N.J. Admin. Code § 7:14A-4.2 - Application requirements
(a) Any person who is
engaged in an activity or proposes to commence an activity that requires an
individual NJPDES permit pursuant to N.J.A.C. 7:14A-2 shall submit a complete
application to the Department in accordance with this subchapter. Any person wishing
to be authorized under a general permit shall comply with the application
requirements in the applicable general permit. The application forms can be obtained
by writing to the address cited in (b) below, or from the Department's web site,
http://www.state.nj.us/dep/dwq/.
(b) Once an applicant has complied with
7:14A-4.3(a)13,
requiring submittal of the application to the local agency or sewerage entity and
municipality, the applicant shall submit two copies of all NJPDES permit
applications to:
New Jersey Department of Environmental Protection
Bureau of Permit Management
Division of Water Quality
PO Box 029
Trenton, NJ 08625-0029
Attn: Administrative Review Unit
(c) It is the duty of any person who is or will be
an operating entity for any part of a facility which includes a discharge or
activity regulated pursuant to this chapter to obtain a NJPDES permit. When a
facility or activity is owned by one or more persons, but is currently operated by
another person, it is the operating entity's duty to obtain a NJPDES permit.
However, the property owner (record owner of fee title interest) shall sign the
"Property Owner's Certification" in the NJPDES-1 Form for all DGW permits.
(d) Whenever pursuant to (c) above, more than one
person is required to obtain an individual NJPDES permit for one or more discharges
or activities at a specific site, the Department may issue a single permit and may
list all of these persons as permittees. Such a permit may identify permit
conditions that apply to one or more of those permittees.
(e) The schedule for submission of applications
(or requests for authorization under a general permit) is as follows:
1. Any person proposing a new facility or
activity, which requires a NJPDES permit pursuant to
7:14A-2.4 and is not exempt pursuant to
7:14A-2.5, shall submit an application
at least 180 days before the date on which the activity is proposed to commence,
unless an alternative date has been established by the Department. The schedule for
submitting an application for certain stormwater discharges is set forth in
7:14A-24.4 and 25.4.
2. For general permits, alternate dates for
submitting requests for authorization may be specified under the terms of the
applicable general permits.
3. Any
person planning to continue discharging after the expiration date of an existing
NJPDES permit shall file an application for renewal or a request for authorization
under a general permit at least 180 calendar days prior to the expiration of the
existing permit, unless:
i. Otherwise required
under (e)4 below;
ii. The existing
permit is a general permit that provides for automatic renewal of authorization when
that general permit is renewed (see
7:14A-6.13(d)9 ) , or
that provides for retroactive renewal of authorization after a new request for
authorization is submitted or granted under the renewed general permit; or
iii. The existing permit is an individual permit
where:
(1) The permittee has been notified by the
Department prior to submitting a renewal application pursuant to
7:14A-2.7 that the permit qualifies for
expedited permit renewal under
7:14A-16.3(h), and
elects to participate; or
(2) The
permittee has a stormwater only permit and is approved by the Department for
expedited permit renewal.
4.
(Reserved)
5.
If the Department revokes the industrial pretreatment program of a delegated local
agency, the Department will notify each affected facility or activity that
discharges under that industrial pretreatment program of the deadline for submitting
an application for an individual NJPDES-SIU permit from the Department.
6. All existing facilities or activities which
require an individual NJPDES-SIU permit due to promulgation of new Categorical
Pretreatment Standards under
40 CFR
403.6 and 40 CFR Chapter I, Subpart N, will be
notified of the application date by the Department following submittal of the
Baseline Report, as required pursuant to
40 CFR
403.12(b). See also
7:14A-21.3(b).
(f) The Department shall not issue a
draft permit for an individual NJPDES permit before receiving a complete permit
application, in accordance with
7:14A-15.4.
Notes
See: 29 N.J.R. 3822(a).
Amended N.J.A.C. references.
Amended by R.2004 d.47, effective
See: 35 N.J.R. 169(a), 35 N.J.R. 1331(a), 36 N.J.R. 813(a).
Rewrote (e)1.
Amended by R.2009 d.7, effective
See: 40 N.J.R. 1478(a), 41 N.J.R. 142(a).
In (a), inserted the last sentence; and rewrote (e)5.
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.