolition material.
3. Schedule of timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 72 days after the close of any public comment period including public hearing, the Department shall complete a public comment review, make any adjustments to the draft permit and issue a final permit decision.
f. Where a variance pursuant to 310 CMR 19.080: Variances is required, the time periods for completion of technical and public comment reviews shall each be increased by 30 days.
4. Permit application fee: $14,275.
(z) (SW48) Permit for a Solid Waste Facility Third Party Inspector.
1. Category: registration of solid waste facility inspector pursuant to 310 CMR 19.018(5): General Requirements, Registration and Qualification for Third Party Inspectors.
2. Description: filing of a Solid Waste Facility Inspector Qualifications Statement.
3. Schedule of timely action: for a qualifications statement filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of a qualifications statement and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 24 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 24 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $595.

Determinations

(z)
(1) (SW39) Permits for solid waste management.
1. Category: determination of beneficial use - use of secondary materials in commercial products pursuant to 310 CMR 19.060(14): Category 1 - Use of Secondary Materials in Commercial Products.
2. Description: determination that the proposed use of a solid waste constitutes the beneficial use of a secondary material when reviewed in accordance with 310 CMR 19.060(14): Category 1 - Use of Secondary Materials in Commercial Products and that such material is no longer classified as a solid waste per approval.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 24 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 24 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $ 2,375.
(aa)
(1) (SW40) Permits for solid waste management.
1. Category: determination of beneficial use - use of secondary materials in a DEP regulated system pursuant to 310 CMR 19.060(15): Category 2 - Use of Secondary Materials in Regulated Systems.
2. Description: a determination that the proposed use of a solid waste constitutes the beneficial use of a secondary material when reviewed in accordance with 310 CMR 19.060(15): Category 1 - Use of Secondary Materials in Regulated Systems and that such material is adequately regulated and no longer classified as a solid waste per approval.
3. Schedule for timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 24 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 24 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $2,375.
(aa)
(2) (SW41) Permits for solid waste management.
1. Category: determination of beneficial use - use of secondary materials in restricted applications pursuant to 310 CMR 19.060(16): Category 3 - Use if Secondary Materials in Regulated Applications.
2. Description: determination that the proposed use of a solid waste constitutes the beneficial use of a secondary material when reviewed in accordance with 310 CMR 19.060(16): Category 3 - Use of Secondary Materials in Regulated Applications and that such material is no longer classified as a solid waste per approval.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $4,455.
(aa)
(3) (SW42) Permits for solid waste management.
1. Category: determination of beneficial use - use of a secondary material in an unrestricted application pursuant to 310 CMR 19.060(17): Category 4 - Use of Secondary Materials in Unrestricted Applications.
2. Description: a determination that the proposed use of a solid waste constitutes the beneficial use of a secondary material when reviewed in accordance with 310 CMR 19.060(17): Category 4 - Use of Secondary Materials in Unrestricted Applications and that such material is no longer classified as a solid waste per approval.
3. Schedule of timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017 individual rule project subject to 310 CMR 4.05.
4. Permit application fee: individual rule project subject to 310 CMR 4.05.
(aa)
(4) (SW44) Permits for solid waste management.
1. Category: determination of beneficial use - modification.
2. Description: modification of a previously approved determination of beneficial use permit in accordance with 310 CMR 19.060: Beneficial Use of Solid Waste.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 24 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 24 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $1,065.
(aa)
(5) (SW49) Permits for solid waste management.
1. Category: certification of transfer of permit for any type of solid waste management facility pursuant to 310 CMR 19.044: Transfer of Permits.
2. Description: submission of a transfer of permit certification pursuant to 310 CMR 19.044: Transfer of Permits.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after May 1, 2020,
a. Within ten days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 45 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 45 days of the Department's statement identifying deficiencies, if any.
d. Within 45 of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $595.
(bb) (SW14) Permits for solid waste management.
1. Category: special waste determination.
2. Description: approval for a facility to accept a listed special waste pursuant to 310 CMR 19.029(3): Use of Presumptive Approval Procedure at 310 CMR 19.034 and 310 CMR 19.061: Special Waste.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after May 1, 2020,
a. Within ten days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 45 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 45 days of the Department's statement identifying deficiencies, if any.
d. Within 45 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $1,940.

Combustion Facility

(dd) (SW15) Permits for solid waste combustion facility.
1. Category: Permit and authorization to construct a new solid waste combustion facility or expansion of an existing facility, pursuant to 310 CMR 19.029(1): Use of Permit Procedure at 310 CMR 19.032 and 19.041: Authorization to Construct.
2. Schedule for timely action: for projects filed on or after March 24, 2017, individual rule project subject to 310 CMR 4.05.
3. Permit application fee: individual rule project subject to 310 CMR 4.05.
(ee) (SW16) Permits for solid waste combustion facility.
1. Category: Authorization to operate or modify an existing combustion facility pursuant to 310 CMR 19.029(2): Use of Permit Procedure at 310 CMR 19.033 .
2. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Where a variance pursuant to 310 CMR 19.080: Variances is required, the time periods for completion of technical reviews shall each be increased by 30 days.
3. Permit application fee: $5,290.

Demonstration Projects

(ff) (SW32) Permit for Solid Waste Demonstration Project.
1. Category: approval for a demonstration project pursuant to 310 CMR19. 062: Demonstration Projects or Facilities.
2. Description: Approval of a scope of work for demonstrating the effectiveness and utility of a new or innovative solid waste management technology.
3. Schedule for timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $2,075.
(gg) (SW33) Permit for Solid Waste Demonstration Project.
1. Category: approval of a demonstration project report pursuant to 310 CMR 19.062(4): Department Evaluation of Demonstration Projects.
2. Description: Approval of a report providing the results of a demonstration project approved pursuant to 310 CMR 4.10(4)(ff).
3. Schedule for timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $4,950.
(hh) (SW35) Permit for Solid Waste: Recycling, Composting, or Conversion Demonstration Project.
1. Category: approval of a demonstration project pursuant to 310 CMR 16.05(8): Demonstration Project for Recycling, Composting or Converting Recyclable or Organic Material.
2. Description: approval for a project to demonstrate the effectiveness and utility of a new or innovative recycling, composting, or conversion technology for recyclable or organic material.
3. Schedule for timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 24 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 24 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 24 days of the close of the period for public comment, including any public hearing, the Department shall complete a public comment review.
4. Permit application fee: $1,458.
(ii) (SW36) Permits for Post-closure Use.
1. Category: permit for post-closure use: major category. Approval of a post-closure use at a solid waste management facility site pursuant to 310 CMR 19.016: Post-closure Use, 19.029(2): Use of Permit Procedure at 310 CMR 19.033 and, when the post-closure use is at a landfill, 310 CMR 19.143: Post-closure Use.
2. Description: approval for post-closure use that is not subject to SW37.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy any identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $3,425.
(jj) (SW37) Permits for Post-closure Use.
1. Category: permit for post-closure use: minor category. Approval of a post-closure use at a solid waste management facility site pursuant to 310 CMR 19.016: Post-closure Use, 19.029(3): Use of Presumptive Approval Procedure at 310 CMR 19.034 and, when the post-closure use is at a landfill, 310 CMR 19.143: Post-closure Use.
2. Description: approval for post-closure use that:
a. does not affect the facility's appurtenances, or
b. is not located on the final cover of a landfill.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after May 1, 2020,
a. Within ten days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 45 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy any identified deficiencies within 45 days of the Department's statement identifying deficiencies, if any.
d. Within 45 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $1,330.
(5) Industrial Wastewater (Reserved)).
(6) Water Supply.
(a) (WS) reserved
(b) (WS) reserved
(c) (WS) reserved
(d) (WS) reserved
(e) (WS) reserved

Underground Injection Control

(f) (WS06) Permits for water supply, underground injection control.
1. Category: registration of underground injection wells and Pre-closure Notification.
2. Description: registration of underground injection wells pursuant to 310 CMR 27.08: Registration and Pre-closure Notification pursuant to 310 CMR 27.04: Prohibited Activities and 310 CMR 27.12: Corrective Action; excluding registration for residential facilities up to four units having only residential activities; and excluding registration in communities where permit review for the UIC well type has been delegated by the Department pursuant to an approved Memorandum of Agreement.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 24 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 24 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee:
a. Well codes 5A24 with the exception of abandoned wells, 5B6, 5C4, 5G1, and 5K pursuant to 40 CFR 144.6 and 146.5: $585.
b. Well codes 4P, 5A19, 5A23, 5B2, 5B3, 5C3, 5C5, 5H2, 5H3, and 5X pursuant to 40 CFR 144.6 and 146.5: $290.
c. Well codes 5A18, 5A24 abandoned wells only, 5B1, 5C2, 5E, and 5H1 pursuant to 40 CFR 144.6 and 146.5: $110.
d. Pre-closure Notification pursuant to 310 CMR 27. 04: Prohibited Activities and 27.12: Corrective Action: $110.
(g) (WS ) reserved
(h) (WS) reserved

Zone 2 Determination for Existing Sources of Drinking Water

(i) (WS07) Zone 2 determination for existing sources of drinking water
1. Category: approval to conduct a pumping test at an existing source for purposes of Zone II delineation.
2. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 36 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 36 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $970.
(j) (WS08) Zone 2 determination for existing sources of drinking water.
1. Category: approval of Zone II delineation for existing source.
2. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
3. Permit application fee: $3,235.
(k) (WS) reserved
(l) (WS) reserved

Cross Connection

(n) (WS10) Permits for water supply: cross connections.
1. Category: certification of backflow prevention device testers and cross connection surveyors pursuant to 310 CMR 22.22(13): Inspection Surveying and Overhauling of Devices.
2. Schedule for timely action: for projects for which applications are filed and fees received on or after May 1, 2020,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 24 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 24 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee:
a. certification of cross connection surveyor excluding currently certified testers: $65.
b. certification of backflow prevention device tester excluding currently certified surveyors: $65.
c. certification of backflow prevention device tester and cross connection surveyor: $65.

