Or. Admin. R. 839-025-0033 - Posting Requirements
(1) Every
contractor or subcontractor must post the prevailing wage rates applicable to
the project in a conspicuous place at the site of work. The posting must be
easily accessible to employees working on the project. Contractors may obtain a
copy of the applicable wage rates by contacting the Prevailing Wage Rate Unit
or any office of the bureau.
(2)
When a contractor or subcontractor provides for or contributes to a health and
welfare plan or pension plan for employees who are working on a public works
project, the contractor or subcontractor must post a notice containing the
following information:
(a) A description of
the plan or plans;
(b) Information
on how and where claims can be made; and
(c) Where to obtain more
information.
(3) The
notice required to be posted in section (2) of this rule must be posted in a
conspicuous place at the site of work and be easily accessible to employees
working on the project. The notice must be posted in the same location as the
prevailing wage rate pursuant to section (1) of this rule.