Nev. Admin. Code § 439A.305 - Letter of intent: General requirements
1. Any person
who intends to initiate a project that may be subject to review pursuant to
NRS
439A.100 shall, before incurring a capital
expenditure for the project, submit to the Department a letter of
intent.
2. A letter of intent must
be submitted on and include the information required by the form prescribed for
this purpose by the Department or must include:
(a) The identity of the applicant;
(b) The proposed location of the
project;
(c) A description of the
proposed project which identifies any facility, medical equipment or health
service to be included;
(d) The
estimated date of completion of the proposed project, including a summary and
schedule of anticipated future phases of construction within the proposed
project;
(e) The total estimated
costs of the project, including:
(1) The total
estimated capital expenditures;
(2)
All other costs of the project, including, without limitation, the cost for:
(I) The development of the site;
(II) A contingency plan for an amount which
must be at least 10 percent of the total cost of the project;
(III) Architecture and engineering;
(IV) Furniture, fixtures and equipment;
and
(V) Major medical equipment;
and
(3) The portion of
estimated capital expenditures which is related to new construction;
and
(f) A copy of a
written estimate of the cost of construction of the proposed project, by major
cost categories, from an architect or contractor.
3. The Department will determine, pursuant to
NAC 439A.315, whether a proposed project is subject to review.
Notes
NRS 439A.081, 439A.100