N.J. Admin. Code § 7:14A-22.20 - Activities which do not require an exemption from the Department
(a) Any project
which has proceeded in accordance with a valid stage II and stage III treatment
works approval from the Department for the construction and operation of
treatment works will not require a sewer ban exemption from the Department
provided that construction of the facilities is undertaken in accordance with
the Department's approval.
(b) For
projects which do not require a treatment works approval pursuant to
7:14A-22.4, a sewer ban exemption
from the Department is not required provided that the owner/applicant of the
project has obtained a building permit prior to the effective date of the sewer
connection ban, and is otherwise lawfully entitled to initiate construction in
conformance with previously issued valid approvals.
(c) Modifications, additions or deletions to
the internal plumbing or piping of any lawfully, pre-existing building will not
require a sewer ban exemption provided that:
1. The size of the building will not increase
(gross area); and
2. The category
and scope of use of the building will remain unchanged in accordance with
7:14A-23.3, Projected flow
criteria.
(d) The
replacement, rehabilitation or modification of existing conveyance and
treatment facilities will not require a sewer ban exemption provided that the
project does not involve any additional contributory flow, as determined by the
Department.