945 CMR 2.09 - Reporting Requirements
(1)
Summary Report. An awarding authority shall submit to
the Office of the Inspector General a summary report on the CM at Risk project
within 70 days from completion of the building project or termination of the
contractor on the CM at Risk building project.
(2) The summary report shall be completed in
a form prescribed by the Inspector General's Office.
(3) The summary report shall be a public
record.