Minn. R. 7850.2000 - APPLICATION REVIEW

Subpart 1. Review by commission.

Within ten working days of receipt of an application for a site permit or a route permit, the commission shall determine whether the application is complete and notify the applicant in writing of the acceptance or rejection of the application. If the commission rejects an application, the commission shall advise the applicant of the deficiencies in the application.

Subp. 2. Resubmission of rejected application.

If the commission should reject an application, an applicant may decide to address the deficiencies identified by the commission and resubmit the application with additional information. In this event, the commission shall again review the application within ten days and determine whether the application is complete and advise the applicant of the commission's determination.

Subp. 3. Reasons for rejection.

The commission shall not reject an application if the information that is missing can be obtained from the applicant within 60 days from the date of the application and the lack of the information will not interfere with the public's ability to review the proposed project.

Subp. 4. Schedule.

The date of the commission's determination that an application is complete marks the start of the schedule for the commission to make a final decision on a permit application.

Notes

Minn. R. 7850.2000
27 SR 1295; L 2005 c 97 art 3 s 19

Statutory Authority: MS s 116C.66; 216E.16