945 CMR 2.09 - Reporting Requirements

(1) Summary Report. An awarding authority shall submit to the Office of the Inspector General a summary report on the CM at Risk project within 70 days from completion of the building project or termination of the contractor on the CM at Risk building project.
(2) The summary report shall be completed in a form prescribed by the Inspector General's Office.
(3) The summary report shall be a public record.

Notes

945 CMR 2.09

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.