New Technology Approval

(o) (WS11) Permits for water supply: new technology approval.
1. Category: approval of minor new technology for treatment of drinking water.
2. Description: minor new technology approval pursuant to 310 CMR 22.04(8): New Product or Technology where no other Department program or interagency review is required of the new technology. Pilot testing may be required.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $2,265.
(p) (WS27) Permits for water supply: new technology approval.
1. Category: approval of new technology additives and coatings.
2. Description: approval of drinking water new technology additives and coatings previously approved by a third-party pursuant to 310 CMR 22.04(8): New Product or Technology.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 24 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 30 days of the Department's statement identifying deficiencies, if any.
d. Within 24 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $290.
(q) (WS31) Permits for vending and POU/POE Devices.
1. Category: approval pursuant to 310 CMR 22.04(1): New or Substantially Modified Public Water Systems and 22.23(4) for vending machines and POU/POE treatment devices that have previous third party approval.
2. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
3. Permit application fee: $290.
(r) (WS28) Permits for new technology.
1. Category: approval of one vending site/source prototype pursuant to 310 CMR 22.04(4): Prohibition on Construction or Substantially Modification of a Public Water System Without Prior Department Approval -- minor.
2. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
3. Permit application fee: $1,380.
(s) (WS12) Permits for water supply: new technology approval.
1. Category: approval of major new technology for treatment of drinking water.
2. Description: major new technology approval for treatment of drinking water pursuant to 310 CMR 22.04(8): New Product Technology where no other Department program or inter-agency review is required of the new technology.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017, 2009, individual rule project subject to 310 CMR 4.05.
4. Permit application fee: individual rule project.

Water Quality Assurance/New Source Approval

(t) (WS13) Permits for water supply, water quality assurance: new source approval.
1. Category: Approval to site source under 70 gallons per minute pursuant to 310 CMR 22.21: Ground Water Supply Protection.
2. Description: approval of exploratory phase work, site examination and land use survey, and approval to conduct pumping test in accordance with the current guidelines and policies for public water systems and 310 CMR 22.21: Ground Water Supply Protection.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $1,380.
(u) (Reserved)
(v) (WS15) Permits for water supply: water quality assurance: new source approval.
1. Category: approval of pumping test report and approval to construct sources under 70 gallons per minute in accordance with current guidelines and policies for public water systems and 310 CMR 22.21: Ground Water Supply Protection.
2. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $1,585.
(v)
(1) (WS37) Permits for water supply, water quality assurance: new source approval.
1. Category: approval of new transient non-community source under 10,000 gallons per day.
2. Description: approval of land use survey, pumping test report, and approval to construct source pursuant to 310 CMR 22.21: Ground Water Supply Protection.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $810.
(x) (WS17) Permits for water supply, water quality assurance: new source approval.
1. Category: approval to site source 70 gallons per minute or greater and to conduct pumping test.
2. Description: approval to site source 70 gallons per minute or greater by approval of exploratory phase work, site screening, site examination, land use survey, and approval to conduct pumping test pursuant to 310 CMR 22.21: Ground Water Supply Protection.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $4,850.
(z) (WS19) Permits for water supply: water quality assurance: new source approval.
1. Category: approval of pumping test report for source 70 gallons per minute or greater pursuant to 310 CMR 22.21: Ground Water Supply Protection.
2. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 48 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 96 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 96 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
3. Permit application fee: $8,205.
(aa) (WS20) Permits for water supply: water quality assurance: new source approval.
1. Category: approval to construct source 70 gallons per minute or greater pursuant to 310 CMR 22.21: Ground Water Supply Protection.
2. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. A WS20 application may be submitted concurrently with a WS19 application in which case both permits will be subject to the WS19 application schedule for timely action.
3. Permit application fee: $2,910.

Water Quality Assurance/Water Treatment

(bb) (WS21) Permits for water supply, water quality assurance: water treatment.
1. Category: approval to conduct pilot study.
2. Description: approval to conduct pilot study pursuant to 310 CMR 22.03(1) and (2) and 22.04: Construction, Operation and Maintenance of Public Water Systems.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 48 days of receipt of an application and payment of the permit application fee, the Department shall complete a technical review.
b. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
c. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee:
a. Less than 40,000 gallons per day: $320.
b. 40,000 gallons per day or more and less than 200,000 gallons per day: $485.
c. 200,000 gallons per day or more and less than one million gallons per day: $850.
d. One million gallons per day or more: $1,135.
(cc) (WS22) Permits for water supply, water quality assurance: water treatment.
1. Category: approval of pilot study report.
2. Description: approval of pilot study report pursuant to 310 CMR 22.03(1) and (2) and 22.04: Construction, Operation and Maintenance of Public Water Systems.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 48 days of receipt of an application and payment of the permit application fee, the Department shall complete a technical review.
b. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
c. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee:
a. Less than 40,000 gallons per day: $915.
b. 40,000 gallons per day or more and less than 200,000 gallons per day: $1,600.
c. 200,000 gallons per day or more and less than one million gallons per day: $2,160.
d. One million gallons per day or more: $2,850.
(dd) (WS23) Permits for water supply: water treatment.
1. Categories: approval to construct a facility to treat drinking water.
2. Description: approval to construct a facility to treat drinking water in daily volumes of less than one million gallons per day pursuant to 310 CMR 22.03(1) and (2) and 22.04: Construction, Operation and Maintenance of Public Water Systems.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee:
a. Less than 40,000 gallons per day: $1,125.
b. 40,000 gallons per day or more, and less than 200,000 gallons per day: $1,780.
c. 200,000 gallons per day or more, and less than one million gallons per day: $5,005.
(ee) (WS24) Permits for water supply water quality assurance: water treatment.
1. Category: treatment approval to construct a facility to treat 1 mgd or greater pursuant to 310 CMR 22.03(1) and (2) and 22.04: Construction, Operation and Maintenance of Public Water Systems.
2. Schedule for timely action: for applications filed on or after March 24, 2017, individual rule project subject to 310 CMR 4.05.
3. Permit application fee: individual rule project subject to 310 CMR 4.05.
(ff) (WS25) Permits for water supply water quality assurance: water treatment
1. Category: approval of treatment facility modification.
2. Description: approval of treatment facility modification permit pursuant to 310 CMR 22.03(1) and (2) and 22.04: Construction, Operation and Maintenance of Public Water Systems.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee:
a. Less than 40,000 gallons per day: $550.
b. 40,000 gallons per day or more, and less than 200,000 gallons per day: $860.
c. 200,000 gallons per day or more, and less than one million gallons per day: $2,210.
d. One million gallons per day or more: $3,070.
(gg) (WS29) Permits for water quality assurance: water treatment.
1. Category: approval of chemical addition retrofit of water systems that serve more than 3300 people.
2. Description: approval of water treatment modifications for the addition of chemicals pursuant to 310 CMR 22.03(1) and (2) and 22.04: Construction, Operation and Maintenance of Public Water Systems.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $705.
(gg)
(1) (WS34) Permits for water quality assurance: water treatment.
1. Category: approval of chemical addition retrofit of water systems that serve less than or equal to 3300 people.
2. Description: approval of water treatment modifications for the addition of chemicals pursuant to 310 CMR 22.03(1) and (2) and 22.04: Construction, Operation and Maintenance of Public Water Systems.
3. Schedule of timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $350.

Water Quality Assurance

(hh) (WS26) Permits for water quality assurance.
1. Category: approval of sale of land for water supply purposes pursuant to 310 CMR 22.24: Sale, Transfer of Property Interest, or Change in Use of Water Supply Land, or of acquisition of land to be used for water supply purposes pursuant to M.G.L. c. 165, § 4B.
2. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017
a. Within 48 days of receipt of an application and payment of the permit application fee, the Department shall complete a technical review.
b. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
c. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
3. Permit Application fee: $1,290.
(hh)
(1) (WS32) Permits for water quality assurance: Distribution System Modifications.
1. Category: approval of distribution system modifications such as storage tanks, distribution pump stations, transmission main installation, etc. for water systems that serve more than 3300 people.
2. Description: approval of distribution system modifications pursuant to 310 CMR 22.03(1) and (2) and 22.04: Construction, Operation and Maintenance of Public Water Systems.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $1,055.
(hh)
(2) (WS33) Permits for water quality assurance: Distribution System Modifications.
1. Category: approval of distribution system modifications such as storage tanks, distribution pump stations, transmission main installation, etc. for water systems that serve less than or equal to 3300 people.
2. Description: approval of distribution system modifications pursuant to 310 CMR 22.03(1) and (2) and 22.04: Construction, Operation and Maintenance of Public Water Systems.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $525.
(hh)
(3) (WS36) Permits for water quality assurance.
1. Category: approval of abandonment of a water source pursuant to 310 CMR 22.25: Abandonment of Water Supply Sources.
2. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017.
a. Within 48 days of receipt of an application and payment of the permit application fee, the Department shall complete a technical review.
b. The permit applicant may remedy any identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
c. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
3. Permit application fee: $70.
(ii) (WS30) Permits for water supply: vending machine and POU/POE treatment device.
1. Category: approval to install vending machine or POU/POE water treatment device.
2. Description: approval to install one type of vending machine or POU/POE water treatment device at one to nine locations on the same public water distribution system pursuant to 310 CMR 22.03(1) and (2) and 22.04: Construction, Operation and Maintenance of Public Water Systems.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee:
a. One type of vending machine at one to nine locations: $290.
b. One type of POU/POE device at one to nine locations: $290.
(ii)
(1) (WS35) Permits for water supply: vending machine and POU/POE treatment device.
1. Category: approval to install vending machine or POU/POE water treatment device.
2. Description: approval to install one type of vending machine or POU/POE water treatment device at ten or more locations on the same public water distribution system pursuant to 310 CMR 22.03(1) and (2) and 22.04: Construction, Operation and Maintenance of Public Water Systems.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials for the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee:
a. One type of vending machine at ten or more locations: $1,630.
b. One type of POU/POE device at ten or more locations: $1,630.

Well Drilling

(ii)
(2) (WS39) Permits for water supply, well drillers.
1. Category: well driller certification.
2. Description: well driller certification pursuant to 310 CMR 46.02: Certification Requirements.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 45 days of receipt of an application and payment of the permit application fee, the Department shall complete a technical review.
b. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
c. Within 45 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $200.
(ii)
(3) (WS40) Permits for water supply, well drillers.
1. Category: well driller certification renewal.
2. Description: well driller certification renewal and renewal of certification with waiver pursuant to 310 CMR 46.02: Certification Requirements and 46.03(4): Annual Renewal.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 45 days of receipt of an application and payment of the permit application fee, the Department shall complete a technical review.
b. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
c. Within 45 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $100.
(ii)
(4) (WS41) Permits for water supply, well drillers.
1. Category: well driller certification with waiver.
2. Description: initial well driller certification with waiver of some requirements pursuant to 310 CMR 46.02(3): Waiver.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 45 days of receipt of an application and payment of the permit application fee, the Department shall complete a technical review.
b. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
c. Within 45 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $400.
(ii)
(5) (WS42) Permits for water supply, well drillers.
1. Category: well drilling rig permit and decal and renewal of permit and decal.
2. Description: well drilling rig permit and decal pursuant to 310 CMR 46.03(1)(c): Rig Permit and Rig Markings for Field Identification and renewal of permit and decal pursuant to 310 CMR 46.03(4): Annual Renewal.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 45 days of receipt of an application and payment of the permit application fee, the Department shall complete a technical review.
b. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
c. Within 45 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $100 per rig.

