N.D. Admin Code 69-05.2-21-06 - Performance standards - Backfilling and grading - Slope measurements
1. The permittee
shall submit a postmining contour map to the commission for approval before
spreading suitable plant growth materials. Along with the contour map, the
permittee shall specify the thickness of topsoil and subsoil to be respread
over the graded area.
2. The
commission will approve or disapprove the postmining topography within thirty
days and notify the permittee in writing of the decision along with reasons for
any disapproval.
Notes
General Authority: NDCC 38-14.1-03
Law Implemented: NDCC 38-14.1-24