Subpart
1.
General.
Each licensed asbestos contractor must notify the
commissioner of each project to be performed in whole or in part by the
licensed asbestos contractor.
Subp.
2.
Requirements for notice.
At least five calendar days before the beginning of a
project, except as provided in part 4620.3420, the commissioner must receive
from the licensed asbestos contractor:
A. a completed notice on a form provided by
the commissioner which seeks only information the commissioner reasonably
considers necessary to inspect the project and issue the permit; and
B. the permit fee for the project as
determined under part 4620.3430.
Subp. 3.
Notice of abatement
schedule.
The commissioner must be notified in advance of the dates and
work shift times for abatement.
A. If
a project will occur in two or more phases between the project start and end
dates specified on the notice, the commissioner must receive a written schedule
of abatement dates and work shift times from the licensed asbestos contractor
performing abatement at least five calendar days before beginning the
project.
B. For a project described
in part 4620.3100, subpart 27b, item B or C, if the licensed asbestos
contractor performing abatement cannot reasonably determine the schedule for
abatement at the time of notice, the licensed asbestos contractor performing
abatement must also submit written notice to the commissioner of abatement
dates and work shift times for each portion of the project which exceeds three
linear feet or three square feet of asbestos-containing material, so that the
commissioner receives the notice as soon as possible before that portion of the
project begins.
C. The asbestos
contractor performing abatement must ensure that at least one site supervisor
is present at the project site on the dates and during the work shifts for
which the commissioner has been notified.
D. The asbestos contractor performing
abatement must ensure that abatement is performed only during dates and work
shifts for which the commissioner has been notified.
Notes
Minn. R. agency 144, ch. 4620, ASBESTOS ABATEMENT, pt. 4620.3410
20 SR 2765; 33 SR
739
Statutory Authority: MS s
144.05;
326.70 to
326.81