Watershed Management

Water Withdrawals

(mm) (WM01) Permits for watershed management.
1. Category: transfer of right to withdraw water pursuant to 310 CMR 36.09: Transfer of a Registration Statement (registrations) or 310 CMR 36.33: Transfer of a Permit (permits).
2. Schedule for timely action: for projects for which applications are filed and fees received on or after May 1, 2020,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete a technical review.
b. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
c. Within 24 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
3. Permit application fee: $215.
(nn) (WM02) Permits for watershed management.
1. Category: amendments to existing withdrawal permits pursuant to 310 CMR 36.29: Permit Amendments, Suspensions, and Terminations.
2. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 36 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 36 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
3. Permit application fee: $1,940.
(oo) (WM03) Permits for watershed management.
1. Category: withdrawal permits.
2. Description: withdrawal permits pursuant to 310 CMR 36.00: Massachusetts Water Resources Management Program.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 30 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $4,100.

Herbicide Applications

(pp) (WM04) Permits for watershed management.
1. Category: approval to apply herbicide(s) to waters of the Commonwealth pursuant to M.G.L. c. 111, § 5E.
2. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 24 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 14 days of the Department's statement identifying deficiencies, if any.
d. Within 24 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
3. Permit application fee: $95.

Surface Water NPDES Permits

(qq) (WM05) Permits for watershed management.
1. Category: major NPDES surface water discharge permit and renewal.
2. Description: permit to discharge pursuant to 314 CMR 3.03: Discharges Requiring a Permit and defined by the USEPA as a major NPDES discharge pursuant to 40 CMR 122.2.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 30 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 200 days of making a determination of administrative completeness or receipt of EPA's draft NPDES permit, whichever is later, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 200 days of the Department's statement identifying deficiencies, if any.
d. Within 200 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 90 days of the close of the period for public comment, including any public hearing, the Department shall complete a public comment review.
4. Permit application fee: $6,785.
(rr) (WM06) Permits for watershed management.
1. Category: minor surface water discharge permit and renewal.
2. Description: permit to discharge pursuant to 314 CMR 3.03: Discharges Requiring a Permit and not otherwise defined as a major NPDES discharger by the USEPA pursuant to 40 CFR 122.2.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 30 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 150 days of making a determination of administrative completeness or receipt of EPA's draft NPDES permit, whichever is later, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 150 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 90 days of the close of the period for public comment, including any public hearing, the Department shall complete a public comment review.
4. Permit application fee: $3,170.
(ss) (WM07) Permits for watershed management.
1. Category: permit modification or renewal.
2. Description: renewals or modifications of permits for existing permitted facilities as defined in WM05, WM06, IW16, and IW18.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 30 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 90 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 90 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 60 days of the close of the period for public comment, including any public hearing, the Department shall complete a public comment review.
4. Permit application fee: $985.
(uu) (WM09) Permits for watershed management.
1. Category: approval of stormwater management plan.
2. Description: review and approval of a stormwater management plan for discharges to Outstanding Resource Waters and coastal Areas of Critical Environmental Concern and other stormwater discharges pursuant to 314 CMR 3.06: General Permits as required by the Department, and that file and qualify for inclusion in EPA's NPDES general permit for stormwater.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the appropriate fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completion, the Department shall complete a technical review.
c. The permit applicant may remedy any identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review and approve or disapprove the plan.
4. Permit application fee: $890.
(uu)
(1) (WM15) Permits for watershed management.
1. Category: general permit coverage for surface water discharge.
2. Description: Notice of Intent for coverage under a general permit for discharges pursuant to 314 CMR 3.06: General Permits and that file and qualify for inclusion in EPA's NPDES general permits.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within ten days of receipt of an application and payment of the permit application fee, the department shall complete an administrative completeness review.
b. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
c. Within ten days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a second administrative completeness review.
d. Within 21 days of making a determination of administrative completeness the Department shall complete a technical review.
e. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
f. Within 21 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $500.
(uu)
(2) (WM16) Permits for watershed management.
1. Category: treatment works plan approval.
2. Description: plan approval for a new facility or plan approval for a modification to an existing facility holding permit IW16, IW18, WM05, or WM06.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $980.
(7) Water Pollution Control.

Title 5

(a)
(1) (WP57) Permits for Water Pollution Control: Title 5.
1. Category: approval for installation of a recirculating sand filter or approved equivalent alternative technology pursuant to 310 CMR 15.202: Use of Recirculating Sand Filters.
2. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 45 days of receipt of an application and payment of the permit application fee, the Department shall complete a technical review.
b. The permit applicant may remedy identified deficiencies within 30 days of the Department's statement identifying deficiencies, if any.
c. Within 45 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
3. Permit application fee: $525.
(a)
(2) (WP58) Permits for Water Pollution Control: Title 5.
1. Category: approval of plans to aggregate nitrogen loading or approval for installation of a shared system.
2. Description:
a. Approval of nitrogen aggregation plans pursuant to 310 CMR 15.216: Aggregate Determinations of Flows and Nitrogen Loadings, or
b. Approval for the installation of a shared system pursuant to 310 CMR 15.290: Shared Systems.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Nitrogen aggregation.
i. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
ii. Within 60 days of making a determination of administrative completeness, the Department shall complete a technical review.
iii. The permit applicant may remedy any identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
iv. Within 60 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
b. Shared System.
i. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
ii. Within 30 days of making a determination of administrative completeness, the Department shall complete a technical review.
iii. The permit applicant may remedy any identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
iv. Within 30 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $1,940.
(a)
(3) (WP59) Permits for Water Pollution Control: Title 5
1. Category: approval of variance.
2. Description: approval of the following variances,
a. (Reserved)
b. Approval of variances pursuant to 310 CMR 15.410: Variances - Standard of Review, granted by Board of Health, except variance for increased flow to existing system, or c. Approval of variance granted by Board of Health for increased flow pursuant to 310 CMR 15.414: Variances for Increased Flow to Existing System or DEP issuance of variance for increased flow pursuant to 310 CMR 15.414: Variances for Increased Flow to Existing System.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 30 days of receipt of an application and payment of the permit application fee, the Department shall complete a technical review.
b. The permit applicant may remedy any identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
c. Within 30 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $335.
(a)
(4) (WP60) Permits for Water Pollution Control: Title 5.
1. Category: variance from Title 5 provisions for schools.
2. Description: approval of a variance from Title 5 provisions for schools pursuant to 310 CMR 15.416: Variances for Schools.
3. Schedule for timely action: or projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 30 days of receipt of an application and payment of the permit application fee, the Department shall complete a technical review.
b. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
c. Within 30 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $1,940.
(a)
(5) (WP61) Permits for Water Pollution Control: Title 5.
1. Category: approval or certification of alternative systems.
2. Description:
a. Approval of alternative systems for remedial use pursuant to 310 CMR 15.284: Approval for Remedial Use, or
b. Approval of alternative systems for pilot use, provisional use, or certification for general use pursuant to 310 CMR 15.281: Purpose through 15.288: Certification of Alternative Systems for General Use.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the department shall complete an administrative review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $3,675.
(a)
(6) (WP62) Permits for Water Pollution Control: Title 5.
1. Category: determination of acceptability for the use of septic system additives, soil absorption conditioners, approval of effluent tee filters, and approval of alternative devices for grease removal.
2. Description:
a. Determination of acceptability for the use of septic system additives pursuant to 310 CMR 15.027: Prohibition of Septic System Additives, or
b. Soil absorption conditioners pursuant to 310 CMR 15.027: Prohibition of Septic System Additives, or
c. Effluent tee filters pursuant to 310 CMR 15.281: Purpose through 15.288: Certification of Alternative Systems for General Use, or
d. Alternative devices for grease removal pursuant to 310 CMR 15.230(12).
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the department shall complete an administrative review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $1,140.
(a)
(7) (WP63) Permits for Water Pollution Control: Title 5.
1. Category: disposal system construction permit for state or federal facilities.
2. Description: disposal system construction permit for new systems, upgrade of small systems, upgrade of large systems which do not trigger failure criteria at 310 CMR 15.303: Systems Failing to Protect Public Health and Safety and the Environment, and/or expansion at state or federal facilities, with or without variances which accompany the permit pursuant to 310 CMR 15.000: The State Environmental Code, Title 5: Standard Requirements for the Siting, Construction, Inspection, Upgrade and Expansion of On-site Sewage Treatment and Disposal Systems and for the Transport and Disposal of Septage.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $1,140.
(a)
(8) (WP64) Permits for Water Pollution Control: Title 5.
1. Category: approval of site use of alternative technology not included in other categories, and approval of tight tanks.
2. Description:
a. Approval of a tight tank pursuant to 310 CMR 15.260: Tight Tanks, or
b. Approval of installation of an alternative system for pilot use pursuant to 310 CMR 15.281: Purpose and 15.285: Approval for Piloting, excluding approved grease devices or systems approved pursuant to WP61 for piloting, provisional or general use, and excluding permits under WP57, or
c. Approval of installation of alternative system pursuant to 310 CMR 15.284: Approval for Remedial Use for remedial use.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Tight Tanks.
i. Within 30 days of receipt of an application and payment of the permit application fee, the permit is presumptively approved unless the Department approves the permit with conditions, denies the permit, or issues a statement of technical deficiencies.
ii. The permit applicant may remedy identified deficiencies within 30 days of the Department's statement identifying deficiencies, if any.
iii. Within 30 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
b. Installation of alternative system for pilot use or remedial use i. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative review.
ii. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
iii. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
iv. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $525.
(a)
(10) (WP66) Permits for Water Pollution Control: Title 5.
1. Category: upgrade, expansion or continued use of large systems or review determined necessary pursuant to 310 CMR 15.003(2)(b).
2. Description:
a. approval for upgrade, expansion or continued use of large systems pursuant to 310 CMR 15.003(2)(b), excluding permits W61 or WP63.
b. approval of system required by the Department pursuant to 310 CMR 15.003(2)(b).
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $1,140.
(a)
(12) (WP70) Permits for Water Pollution Control: Title 5.
1. Category: request for alternative design flow pursuant to 310 CMR 15.203(6) or approval to discharge non-sanitary wastewater to a septic system pursuant to 310 CMR 15.004(4).
2. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 48 days of receipt of an application and payment of the permit application fee, the Department shall complete a technical review.
b. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
c. Within 24 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
3. Permit application fee: $700.
(a)
(13) (WP75) Permits for Water Pollution Control: Title 5.
1. Category: modification or renewal of alternative systems.
2. Description:
a. Modification or renewal of alternative systems for remedial use pursuant to

310 CMR 15.284: Approval for Remedial Use, or

b. Modification or renewal of alternative systems for pilot use, provisional use, or certification for general use, pursuant to 310 CMR 15.281: Purpose through 15.288: Certification of Alternative Systems for General Use.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the department shall complete an administrative review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $ 2,160.

