Or. Admin. R. 345-015-0160 - Project Order
(1)
Following the review of a notice of intent or, in the case of an expedited
review, following receipt of a preliminary application for a site certificate,
the Department of Energy shall issue a project order to the applicant
establishing the following:
(a) All state
statutes and administrative rules containing standards or criteria that must be
met for the Council to issue a site certificate for the proposed facility,
including applicable standards of divisions 22, 23 and 24 of this
chapter.
(b) All local government
ordinances applicable to the Council's decision on the proposed
facility.
(c) All application
requirements in OAR 345-021-0010 applicable to the proposed facility.
(d) All state and local permits necessary to
the construction and operation of the proposed facility and the name of each
agency with the authority to issue such permits.
(e) Any other data and information that must
be included in the application for a site certificate to allow the Council to
determine whether the proposed facility will comply with applicable statutes,
administrative rules and local government ordinances.
(f) The analysis area(s) for the proposed
facility.
(g) Public concerns that
address matters within the jurisdiction of the Council that the applicant shall
consider and discuss in the application for a site certificate, based on
comments the Department has received in writing or at any informational meeting
held under OAR 345-015-0130.
(h) If
the applicant has identified one or more proposed corridors in Exhibit D of the
notice of intent as required by OAR 345-020-0011(1)(d), any adjustments to the
corridor(s) that the applicant shall evaluate in the corridor selection
assessment described in 345-021-0010(1)(b).
(i) If the applicant chooses to demonstrate
need for a proposed electric transmission line, natural gas pipeline, or
liquefied natural gas storage facility under the economically reasonable rules,
OAR 345-023-0030 and 345-023-0040, any alternatives to construction and
operation of the proposed facility that the applicant must evaluate in the
application in addition to the alternatives described in 345-021-0010(1)(n)(F)
or (G).
(j) Except in the case of
an expedited review granted under OAR 345-015-0300 or 345-015-0310, the
expiration date of the notice of intent, according to
345-020-0060(1).
(2) In
determining the application and study requirements to be included in the
project order, the Department shall consider the size and type of proposed
facility and significant potential impacts of the proposed facility.
(3) The Council or the Department may amend
the project order at any time.
(4)
The project order is not a final order.
(5) Except in the case of an expedited review
granted under OAR 345-015-0300 or 345-015-0310, the Department shall, to the
extent practicable, issue the project order within 140 days following the date
of submission of the notice of intent.
Notes
Statutory/Other Authority: ORS 469.373 & ORS 469.470
Statutes/Other Implemented: ORS 469.330 & ORS 469.370