Nev. Admin. Code § 449.Sec. 6.2 - NEW
1.
Except as otherwise provided in subsection 2, before any construction of a new
facility for hospice care or remodeling of an existing facility for hospice
care commences, the facility must submit two complete sets of the building
plans for the construction or remodeling, as applicable, to:
(a) The entity designated by the Division to
review such plans in the manner prescribed by NAC
449.0115, regardless of whether
the facility is applying for a license or the renewal of a license. The review
by that entity is only advisory, and approval by that entity does not
constitute the approval of the construction or remodeling by the
Bureau.
(b) The Division. The
facility shall not commence the construction or remodeling, as applicable,
until the plans have been approved by the Division.
2. The provisions of subsection 1 do not
apply to the remodeling of an existing facility for hospice care if the
remodeling is limited to refurbishing an area within the facility including,
without limitation, painting the area, replacing flooring in the area,
repairing windows in the area or replacing window and wall coverings in the
area.
3. The Division shall not
issue a license to operate a newly constructed facility for hospice care until
the Bureau has approved the construction. The Bureau shall not approve the
construction without conducting a survey at the site of the facility. Such a
survey must occur after the construction has been completed.
Notes
NRS 439.200, 449.0302