Sanitary Groundwater Discharges

(l) (WP11) Permits for water pollution control: groundwater discharges.
1. Category: permit modification or renewal, with plan approval.
2. Description: permit renewal or major modification with plan approval pursuant to 314 CMR 5.12: Modification, Suspension, Revocation, Renewal, and Transfer of Permits and reclaimed water pursuant to 314 CMR 20.00: Reclaimed Water Permit Program and Standards for WP05, WP06, WP08, WP10, WP79, WP84, and WP85 permits.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 36 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 30 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 60 days of the close of the period for public comment, including any public hearing, the Department shall complete a public comment review.
4. Permit application fee: $1,830.
(m) (WP12) Permits for water pollution control: groundwater discharges.
1. Category: permit modification or renewal without plan approval.
2. Description: permit renewal or major modification without plan approval pursuant to 314 CMR 5.12: Modification, Suspension, Revocation, Renewal, and Transfer of Permits and reclaimed water pursuant to 314 CMR 20.00: Reclaimed Water Permit Program and Standards for WP05, WP06, WP08, WP10, WP79, WP84, WP85 permits.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 36 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 30 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 60 days of the close of the period for public comment, including any public hearing, the Department shall complete a public comment review.
4. Permit application fee: $890.
(m)
(1) (WP79) Permits for water pollution control: groundwater discharges.
1. Category: individual sewage treatment permit.
2. Description: individual sewage treatment permit not included under WP81 pursuant to 314 CMR 5.03: Discharges Requiring a Permit.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 36 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 30 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 60 days of the close of the period for public comment, including any public hearing, the Department shall complete a public comment review.
4. Permit application fee: $5,000.
(m)
(2) (WP80) Permits for water pollution control: groundwater discharges.
1. Category: general permit or general permit renewal for specified discharges.
2. Description: general permit or general permit renewal for discharge of reject water from reverse osmosis facility, boiler blowdown, carwash, laundromat, wastewater from water purification plant and or water treatment lagoon, and point source agricultural discharge pursuant to 314 CMR 5.03: Discharges Requiring a Permit, and 310 CMR 5.13(1): Authority to Issue General Permits.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 30 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness and technical review.
b. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
c. Within 21 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
d. Within 15 days of the close of public comment period or public hearing, if any, the Department shall complete a final decision.
4. Permit application fee: $745.
(m)
(3) (WP81) Permits for water pollution control: groundwater discharges.
1. Category: small sewage treatment works general permit to discharge or general permit renewal.
2. Description: small sewage treatment work designed to receive 50,000 gpd or less general permit to discharge or renewal of general permit pursuant to 314 CMR 5.03: Discharges Requiring a Permit, and 310 CMR 5.13(1): Authority to Issue General Permits.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 30 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness and technical review.
b. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
c. Within 21 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
d. Within 15 days of the close of public comment period or public hearing, if any, the Department shall complete a final decision.
4. Permit application fee: $755.
(m)
(4) (WP82) Permits for water pollution control: groundwater discharges.
1. Category: administrative renewal of groundwater discharge permit.
2. Description: administrative renewal of groundwater discharge permit pursuant to 314 CMR 5.12(9): Administrative Renewal of Permits.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after May 1, 2020,
a. Within 45 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness and technical review.
b. The permit applicant may remedy identified deficiencies within 30 days of the Department's statement identifying deficiencies, if any.
c. Within 15 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $265.
(m)
(5) (WP83) Permits for water pollution control: groundwater discharges.
1. Category: hydrogeologic report.
2. Description: hydrogeologic report approval and authorization pursuant to 314 CMR 5. 09: Duty to Submit Hydrogeological Evaluation.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 45 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness and technical review.
b. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
c. Within 30 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $10,005.
(m)
(6) (WP84) Permits for water pollution control: groundwater discharges.
1. Category: reclaimed water system.
2. Description: reclaimed water system construction, modification, and operation pursuant to 314 CMR 20.03: Permit Requirements for Reclaimed Water Systems.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 36 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 30 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 60 days of the close of the period for public comment, including any public hearing, the Department shall complete a public comment review.
4. Permit application fee: $5,000.
(m)
(7) (WP85) Permits for water pollution control: groundwater discharges.
1. Category: other groundwater discharge individual permits.
2. Description: permit for project requiring an individual discharge permit not specifically included in category WP79 or WP80.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 36 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 30 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 60 days of the close of the period for public comment, including any public hearing, the Department shall complete a public comment review.
4. Permit application fee: $2,470.

Industrial Groundwater Discharges

(m)
(8) (WP86) Permits for Industrial Wastewater: groundwater discharge.
1. Category: permit and plan approval for Type II industrial wastewater treatment facility (formerly IW03).
2. Description: permit to discharge pursuant to 314 CMR 5.03: Discharges Requiring a Permit and authorization to construct and operate a Type II industrial wastewater treatment facility, as defined in 257 CMR 2.15: Permit for Discharge.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 120 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 120 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 72 days of the close of the period for public comment, including any public hearing, the Department shall complete a public comment review.
4. Permit application fee: $6,190.
(m)
(9) (WP87) Permits for Industrial Wastewater: groundwater discharge.
1. Category: permit and plan approval for Type I industrial wastewater treatment facility, (formerly IW05).
2. Description: permit to discharge pursuant to 314 CMR 5.03: Discharges Requiring a Permit and authorization to construct and operate a Type I industrial wastewater treatment facility, as defined in 257 CMR 2.15: Permit for Discharge.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 96 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 96 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 72 days of the close of the period for public comment, including any public hearing, the Department shall complete a public comment review.
4. Permit application fee: $3,185.
(m)
(10) (WP88) Permits for Industrial Wastewater: groundwater discharge.
1. Category: permit renewal or modification, with plan modification of industrial wastewater treatment facility; (formerly IW30).
2. Description: permit renewal or modification, with plan modification, for facility holding permit IW03, IWP05, WP86, or WP87.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the department shall complete an administrative completeness review.
b. Within 88 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 88 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 72 days of the close of the period for public comment including any period for public hearing, the Department shall complete a public comment review.
4. Permit application fee: $1,445.
(m)
(11) (WP89) Permits for Industrial Wastewater: groundwater discharge.
1. Category: permit renewal or modification, without plan modification of industrial wastewater treatment facility (formerly IW31).
2. Description: permit renewal or modification, without plan modification, for facility holding permit IW03, IW05, WP86, or WP87.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 72 days of the close of the period for public comment, including any period for public hearing, the Department shall complete a public comment review.
4. Permit application fee: $645.
(m)
(12) (WP90) Permits for Industrial Wastewater: groundwater discharge.
1. Category: plan approval modification for industrial wastewater treatment system (formerly IW32).
2. Description: plan approval modification for facility holding permit IW03, IW05, WP86, or WP87.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $940.

Treatment Works Plan Approval

(n) (WP68) Permits for Water Pollution Control: treatment works plan approval.
1. Category: treatment works plan approval.
2. Description: plan approval for a new facility or plan approval for modifications to existing facilities with permitted discharges to the ground or surface water pursuant to 310 CMR 5.00: Ground Water Discharge Permit Program.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
3. Permit application fee: $970.

Holding Tanks

(o) (WP56) Permits for Holding Tanks.
1. Category: certification of industrial wastewater holding tank pursuant to M.G.L. c. 21, § 27, and 314 CMR 18.10: Certification.
2. Description: certification covers new industrial wastewater holding tank installation and conversion of existing tanks into industrial wastewater holding tanks.
3. Schedule for timely action: for projects for which application is filed and fees received on or after May 1, 2020,
a. Within 30 days of receipt of an application and payment of the application fee, the Department shall complete an administrative review.
b. Within 30 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any,
d. Within 30 days of receipt of materials in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review. In the absence of a written decision, the certification shall be presumptively approved.
4. Permit application fee: $140.

Sewer Connections/Extensions

(y) (WP91) Permits for water pollution control: sewer connections/extensions.
1. Category: sewer connection/ extension.
2. Description: sewer connection permit as determined by the Department permit pursuant to 314 CMR 7.03(3).
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 90 days of receipt of an application and payment of the permit application fee, the Department shall complete a technical review.
b. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
c. Within 45 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
d. Within 20 days of the close of the period for public comment, including a public hearing, if any, the Department shall complete a public comment review.
4. Permit application fee: $3,000.
(z) (WP92) Permits for industrial sewer connections.
1. Category: sewer connection.
2. Description: permit pursuant to 314 CMR 7.03(2).
3. Schedule for timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 45 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness and technical review.
b. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any.
c. Within 45 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
d. Within 20 days of the close of the period for public comment, including a public hearing, if any, the Department shall complete a public comment review.
4. Permit application fee: $1,795.

