N.J. Admin. Code § 7:14A-22.21 - Application procedures for obtaining a sewer connection ban exemption from the Department
(a) The sewerage
authority or municipality imposing the ban shall provide the applicant with the
following:
1. A copy of the ban exemption
regulations contained in N.J.A.C. 7:14-22.18 through 22.22;
2. The Department's ban exemption application
form, WFR001, entitled: "Application for Exemption from a Sewer Connection
Ban";
3. The effective date of the sewer
connection ban; and
4. A copy of the
authority's sewer ban exemption criteria.
(b) An applicant requesting an exemption shall
submit the Department's application form for an exemption from a sewer connection
ban and any other appropriate documentation to the appropriate sewerage authority or
municipality, who shall review the request for compliance with the applicable
criteria.
(c) If the affected sewerage
authority or municipality determines that the applicant meets the criteria specified
in 7:14A-22.22, or more stringent criteria
that may be locally adopted, the authority shall forward the application package and
a written letter of consent, to the Department for a final decision, unless the
local authority has been delegated the authority to approve exemption requests
pursuant to 7:14A-22.23.
(d) If the sewerage authority or municipality
denies the sewer ban exemption request, that decision cannot be appealed to the
Department.
(e) After reviewing the
application for a sewer connection ban exemption, the Department will notify the
affected sewerage authority of the results of its review.
(f) Before making a decision, the Department may
request that the applicant supply additional documentation. If the additional
requested information is not supplied, the Department may deny the exemption
request.
(g) The granting of an
exemption by the Department and the affected sewerage authority does not relieve the
applicant of the responsibility to comply with all other State and local
requirements, including compliance with the appropriate water quality management
plan requirements and obtaining a treatment works approval from the Department, if
required.