15 Miss. Code. R. 18-77-5.5.18 - Distribution of Effluent [Chamber Systems]
1. When a
change in elevation of the chamber system is required, a distribution box,
connecting lateral or crossover must be used. At the point where a crossover
line leaves a lateral, the trench for the crossover line shall be dug no deeper
than the top of the endplate inlet or the inlet in the top of the chamber in
the preceding trench so that an undisturbed block of earth will remain in place
for the full depth of the system. The invert of the crossover must be at least
four inches lower than the invert of the septic tank outlet line.
2. Distribution boxes may be used to connect
the effluent line to the effluent distribution lines. The distribution box
shall be level and supply all lines equally. Field lines (chambers) must be
equal lengths when served by one distribution box. Non-perforated rigid pipe
shall exit the distribution box for a minimum of five feet at level grade
before the effluent distribution line begins.