Residuals Management

(aa) (WP28) Permits for water pollution control: residuals management.
1. Category: approval of sampling and analysis plan for land application of residuals, as required prior to classification and permit for land application.
2. Description: approval of sampling and analysis plan pursuant to 310 CMR 32.00: Land Application of Sludge and Septage for beneficial use of sludge, sludge products or septage.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $860.
(bb) (WP29) Permits for water pollution control: residuals management.
1. Category: determination of suitability for land application of residuals.
2. Description: classification of sludge, sludge products, or septage prior to land application for beneficial use, pursuant to 310 CMR 32.00: Land Application of Sludge and Septage.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 72 days of the close of the period for public comment, including any public hearing, the Department shall complete a public comment review.
4. Permit application fee: $3,500.
(cc) (WP30) Permits for water pollution control: residuals management.
1. Category: certification pursuant to 310 CMR 32.00: Land Application of Sludge and Septage of major projects for land application of sludge, sludge products, or septage.
2. Description: land application certification for Type 2 or Type 3 classified residuals, for projects of 0.5 acres or more.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 72 days of the close of the period for public comment, including any public hearing, the Department shall complete a public comment review.
4. Permit application fee: $2,910.
(dd) (WP31) Permits for water pollution control: residuals management.
1. Category: certification pursuant to 310 CMR 32.00: Land Application of Sludge and Septage of minor projects for land application of sludge, sludge products, or septage.
2. Description: land application certification for Type 2 or Type 3 classified residuals, for projects of less than 0.5 acre.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 72 days of the close of the period for public comment, including any public hearing, the Department shall complete a public comment review.
4. Permit application fee: $755.
(ee) (WP32) Permits for water pollution control: residuals management.
1. Category: renewal or modification of certification pursuant to 310 CMR 32.00: Land Application of Sludge and Septage of projects for land application of sludge, sludge products, or septage.
2. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 48 days of the close of the period for public comment, including any public hearing, the Department shall complete a public comment review.
4. Permit application fee: $315.
(ff) (WP33) Permits for water pollution control: residuals management.
1. Category: approval of wastewater treatment residuals landfill, pursuant to M.G.L. c. 21, § 27 or § 43(2), M.G.L. c. 83, §§ 6 and 7, or M.G.L. c. 21A, § 13, 314 CMR 5.00: Ground Water Discharge Permit Program or 3.00: Surface Water Discharge Permit Program, or 7.00: Sewer System Extension and Connection Permit Program.
2. Schedule of timely action: for applications received on or after March 24, 2017, individual rule project subject to 310 CMR 4.05.
3. Permit application fee: for projects for which applications are filed and fees received on or after March 24, 2017, individual rule project subject to 310 CMR 4.05.
(gg) (WP34) Permits for water pollution control: residuals management.
1. Category: approval of closure of wastewater treatment residuals landfill, pursuant to M.G.L. c. 21, §§ 27 and 43(2), M.G.L. c. 83, §§ 6 and 7, M.G.L. c. 21A, § 13 or 314 CMR 3.00: Surface Water Discharge Permit Program, 5.00: Ground Water Discharge Permit Program, or 7.00: Sewer System Extension and Connection Permit Program.
2. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
3. Permit application fee: $8,745.
(hh) (WP35) Permits for water pollution control: residuals management.
1. Category: approval of design plans and specifications for residuals management facilities, pursuant to M.G.L. c. 21, § 27 or § 43(2), M.G.L. c. 83, §§ 6 and 7, or M.G.L. c. 21A, § 13 or 314 CMR 12.00: Operation and Maintenance and Pretreatment Standards for Wastewater Treatment Works and Indirect Dischargers.
2. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 120 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 120 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
e. Within 72 days of the close of the period for public comment, including any public hearing, the Department shall complete a public comment review.
3. Permit application fee: $5,350.
(ii) (WP44) Permits for water pollution control: residuals management.
1. Category: modifications to permits for residuals landfills.
2. Description: modifications to existing approvals including but not limited to changes in design, operation, and monitoring plans.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
3. Permit application fee: $2,180.
(jj) (WP45) Permits for water pollution control: residuals management.
1. Category: modifications to residuals management facilities.
2. Description: modifications to existing plan approvals for all residual management facilities excluding residual landfills, but including and not limited to revisions to design, operation, monitoring, and material processing operations.
2. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
3. Permit application fee: $1,280.
(kk) (WP93) Permits for water pollution control: residuals management.
1. Category: renewal for land application of Type I residuals.
2. Description: renewal of Type I approval pursuant to 310 CMR 32.13(11).
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017, (see 310 CMR 32.13(11)) for the terms of presumptive approval),
a. Within 45 days of receipt of an application and payment of the permit application fee, the Department shall complete a technical review.
b. The permit applicant may remedy any identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
c. Within 45 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $1,700.

Wastewater Treatment Plant Operators

(pp) (WP47) Permits for water pollution control: licenses for wastewater treatment plant operators.
1. Category: certification through reciprocity.
2. Description: certifications for the seven grades of wastewater treatment plant operators pursuant to 257 CMR 2.00: Certification of Operators of Wastewater Treatment Facilities by reciprocity review and status.
3. Schedule for timely action: for certifications for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the application fee, the Board shall complete an administrative review.
b. Within 24 days of making a determination of administrative completeness, the Board shall complete a technical review.
c. The applicant may remedy identified deficiencies within 30 days of the Board statement of deficiencies.
d. Within 24 days of receipt of materials from the applicant in response to a statement identifying deficiencies, the Board shall complete a supplemental technical review.
4. Permit application fee: $95.
(qq) (WP48) Permits for water pollution control: licenses for wastewater treatment plant operators.
1. Category: emergency and provisional certifications.
2. Description: approval of emergency and provisional certifications for the seven grades of wastewater treatment plant operators pursuant to 257 CMR 2.00: Certification of Operators of Wastewater Treatment Facilities.
3. Schedule for timely action: for certifications for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the application fee, the Board shall complete an administrative review.
b. Within 24 days of making a determination of administrative completeness, the Board shall complete a technical review.
c. The applicant may remedy identified deficiencies within 30 days of the Board statement of deficiencies.
d. Within 24 days of receipt of materials from the applicant in response to a statement identifying deficiencies, the Board shall complete a final technical review.
4. Permit application fee: $35.
(8) Wetlands and Waterways

Waterways Permits

(a) (WW01) Permits for waterways.
1. Category: waterways license or permit: water-dependent use projects.
2. Description: license or permit pursuant to 310 CMR 9.04: Geographic Areas Subject to Jurisdiction, 314 CMR 9.05: Activities Subject to Jurisdiction, and 9.11(2)(a).
3. Schedule for timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 30 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative review.
b. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
c. Within 30 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental administrative review.
d. Within 60 days of the close of the public comment period and notification by the applicant that the public notice has been published, the Department shall complete a technical review by issuing a statement of deficiencies or a written document ending this review timeline pursuant to 310 CMR 4.00.
e. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
f. Within 60 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review and issue a written document ending this review timeline pursuant to 310 CMR 4.00.
4. Permit application fee:
a. Residential water-dependent use projects for four dwelling units or less: $215.
b. Other water-dependent use projects: $330.
c. Licenses with extended terms, or facilities described in 310 CMR 9. 00: Waterways: $3,350.
(a)
(1) (WW14) Permits for waterways.
1. Category: waterways license or permit for nonwater-dependent projects with partial initial application.
2. Description: license or permit pursuant to 310 CMR 9.04: Geographic Areas Subject to Jurisdiction and 9.05: Activities Subject to Jurisdiction, when an applicant initially submits a partial application and completes the application after the public hearing.
3. Schedule for timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 45 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative review.
b. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
c. Within 45 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental administrative review.
d. Within 90 days of the close of the public comment period and notification by the applicant that the public notice has been published, the Department shall complete a technical review by issuing a statement of deficiencies or a written determination ending this timeline pursuant to 310 CMR 4.00.
e. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
f. Within 60 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review by issuing a written determination ending this timeline pursuant to 310 CMR 4.00.
4. Permit application fee:
a. Residential nonwater-dependent use projects for four dwelling units or less: $665.
b. Other nonwater-dependent use projects: $2,005.
c. Licenses with extended terms, or facilities described in 310 CMR 9.16(3)(b)2.: $3,350.
(a)
(2) (WW15) Permits for waterways
1. Category: non-water Dependent project with initial full application.
2. Description: license or permit pursuant to 310 CMR 9.04: Geographic Areas Subject to Jurisdiction and 9.05: Activities Subject to Jurisdiction, when an applicant initially submits a partial application and completes the application after the public hearing.
3. Schedule for timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 45 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative review.
b. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
c. Within 45 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental administrative review.
d. Within 60 days of the close of the public comment period and notification by the applicant that the public notice has been published, the Department shall complete a technical review by issuing a statement of deficiencies or a written determination ending this timeline pursuant to 310 CMR 4.00.
e. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
f. Within 60 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review by issuing a written determination ending this timeline pursuant to 310 CMR 4.00.
4. Permit application fee:
a. Residential nonwater-dependent use projects for four dwelling units or less: $665
b. Other nonwater-dependent use projects: $2,005.
c. Licenses with extended terms, or facilities described in 310 CMR 9.16(3)(b)2.: $3,350.
(a)
(3) (WW16) Permits for waterways
1. Category: waterways license or permit for nonwater-dependent projects within a Municipal Harbor Plan.
2. Description: license or permit pursuant to 310 CMR 9.04: Geographic Areas Subject to Jurisdiction and 9.05: Activities Subject to Jurisdiction, within an area subject to a Municipal Harbor Plan approved under 301 CMR 23.00: Review and Approval of Municipal Harbor Plans.
3. Schedule for timely action: for projects for which applications are filed and/or fees received on or after, March 24, 2017,
a. Within 45 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative review.
b. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
c. Within 45 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental administrative review.
d. Within 75 days of the close of the public comment period and notification by the applicant that the public notice has been published, the Department shall complete a technical review by issuing a statement of deficiencies or a written determination ending this timeline pursuant to 310 CMR 4.00.
e. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
f. Within 45 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review and issue final written determination ending this timeline pursuant to 310 CMR 4.00.
4. Permit application fee:
a. Residential nonwater-dependent use projects (for four dwelling units or less): $665.
b. Other nonwater-dependent use projects: $2,005.
c. Licenses with extended terms, or facilities described in 310 CMR 9.16(3)(b)2.: $3,350.
(a)
(4) (WW17) Permits for waterways.
1. Category: waterways license or permit for nonwater-dependent projects with Joint MEPA Application.
2. Description: license or permit when applicants file a Final Environmental Impact Report under 301 CMR 11.07(4) that serves as an application meeting the requirements of 310 CMR 9.11(3)(a) through (c): Appraisal Procedure.
3. Schedule for timely action: for projects for which applications are filed and/or fees received on or after, March 24, 2017,
a. Within 90 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative review.
b. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
c. Within 25 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental administrative review.
d. Within 30 days of the close of the public comment period and notification by the applicant that the public notice has been published, the Department shall complete a technical review by issuing a statement of deficiencies or a written determination ending this timeline pursuant to 310 CMR 4.00.
e. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
f. Within 30 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review and issue a written determination ending this timeline pursuant to 310 CMR 4.00.
4. Permit application fee:
a. Residential nonwater-dependent use projects for four dwelling units or less: $665.
b. Other nonwater-dependent use projects: $2,005.
c. Licenses with extended terms, or facilities described in 310 CMR 9.16(3)(b)2.: $3,350.
(c) (WW03) Permits for waterways.
1. Category: amendment of waterways license or permit.
2. Description: amendment of license or permit pursuant to 310 CMR 9.04: Geographic Areas Subject to Jurisdiction and 9.05: Activities Subject to Jurisdiction.
3. Schedule for timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 30 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative review.
b. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
c. Within 30 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental administrative review.
d. Within 60 days of the close of the public comment period and notification by the applicant that the public notice has been published, the Department shall complete a technical review by issuing a statement of deficiencies or a written document ending this timeline pursuant to 310 CMR 4.00.
e. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
f. Within 60 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review by issuing a written document ending this timeline pursuant to 310 CMR 4.00.
4. Permit application fee:
a. Residential water-dependent use projects for four dwelling units or less: $100.
b. Other water-dependent use projects: $125.
c. Residential nonwater-dependent use projects for four dwelling units or less: $530.
d. Other nonwater-dependent use projects: $1,000.
e. Licenses with extended terms, or facilities described in 310 CMR 9.16(3)(b)2.: $1,335.
(d) (WW04) Permits for waterways.
1. Category: determinations of applicability pursuant to 310 CMR 9.06: Requests for Determination of Applicability.
2. Schedule for timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review in accordance with the standards of 310 CMR 9.06(1) and (2).
b Within 48 days of making a determination of administrative completeness, or of the close of any public comment period pursuant to 310 CMR 9.06(3), the Department shall complete a technical review.
c. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
3. Permit application fee: $100.
(e) (WW05) Permits for waterways.
1. Category: certificates of compliance pursuant to 310 CMR 9.19: Certificate of Compliance.
2. Schedule for timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review in accordance with the standards of 310 CMR 9.16: Fees and 9.19: Certificate of Compliance.
b. Within 292 days of making a determination of administrative completeness, the Department shall complete its technical review.
c. If the Department has required changes as necessary to bring the project into compliance, the Department will complete technical review within 146 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies.
3. Permit application fee:
a. Water-dependent use projects, except facilities described in 310 CMR 9.16(3)(b)2.: $100.
b. Nonwater-dependent use projects: $215.
c. Licenses with extended terms, or facilities described in 310 CMR 9.16(3)(b)2.: $430.
(f) (WW06) Permits for waterways.
1. Category: waterways license, small structures accessory to residences.
2. Description: license for small dock/pier projects meeting the requirements of 310 CMR 9.10(1): Projects Eligible for Simplified Procedures.
3. Schedule for timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
c. Within 24 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental administrative review.
d. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review by issuing a statement of deficiencies or a written document ending this timeline pursuant to 310 CMR 4.00.
e. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
f. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review and issue a written document ending this timeline pursuant to 310 CMR 4.00.
4. Permit application fee: $75.
(f)
(1) (WW12) Permits for waterways.
1. Category: Waterways License renewal, small structures accessory to residences.
2. Description: license renewal for small dock/pier projects meeting the requirements of 310 CMR 9.10(6): Renewal and Transfer of Licenses from the Department.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
c. Within 24 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental administrative review.
d. Within 48 days of notification by the applicant that the public notice has been published or the close of the public comment period, whichever is later, the Department shall complete a technical review.
e. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
f. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $35.
(f)
(2) (WW24) Permits for waterways.
1. Category: waterways general license, small structures accessory to residences.
2. Description: certification under the general license for small dock/pier projects meeting the requirements of 310 CMR 9.29(2): Projects Eligible for General License Certification.
3. Schedule for timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 60 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
c. Within 45 days of making a determination of administrative completeness, the Department shall complete a technical review.
4. Permit application fee: $75.
(f)
(3) (WW25) permits for waterways.
1. Category: permits for test projects.
2. Description: Permits for in situ testing of water-dependant pilot technologies pursuant to 310 CMR 9.30: Permitting of Test Projects.
3. Schedule for timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
c. Within 24 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental administrative review.
d. Within 30 days of making a determination of administrative completeness, the Department shall complete a technical review.
e. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
f. Within 30 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $440.

