12 Miss. Code. R. 3-20-700.17 - PROGRESS MEETINGS
The Bureau will schedule regular Progress meetings at the time of the Pre-construction Conference where the Owner's Project Manager, Professional and his Consultants, and Subcontractors pertinent to the agenda will attend. The Contractor will prepare the agenda to include:
1. Review, approve minutes of the previous
meeting
2. Review work progress
since last meeting
3. Note field
observations, problems and decisions
4. Identify problems which impede planner
progress
5. Review off-site
fabrication problems
6. Revise
construction schedule as indicated
7. Plan progress during the next work
period
8. Review proposed
changes
9. Complete other current
business
10. Review application for
payment submitted by the Contractor