PURPOSE: This rule addresses the application
requirement, issuing of permits and installation inspections for the repair,
replacement or new installation of objects that are subject to the Act and
these rules.
(2) Effective January 1, 2007 an installation
permit shall be obtained by the installer from the Division of Fire Safety,
Boiler and Pressure Vessel Unit before the start of work for each new, second
hand or reinstalled boiler, water heater or pressure vessel. Replacement or
relocation of an existing boiler, water heater or pressure vessel shall be
permitted as a new installation. The requirement to obtain an installation
permit prior to the start of work is waived for an emergency replacement upon
notification to the chief inspector.
(3) An application for an installation permit
shall be submitted to the chief inspector on forms provided by the Division of
Fire Safety, Boiler and Pressure Vessel Unit at least sixty (60) days prior to
the start of the installation.
(A) In the case
of an emergency replacement, the application shall be submitted to the chief
inspector as soon as possible but not more than seven (7) calendar days after
the work has started.
(B)
Installation permits for multiple boilers, water heaters or pressure vessels
may be requested on a single application provided they are all located at the
same installation site. In such cases separate installation permits will be
issued and fees will be charged for each permit.
(C) Upon review of the installation permit,
the chief inspector may require a plan review prior to issuing an installation
permit. A separate fee of thirty-five dollars ($35) per hour not to exceed five
hundred dollars ($500) total will be charged for the plan review.
(D) Upon completion of the review process and
payment of the required fees an installation permit will be issued. The
installer shall maintain a legible copy of the installation permit at the
installation site.
(4)
Fees.
|
(A) Plan Review Hourly Fee
|
$ 35
|
|
(B) Installation Permit Fees-
1. Hot Water Heating Boiler-
|
|
|
A. 400,000 BTUH and less
|
$ 70
|
|
B. Greater than 400,000 BTUH but less than
12,500,000 BTUH
|
$175
|
|
C. 12,500,000 BTUH and above
|
$245
|
|
2. Hot Water Supply Boilers, Circulating Water
Heaters, and Pool Heaters-
|
|
|
A. 400,000 BTUH and less
|
$ 70
|
|
B. Greater than 400,000 BTUH but less than
12,500,000 BTUH
|
$175
|
|
C. 12,500,000 BTUH and above
|
$245
|
|
3. Fired Jacketed Steam Kettles
|
$ 70
|
|
4. Power Boilers-
|
|
|
A. 400,000 BTUH and less
|
$ 70
|
|
B. Greater than 400,000 BTUH but less than
12,500,000 BTUH
|
$175
|
|
C. 12,500,000 BTUH and above
|
$245
|
|
5. Pressure Vessel-
|
|
|
A. 1,000 cu.ft. (7,500 gallons) or
less
|
$ 70
|
|
B. Greater than 1,000 cu. ft.
|
$175
|
|
C. Compressed air receivers including tank mounted
air compressors designed to operate at 250 psi or less and having a volume of
250 gallons or less
|
$ 25
|
|
D. Carbon Dioxide Storage Vessels used solely for
carbonated beverage systems
|
$ 25
|
|
6. Steam Heating Boilers-
|
|
|
A. 400,000 BTUH or less
|
$ 70
|
|
B. Above 400,000 BTUH but less than 12,500,000
BTUH
|
$175
|
|
C. 12,500,000 BTUH and above
|
$245
|
|
7. Fired Storage Water Heaters (Above 200,000 BTUH
or 120 gallons)
|
$ 70
|
(5)
Upon completion of an installation, the chief inspector or a deputy inspector
shall perform a certificate inspection. After correcting any deficiencies noted
during the certificate inspection and payment of the required fees, the chief
inspector will issue an Inspection Certificate.
(A) The Special Inspectors shall perform a
certificate inspection, with an Approved Installation Permit from the Chief
Inspector, on all boilers and pressure vessels insured by their respective
companies, and, when so inspected, the owners and users of the boilers and
pressure vessels shall be exempt from the payment to the state of the
inspection fees provided for in section 650.275, RSMo. All pressure vessels in
which steam is generated by the application of heat resulting from the
combustion of fuel (solid, liquid, or gaseous) or electrical energy for use
external to itself shall be classified as a fired steam boiler.
(6) Any boiler, water heater or
pressure vessel installed on or after January 1, 2007 without obtaining the
required permit shall obtain an installation permit and correct any
deficiencies identified during the certificate inspection before an Inspection
Certificate can be issued. If additional inspections are required to confirm
the adequacy of the required corrective actions the applicable inspection fees
will be charged.
Notes
11 CSR 40-2.025
AUTHORITY:
section 650.215, RSMo 2000.* Original
rule filed March 23, 2006, effective Dec. 30, 2006. Emergency amendment filed
Dec. 22, 2008, effective Jan. 1, 2009, expired June 29, 2009. Amended: Filed
Dec. 22, 2008, effective June 30, 2009.
AUTHORITY: section
650.215, RSMo 2000.* Original
rule filed March 23, 2006, effective Dec. 30, 2006. Emergency amendment filed
Dec. 22, 2008, effective Jan. 1, 2009, expired June 29, 2009. Amended: Filed
Dec. 22, 2008, effective June 30, 2009.