Water Quality Certifications

(g) (WW07) Permits for wetlands and waterways.
1. Category: water quality certifications for major dredging projects.
2. Description: Water Quality Certification pursuant to 314 CMR 9.00: 401 Water Quality Certification for Discharge of Dredged or Fill Material, Dredging, and Dredged Material Disposal in Waters of the United States Within the Commonwealth for major dredging and dredge material disposal projects, limited to projects involving dredging of 5,000 cubic yards (c.y.) or greater.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 96 days of making a determination of administrative completeness, the Department shall complete a technical review, including public comment review, if any.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 96 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review, including public comment review.
4. Permit application fee: $490.
(h) (WW08) Permits for wetlands and waterways.
1. Category: water quality certifications for minor dredging projects.
2. Description: Water Quality Certification pursuant to 314 CMR 9.00: 401 Water Quality Certification for Discharge of Dredged or Fill Material, Dredging, and Dredged Material Disposal in Waters of the United States Within the Commonwealth for minor dredging and dredge material disposal projects, limited to projects involving dredging less than 5,000 c.y. but more than 100 c.y.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review, including public comment review, if any.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review, including public comment review.
4. Permit application fee: $95.
(i) (WW09) Permits for wetlands and waterways.
1. Category: amendment of water quality certifications for dredging projects.
2. Description: amendment of Water Quality Certification pursuant to 314 CMR 9.00: 401 Water Quality Certification for Discharge of Dredged or Fill Material, Dredging, and Dredged Material Disposal in Waters of the United States Within the Commonwealth for dredging and dredge material disposal projects.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review, including public comment review, if any.
c. The permit applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
d. Within 48 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review, including public comment review.
4. Permit application fee:
a. Increase in dredge volume by 50% or less with no change in dredge footprint: $90.
b. Change in dredge or disposal construction methods or plans: $190.
c. Change in one or more certification conditions relating to dredging or disposal: $280.
(j) (WW10) Permits for wetlands & waterways.
1. Category: water quality certifications for major projects.
2. Description: Water Quality Certification pursuant to 314 CMR 9.00: 401 Water Quality Certification for Discharge of Dredged or Fill Material, Dredging, and Dredged Material Disposal in Waters of the United States Within the Commonwealth for major fill and excavation projects in waters and wetlands, except for those exempted under the provisions of 314 CMR 9.03: Activities Not Requiring an Application. Major fill and excavation projects are limited to projects:
a. with a cumulative loss of more than 5,000 sq. ft. loss of bordering and isolated vegetated wetland and land under water, except for routine maintenance projects meeting the criteria of 314 CMR 9.04(5): Routine Maintenance and agricultural limited projects meeting the criteria of 314 CMR 9.04(1): More than 5000 sq. ft.; or
b. with a loss of any amount of vegetated wetland or land under water involving:
i. Outstanding Resource Waters;
ii. rare species in Isolated Vegetated Wetland;
iii. salt marsh;
iv. an individual 404 Permit;
v. activities where the Department invokes discretionary authority pursuant to 314 CMR 9.04(11): Discretionary Authority to require an application for an individual Water Quality Certification.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 96 days of making a determination of administrative completeness, the Department shall complete a technical review, including public comment review, if any.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 96 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review, including public comment review.
4. Permit application fee: $490.
(k) (WW11) Permits for wetlands & waterways.
1. Category: water quality certifications for minor projects.
2. Description: Water Quality Certification pursuant to 314 CMR 9.00: 401 Water Quality Certification for Discharge of Dredged or Fill Material, Dredging, and Dredged Material Disposal in Waters of the United States Within the Commonwealth for minor fill and excavation projects in waters and wetlands, except for those exempted under the provisions of 314 CMR 9.03: Activities Not Requiring an Application. Minor fill and excavation projects are limited to projects:
a. with a cumulative loss of less than 5000 sq. ft. loss of bordering and isolated vegetated wetland and land under water, involving:
i. real estate subdivisions required to file applications for individual water quality certifications under the provisions of 314 CMR 9.04(3): Real Estate Subdivision;
ii. activities exempt under M.G.L. c. 131, § 40 under the provisions of 314 CMR 9.04(4): Activities Exempt under M.G.L. c. 131, § 40;
iii. any activity subject to the provisions of 314 CMR 9.04(13);
b. with a cumulative loss of more than 5,000 sq. ft. of vegetated wetland or land under water involving routine maintenance meeting the criteria of 314 CMR 9.04(5): Routine Maintenance; and
c. with any cumulative loss of vegetated wetland or land under water involving an agricultural limited projects meeting the criteria of 314 CMR 9.04(10): Activities Exempt under M.G.L. c. 131, § 40.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of making a determination of administrative completeness, the Department shall complete a technical review, including public comment review, if any.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review, including public comment review.
4. Permit application fee: $95.

Combined Permits

(k)
(1) (WW26) Combined permits for waterways and water quality certifications.
1. Category: combined permits for waterways and water quality certifications.
2. Description: combined permit for water quality certification and waterways license pursuant to 314 CMR 9.00: 401 Water Quality Certification for Discharge of Dredged or Fill Material, Dredging, and Dredged Material Disposal in Waters of the United States Within the Commonwealth and 310 CMR 9.00: Waterways.
3. Schedule for timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 30 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative review.
b. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
c. Within 30 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental administrative review.
d. Within 96 days of the close of the public comment period and notification by the applicant that the public notice has been published, the Department shall complete a technical review.
e. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
f. Within 96 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: the application fee is the sum of fees associated with each individual permit category included in the combined permit. Eligible categories include WW07, $490, WW08, $95, WW10, $490, WW11, $95, WW01a, $215, and WW01b, $330.
(k)
(2) (WW27) Combined permit amendment for waterways and water quality certifications.
1. Category: combined permit amendment for waterways and water quality certifications.
2. Description: combined permit amendment for water quality certification (WW09) and waterways license (WW03) pursuant to 314 CMR 9.00: 401 Water Quality Certification for Discharge of Dredged or Fill Material, Dredging, and Dredged Material Disposal in Waters of the United States Within the Commonwealth and 310 CMR 9.00: Waterways.
3. Schedule for timely action: for projects for which applications are filed and/or fees received on or after March 24, 2017,
a. Within 30 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative review.
b. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
c. Within 30 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental administrative review.
d. Within 60 days of the close of the public comment period and notification by the applicant that the public notice has been published, the Department shall complete a technical review.
e. The applicant may remedy identified deficiencies within 60 days of the Department's statement identifying deficiencies, if any.
f. Within 60 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee: $302.

