Nev. Admin. Code § 439A.305 - Letter of intent: General requirements

1. Any person who intends to initiate a project that may be subject to review pursuant to NRS 439A.100 shall, before incurring a capital expenditure for the project, submit to the Department a letter of intent.
2. A letter of intent must be submitted on and include the information required by the form prescribed for this purpose by the Department or must include:
(a) The identity of the applicant;
(b) The proposed location of the project;
(c) A description of the proposed project which identifies any facility, medical equipment or health service to be included;
(d) The estimated date of completion of the proposed project, including a summary and schedule of anticipated future phases of construction within the proposed project;
(e) The total estimated costs of the project, including:
(1) The total estimated capital expenditures;
(2) All other costs of the project, including, without limitation, the cost for:
(I) The development of the site;
(II) A contingency plan for an amount which must be at least 10 percent of the total cost of the project;
(III) Architecture and engineering;
(IV) Furniture, fixtures and equipment; and
(V) Major medical equipment; and
(3) The portion of estimated capital expenditures which is related to new construction; and
(f) A copy of a written estimate of the cost of construction of the proposed project, by major cost categories, from an architect or contractor.
3. The Department will determine, pursuant to NAC 439A.315, whether a proposed project is subject to review.

Notes

Nev. Admin. Code § 439A.305
Added to NAC by Dep't of Human Resources, eff. 9-4-84; A 3-6-86; 11-10-87; 1-2-90; 10-14-97

NRS 439A.081, 439A.100

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.