Minn. R. 7850.1600 - JOINT PROCEEDING

The proposer of a large electric power generating plant that will also require a high voltage transmission line may elect to apply for both a site permit for the large electric power generating plant and a route permit for the high voltage transmission line in one application and in one process. The PUC on its own volition may elect to combine two pending applications if it is appropriate to consider both projects as part of one proceeding. An applicant may also combine an application for a pipeline routing permit if a natural gas or petroleum pipeline to a new large electric power generating facility will be required.

Notes

Minn. R. 7850.1600
27 SR 1295; L 2005 c 97 art 3 s 19

Statutory Authority: MS s 116C.66; 216E.16

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.