Wetlands

(m) (WW13) Permits for wetlands.
1. Category: permits for renovation of abandoned cranberry bogs.
2. Description: permits pursuant to 310 CMR 23.00: Renovation of Abandoned Cranberry Bogs for renovation of abandoned cranberry bogs.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 72 days of the close of the public comment or administrative completeness period or public hearing, if any, whichever occurs later, the Department shall complete a technical review.
c. The permit applicant may remedy identified deficiencies within 180 days of the Department's statement identifying deficiencies, if any.
d. Within 72 days of receipt of materials from the applicant in response to the Department's statement identifying deficiencies or the close of public hearing, if any, whichever later, the Department shall complete a supplemental technical review.
4. Permit application fee: $785.
(n) (WW18) Permits for Wetlands.
1. Category: Notice of Intent and Abbreviated Notice of Intent.
2. Description: Notice of Intent and Abbreviated Notice of Intent pursuant to M.G.L. c. 131, § 40 and 310 CMR 10.05(4): Notices of Intent. The designation of the Department's file number shall not imply that the plans and supporting documents have been judged adequate for the issuance of an Order, but only that copies of the minimum submittal requirements contained in the general instructions have been filed.
3. Schedule for timely action: for projects for which Notices of Intent or Abbreviated Notices of Intent are filed and fees received on or after March 24, 2017,
a. Within 21 days of receipt of a Notice of Intent or Abbreviated Notice of Intent and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. The permit applicant may remedy identified deficiencies within 21 days of the Department's statement identifying deficiencies, if any.
c. Within 21 days of the Department's receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a final review resulting in a decision to issue or deny a file number.
4. Permit application fee: The fee, created pursuant to M.G.L. c. 131, § 40, is for work proposed under a single Notice of Intent. When the application involves more than one activity the fee shall be determined by adding the fees for each proposed activity, except that when work involves activities within the riverfront area as well as another resource area, the fee shall be determined by adding an additional 50% to the fee calculated for activities in another resource area(s) or the buffer zone to another resource area for each of the proposed activities within the riverfront area:
a. Category 1: $110
b. Category 2: $500
c. Category 3: $1050
d. Category 4: $1450
e. Category 5: $4 per linear foot f. Category 6: $2 per linear foot with a maximum of $200 for a single-family house project and a maximum of $2000 for any other activity.
(o) (WW19) Permits for Wetlands.
1. Category: Superseding Determination of Applicability.
2. Description: Superseding Determination of Applicability pursuant to 310 CMR 10.05(3)(c): Appeal to the Department.
3. Schedule: for projects for which Requests for Superseding Determination of Applicability are filed and fees received on or after March 24, 2017,
a. Within 70 days of receipt of Request for Superseding Determination of Applicability and payment of the application fee, the Department shall complete technical review.
b. The permit applicant may remedy identified deficiencies within 70 days of the Department's statement identifying deficiencies, if any.
c. Within 40 days of the Department's receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental review.
4. Permit application fee: $120.
(p) (WW20) Permits for Wetlands.
1. Category: Superseding Order of Conditions.
2. Description: Superseding Order of Conditions pursuant to 310 CMR 10.05(7): Requests for Actions by the Department (Appeals).
3. Schedule: for projects for which Requests for Superseding Order of Conditions are filed and fees received on or after March 24, 2017,
a. Within 70 days of receipt of Request for Superseding Order of Conditions and payment of the application fee, the Department shall complete technical review.
b. The permit applicant may remedy identified deficiencies within 70 days of the Department's statement identifying deficiencies, if any.
c. Within 40 days of the Department's receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental review.
4. Permit application fee:
a. Superseding Order of Conditions for individual single-family homes with associated structures: $120.
b. All Other Superseding Order of Conditions: $245.
(q) (WW21) Permits for Wetlands.
1. Category: Superseding Order of Resource Area Delineation.
2. Description: Superseding Order of Resource Area Delineation pursuant to 310 CMR 10.05(7): Requests for Actions by the Department (Appeals).
3. Schedule: for projects for which Requests for Superseding Order of Resource Area Delineation are filed and fees received on or after March 24, 2017,
a. Within 70 days of receipt of Request for Superseding Determination of Applicability and payment of the application fee, the Department shall complete technical review.
b. The permit applicant may remedy identified deficiencies within 70 days of the Department's statement identifying deficiencies, if any.
c. Within 40 days of the Department's receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental review.
4. Permit application fee: $120.
(r) (WW22) Permits for Wetlands.
1. Category: Request for Variance.
2. Description: Variance pursuant to 310 CMR 10.05(10): Variance.
3. Schedule: for projects for which Requests for Variance are filed and fees received on or after March 24, 2017,
a. Within 70 days of receipt of Request for Variance and payment of the application fee, the Department shall complete technical review.
b. The permit applicant may remedy identified deficiencies within 70 days of the Department's statement identifying deficiencies, if any.
c. Within 40 days of the Department's receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental review.
4. Permit application fee: $9,830.
(s) (WW23) Permits for Wetlands.
1. Category: Request for Variance with a claim of unconstitutional taking of property.
2. Description: Variance with a claim of unconstitutional taking of property pursuant to 310 CMR 10.05(10): Variance.
3. Schedule: for projects for which Requests for Variance are filed and fees received on or after March 24, 2017,
a. Within 70 days of receipt of Request for Variance and payment of the application fee, the Department shall complete technical review.
b. The permit applicant may remedy identified deficiencies within 70 days of the Department's statement identifying deficiencies, if any.
c. Within 40 days of the Department's receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental review.
4. Permit application fee: $245.
(9) Laboratory Certification
(a) (LES01EA) Permits for laboratory certification.
1. Category: initial certification for microbiology laboratory.
2. Description: initial certification of laboratory for microbiology analyses pursuant to 310 CMR 42.05(1)(a): Microbiology and (2)(a): Microbiology.
3. Schedule for timely action for applications filed after March 24, 2017,
a. Within 36 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete the technical review required prior to on-site inspection. c. The permit applicant may remedy identified deficiencies during technical review within 60 days of the Department's statement identifying deficiencies, if any. The Department shall complete review of supplemental material within 48 days.
d. Within 80 days of completing a technical review, the Department shall complete on-site inspection and post-inspection review.
e. The permit applicant may remedy deficiencies identified during inspection review within 90 days of the Department's statement identifying deficiencies, if any.
f. Within 80 days of receipt of supplemental materials from the applicant in response to the Department's statement identifying deficiencies during the inspection review period, the Department shall complete the supplemental technical review.
4. Permit application fee: $280 includes an application for one or more certifications to test potable water treatment and distribution samples for total coliform, fecal coliform, Escherichia coli, and or heterotrophic plate count; plus an amount for each testing category applied for as follows:
a. Total Coliform in Source Water: $45.
b. One or more certifications to test for Fecal Coliform in Source Water, and or Wastewater: $43.
c. One or more certifications to test for Escherichia coli in Source water, Ambient water, and or Wastewater: $45.
d. One or more certifications to test for Enterococci in Source Water, Ambient Water, and or Wastewater: $43.

Single fee includes later added certification using the same or similar method, and no modification fee is required.

e. When an out-of-state inspection of a laboratory is necessary, applicants shall be charged for on-site inspection where costs are reasonably expected to exceed $100 including necessary costs of travel, meals, and lodging, at the rate established for state employees, as determined by the Department. The Department shall promptly notify the applicant of all such costs and may require payment prior to inspection.
(b) (LES02EA) Permits for laboratory certification.
1. Category: initial certification for chemical laboratory.
2. Description: initial certification of laboratory for chemical analyses pursuant to 310 CMR 42.00: Certification and Operation of Environmental Analysis Laboratories.
3. Schedule for timely action for applications filed after March 24, 2017,
a. Within 36 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete the technical review required prior to on-site inspection.
c. The permit applicant may remedy identified deficiencies during technical review within 60 days of the Department's statement identifying deficiencies, if any, and the Department shall complete review of supplemental material within 48 days.
d. Within 80 days of completing a technical review, the Department shall complete on-site inspection and post-inspection review.
e. The permit applicant may remedy deficiencies identified during inspection review within 90 days of the Department's statement identifying deficiencies, if any.
f. Within 80 days of receipt of supplemental materials from the applicant in response to the Department's statement identifying deficiencies during the inspection review period, the Department shall complete the supplemental technical review.
4. Permit application fee: $1,055 plus an amount for each certification category as follows:
a. Single Fee for one or both of potable water or non-potable water chemistry certifications for a single analyte category listed in group a. Single fee includes later added potable or nonpotable component using the same or similar method. Later addition of a component will not require a modification fee.

Alkalinity, Total

$40

Calcium

$65

Chloride

$35

Chlorine, Residual

$35

Cyanide

$90

Fluoride

$65

Metals: one or more of aluminum, antimony, arsenic, barium, beryllium, cadmium, chromium, cobalt, copper, iron, lead, manganese, mercury, molybdenum, nickel, selenium, silver, strontium, thallium, titanium, vanadium, zinc. Single fee includes later added certification using the same or similar method and no modification fee.

$230

Nitrate-N

$65

Perchlorate

$95

pH

$18

Sodium

$65

Sulfate

$55

Total Dissolved Solids

$40

Volatile Organic Compounds, including vinyl chloride

$140

b. Chemistry Certification for Potable Water Only

Adipate/Phthalates

$90

Asbestos

$90

Benzo-a-pyrene

$110

Bromate

$60

Carbamates: aldicarb, aldicarb sulfone, aldicarb sulfoxide, carbofuran, Vydate. Single fee includes later added certifications using the same or similar method and no modification fee

$90

Chlorite

$60

1,4-Dioxane

$110

Diquat

$70

EDB (1,2-Dibromoethane) and

DBCP (1,2-Dibromo-3-chloropropane)

$70

Endothall

$70

Glyphosate

$60

Haloacetic Acids

$100

Herbicides: 2,4-D; 2,4,5-TP; dalapon, dinoseb, pentachlorophenol, picloram. Single fee includes later added certifications using the same or similar method and no modification fee.

