Minn. R. agency 144, ch. 4620, ASBESTOS ABATEMENT, pt. 4620.3410 - ASBESTOS-RELATED WORK PROJECT NOTICE

Subpart 1. General.

Each licensed asbestos contractor must notify the commissioner of each project to be performed in whole or in part by the licensed asbestos contractor.

Subp. 2. Requirements for notice.

At least five calendar days before the beginning of a project, except as provided in part 4620.3420, the commissioner must receive from the licensed asbestos contractor:

A. a completed notice on a form provided by the commissioner which seeks only information the commissioner reasonably considers necessary to inspect the project and issue the permit; and
B. the permit fee for the project as determined under part 4620.3430.
Subp. 3. Notice of abatement schedule.

The commissioner must be notified in advance of the dates and work shift times for abatement.

A. If a project will occur in two or more phases between the project start and end dates specified on the notice, the commissioner must receive a written schedule of abatement dates and work shift times from the licensed asbestos contractor performing abatement at least five calendar days before beginning the project.
B. For a project described in part 4620.3100, subpart 27b, item B or C, if the licensed asbestos contractor performing abatement cannot reasonably determine the schedule for abatement at the time of notice, the licensed asbestos contractor performing abatement must also submit written notice to the commissioner of abatement dates and work shift times for each portion of the project which exceeds three linear feet or three square feet of asbestos-containing material, so that the commissioner receives the notice as soon as possible before that portion of the project begins.
C. The asbestos contractor performing abatement must ensure that at least one site supervisor is present at the project site on the dates and during the work shifts for which the commissioner has been notified.
D. The asbestos contractor performing abatement must ensure that abatement is performed only during dates and work shifts for which the commissioner has been notified.

Notes

Minn. R. agency 144, ch. 4620, ASBESTOS ABATEMENT, pt. 4620.3410
20 SR 2765; 33 SR 739

Statutory Authority: MS s 144.05; 326.70 to 326.81

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.