Or. Admin. R. 734-010-0460 - Final Inspection

(1) Notification of Completion; inspection. The Contractor shall notify ODOT in Writing when the Contractor considers the on-site Contract Work completed. Within 15 Days of receiving the Contractor's notice, ODOT will inspect the project and project records, and will either accept the Work or notify the Contractor of remaining Work to be performed.
(2) Acknowledgment of acceptance. When ODOT finds that all Work required under the Contract, both on-site and administrative, has been completed satisfactorily, ODOT shall acknowledge acceptance of the Work in Writing.

Notes

Or. Admin. R. 734-010-0460
Renumbered from 731-007-0320 by DOT 1-2022, filed 1/13/2022, effective 1/13/2022

Statutory/Other Authority: ORS 184.616, 184.619, 279A.050, 279A.065

Statutes/Other Implemented: ORS 279C.570

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.