$110

Nitrite-N

$55

Polychlorinated biphenyls

$110

Pesticides: alachlor, atrazine, chlordane, endrin, heptachlor, heptachlor epoxide, hexachlorobenzene, hexachlorocyclopentadiene, lindane, methoxychlor, simazine, and toxaphene. Single fee includes later added certifications using the same or similar method and no modification fee

$110

Per- and Polyfluoroalkly substances (PFAS)

$100

Radiochemistry

Gross alpha and gross beta

$45

Strontium-89 and Strontium-90

$70

Radium-226 and Radium-228

$60

Tritium

$60

Uranium

$60

Iodine-131

$60

Cesium-134 and Cesium-137

$60

Cobalt-60

$70

Ruthenium-106

$60

Trihalomethanes

$70

Turbidity

$35

c. Chemistry Certification for Non-Potable Water Only

Ammonia-N

$70

Biochemical Oxygen Demand

$55

Chemical Oxygen Demand

$35

Hardness, total

$35

Kjeldahl-N

$70

Magnesium

$55

Oil and Grease

$55

Orthophosphate

$70

Polychlorinated biphenyls (water)

$110

Polychlorinated biphenyls (oil)

$110

Pesticides: aldrin, alpha-BHC, beta-BHC, delta-BHC, gamma-BHC, chlordane, 4,4'-DDD, 4,4'-DDE, 4,4'-DDT, dieldrin, endosulfan I, endosulfan II, endosulfan sulfate, endrin, endrin aldehyde, heptachlor, heptachlor epoxide, and toxaphene. Single fee includes later added certifications using the same or similar method, and no modification fee.

$110

Phenols, total

$55

Phosphorus, total

$70

Potassium

$55

Residue, Non-filterable

$35

Semi-volatile Organic Compounds: Acid Extractables and Base/Neutral Extractables. Single fee includes later added certifications using the same or similar method, and no modification fee.

$140

Specific Conductivity

$35

Total Organic Carbon

$35

d. When an out-of-state inspection of a laboratory is necessary, applicants shall be charged for on-site inspection where costs are reasonably expected to exceed $100 including necessary costs of travel, meals, and lodging, at the rate established for state employees, as determined by the Department. The Department shall promptly notify the applicant of all such costs and may require payment prior to inspection.
(c) (LES03EA) Permits for laboratory certification.
1. Category: modification of certification for chemical laboratory.
2. Description: application to certify additional testing categories pursuant to 310 CMR 42.00: Certification and Operation of Environmental Analysis Laboratories.
3. Schedule for timely action for applications filed and fees received after March 24, 2017,
a. Within 36 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete the technical review required prior to on-site inspection. c. The permit applicant may remedy identified deficiencies during technical review within 60 days of the Department's statement identifying deficiencies and the Department shall complete review of supplemental material within 48 days.
d. Within 80 days of completing a technical review, the Department shall complete on-site inspection and post-inspection review.
e. The permit applicant may remedy deficiencies identified during the inspection review period within 90 days of the Department's statement identifying deficiencies, if any.
f. Within 80 days of receipt of supplemental materials from the applicant in response to the Department's statement identifying deficiencies during the inspection review period, the Department shall complete the supplemental technical review.
4. Certificate modification permit fee:
a. The certificate modification permit fee shall include $385 plus an amount for each testing category included in the application in the amounts as set forth in 310 CMR 4.10(9)(b).
b. When an out-of-state inspection of a laboratory is necessary, applicants shall be charged for on-site inspection where costs are reasonably expected to exceed $100 including necessary costs of travel, meals, and lodging, at the rate established for state employees, as determined by the Department. The Department shall promptly notify the applicant of all such costs and may require payment prior to inspection.
(d) (LES04EA) Permits for laboratory certification.
1. Category: modification of certification for microbiological laboratory.
2. Description: application to certify additional testing categories pursuant to 310 CMR 42.05(1)(a): Microbiology and 310 CMR 42.05(2)(a): Microbiology.
3. Schedule for timely action for applications filed and fees received after March 24, 2017,
a. Within 36 days of receipt of an application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete the technical review required prior to on-site inspection.
c. The permit applicant may remedy identified deficiencies during technical review within 60 days of the Department's statement identifying deficiencies and the Department shall complete review of supplemental material within 60 days.
d. Within 80 days of completing a technical review, the Department shall complete on-site inspection and post-inspection review.
e. The permit applicant may remedy deficiencies identified during the inspection review period within 90 days of the Department's statement identifying deficiencies, if any.
f. Within 80 days of receipt of supplemental materials from the applicant in response to the Department's statement identifying deficiencies during the inspection review period, the Department shall complete the supplemental technical review.
4. Permit application fee:
a. $220 plus an amount for each testing category included in the application in the amounts as set forth in 310 CMR 4.10(9)(a).
b. When an out-of-state inspection of a laboratory is necessary, applicants shall be charged for on-site inspection where costs are reasonably expected to exceed $100 including necessary costs of travel, meals, and lodging, at the rate established for state employees, as determined by the Department. The Department shall promptly notify the applicant of all such costs and may require payment prior to inspection.
(10) Waste Site Cleanup
(g) (WSC40) Permits for Waste Site Cleanup: Grants of Environmental Restriction.
1. Category: grants of Environmental Restriction.
2. Description: a Grant of Environmental Restriction implemented pursuant to 310 CMR 40.1070: Implementation and Use Limitations.
3. Schedule for timely action: for sites for which permit applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of a permit application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified technical deficiencies within 30 days of the Department's statement identifying deficiencies, if any.
d. Within 36 days from receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee, not to exceed $6,000:
a. $1,290 per Grant of Environmental Restriction.
b. The applicant(s) may apply for consolidated review of multiple applications related to a site meeting the following criteria:
i. the application includes Grants of Environmental Restriction for six or more separate parcels which comprise, in whole or in part, a single site; and
ii. each of the proposed Grants of Environmental Restriction references a single Activity and Use Limitation Opinion rendered in accordance with 310 CMR 40.1071(2)(g); and
iii. the activities and uses to be prohibited and permitted by, and the obligations and conditions listed in, the proposed Grants of Environmental Restriction are identical for each of the parcels to which the proposed Grants of Environmental Restrictions would apply.
c. For consolidated applications, the Department shall refund any portion of the permit application fees that exceed the Department's actual costs of Departmental review and approval. The Department's costs shall be calculated by applying the same method used to calculate Response Action Costs in 310 CMR 40.1220(1): Response Action Costs and the Indirect Rate set forth in 310 CMR 40.1221(2). In no event shall the fee for reviewing multiple applications for Grants of Environmental Restriction for a site be less than $1,290.
(h) (WSC41) Permits for Waste Site Cleanup: Amendments of Environmental Restriction.
1. Category: Amendments of Environmental Restrictions.
2. Description: an Amendment of a Grant of Environmental Restriction implemented pursuant to 310 CMR 40.1070: Implementation of Activity and Use Limitations.
3. Schedule for timely action: for sites for which permit applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of a permit application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified technical deficiencies within 30 days of the Department's statement identifying deficiencies, if any.
d. Within 36 days from receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee, not to exceed $6000: $1,040.
(i) (WSC42) Permits for Waste Site Cleanup: Releases of Environmental Restriction.
1. Category: Releases of Environmental Restriction.
2. Description: a Release of a Grant of Environmental Restriction implemented pursuant to 310 CMR 40.1070: Implementation of Activity and Use Limitations.
3. Schedule for timely action: for sites for which permit applications are filed and fees received on or after March 24, 2017,
a. Within 24 days of receipt of a permit application and payment of the permit application fee, the Department shall complete an administrative completeness review.
b. Within 48 days of making a determination of administrative completeness, the Department shall complete a technical review.
c. The permit applicant may remedy identified technical deficiencies within 30 days of the Department's statement identifying deficiencies, if any.
d. Within 36 days from receipt of materials from the applicant in response to the Department's statement identifying deficiencies, the Department shall complete a supplemental technical review.
4. Permit application fee, not to exceed $6000: $795.
(j) (BWSC50) Permits for Waste Site Cleanup: Special Project Designation.
1. Category: Special Project Designation.
2. Description: project containing one or more properties, sites or portions of sites pursuant to 310 CMR 40.0060: Special Project Designation Permits.
3. Schedule for timely action: for projects for which applications are filed and fees received on or after March 24, 2017,
a. Within 36 days of receipt of a complete application and payment of the permit application fee, pursuant to 310 CMR 40.0070(2): Commencement of Schedule, the Special Project designation permit is presumptively approved unless the Department approves the permit with conditions, denies the permit, or issues a notice of extended review pursuant to 310 CMR 40.0070(3)(c), extending the permit review a second 36 days or the permit review schedule is extended by written agreement.
b. Within 36 days of issuing a notice of extended review pursuant to 310 CMR 4.10(10)(j)3.a., the permit is presumptively approved unless the Department approves the permit with conditions, denies the permit, or the permit review schedule is extended by written agreement.
4. Permit application fee: $920.
(11) Environmental Results Program
(b) (ERP02) Permits for Dental Mercury Amalgam Recycling.
1. Category: certification of Dental Mercury Amalgam Collection and Recycling.
2. Description: certification of dental facilities and practices subject to collection and recycling dental mercury amalgam pursuant to 310 CMR 70.00: Environmental Results Program Certification and 73.00: Amalgam Wastewater and Recycling Regulations for Dental Facilities, but excluding dental facilities and practices filing one-time certifications pursuant to 310 CMR 73.03(1) to establish their exemption from the provisions of 310 CMR 70.00: Environmental Results Program Certification and 73.00: Amalgam Wastewater and Recycling Regulations for Dental Facilities or who hold five year certifications that will expire in a fiscal year following the fiscal year of the two year certification due date.
3. Schedule for timely action: for projects for which application is filed and fee received on or after March 24, 2017;
a. Within 48 days of receipt of an application and payment of the application fee, the Department shall complete an administrative and technical review;
b. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies; if any
c. Within 48 days of receipt of materials in response to the Department's statement identifying deficiencies, the Department shall complete a final review.
4. Permit application fee: $200.
(d) (ERP04) Permits for Mercury-added Product Collection and Recycling Programs
1. Category: certification of Mercury-added Product Collection and Recycling Programs.
2. Description: certification of mercury-added product manufacturer product collection and recycling program subject to product collection and recycling requirements pursuant to 310 CMR 70.00: Environmental Results Program Certification and 75.04(9): Annual Compliance Certification.
3. Schedule for timely action: for projects for which application is filed and fees received on or after March 24, 2017,
a. Within 60 days of receipt of an application and payment of the application fee, the Department shall complete an administrative and technical review.
b. The permit applicant may remedy identified deficiencies within 90 days of the Department's statement identifying deficiencies, if any,
c. Within 60 days of receipt of materials in response to the Department's statement identifying deficiencies, the Department shall complete a final review.
4. Permit application fee: $160.

Notes

310 CMR 4.10
Amended by Mass Register Issue 1263, eff. 6/20/2014. Amended by Mass Register Issue 1321, eff. 9/9/2016. Amended by Mass Register Issue 1335, eff. 3/24/2017. Amended by Mass Register Issue 1388, eff. 4/5/2019. Amended by Mass Register Issue 1416, eff. 5/1/2020.

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.