N.J. Admin. Code § 5:23-2.17 - Demolition or removal of structures; abandoned wells
(a) Service
connections: Before a structure can be demolished or removed, the owner or
agent shall notify all utilities having service connections within the
structure, such as water, electric, gas, sewer and other connections. A permit
to demolish or remove a structure shall not be issued until releases are
obtained from all utilities that provided service to the property, stating that
their respective service connections and appurtenant equipment, such as meters
and regulators, have been removed or sealed or plugged in a safe
manner.
(b) Abandoned wells:
1. In the event that there is a well on the
property that has been abandoned, or that will be abandoned in conjunction with
the proposed demolition, a permit to demolish or remove a structure on that
property shall not be issued until a certification has been obtained from a
well driller licensed by the Department of Environmental Protection indicating
that the well has been sealed in accordance with N.J.A.C. 7:9-9. If such
certification is not presented within 15 days of the application for the
permit, the construction official shall give notice of the absence of such
certification to the Bureau of Water Allocation, Department of Environmental
Protection, PO Box 029, Trenton, NJ 08625-0029.
2. Notice shall also be given by the
construction official to the Bureau of Water Allocation in the event of any
demolition activity found to have been undertaken without a permit at a
building or premises currently or previously served by a well and in any other
case in which no permit application for demolition has been made but the
construction official becomes aware that a well has been, or is about to be,
abandoned without having been sealed by a licensed well driller.
(c) Notice to adjoining owners:
Only when written notice has been given by the applicant to the owners of
adjoining lots and to the owners of wired or other facilities, of which the
temporary removal may be necessitated by the proposed work, shall a permit be
granted for the demolition or removal of a building or structure.
(d) Lot regulation: Whenever a structure is
demolished or removed, the premises shall be maintained free from all unsafe or
hazardous conditions by the proper regulation of the lot, restoration of
established grades and the erection of the necessary retaining walls and fences
in accordance with the provisions of the appropriate subcodes.
(e) Asbestos abatement: Before a structure
can be demolished or removed, the owner or agent shall document that the
requirements of USEPA 40 CFR 61 subpart M have been or shall be met. A permit
to demolish or remove the structure shall not be issued until the owner or
agent notifies the enforcing agency that all friable asbestos or
asbestos-containing material that will become friable during demolition or
removal has been or will be properly abated prior to demolition.
Notes
See: 24 N.J.R. 1422(a), 25 N.J.R. 2519(b).
Amended by R.1993 d.420, effective
See: 25 N.J.R. 2158(a), 25 N.J.R. 4072(a).
Amended by R.1997 d.409, effective
See: 29 N.J.R. 2736(a), 29 N.J.R. 4281(a).
Amended by R.1998 d.36, effective
See: 29 N.J.R. 4214(a), 30 N.J.R. 193(a).
Added (b); and recodified existing (b) through (d) as (c) through (e).