1. The postmining
land use must be compared to those uses the land previously supported under
proper management unless the land has been previously mined and not reclaimed.
2. The postmining land use for
land that has been previously mined and not reclaimed must be judged on the
basis of the land use that existed prior to any mining. However, if the land
cannot be reclaimed to the land use that existed prior to any mining because of
the previously mined condition, the postmining land use must be judged on the
basis of the highest and best use that can be achieved which is compatible with
surrounding areas and does not require the disturbance of areas previously
unaffected by mining.
3. If the
premining use of the land was changed within five years of beginning of mining,
the comparison of postmining use to premining use must also include the
historic use of the land preceding mining.
Notes
General Authority: NDCC 38-14.1-08, 38-14.1-24
Law Implemented: NDCC 38-14.1-24
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.